SHANKHESHWAR PUSHP

By SHREE SHANKHESHWAR ENTERPRISES

RG-MH-23762 · RERA P51700079074 · Last updated on MahaRERA portal: 9 Apr 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 2 earlier projects delivered on promise

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 2 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Mar 2027Possession promisedno revision filed
4 of 11Construction stages donefurthest along: External plumbing and external plaster, 90%
43 of 46Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 51 documents Report an error

SHANKHESHWAR PUSHP is a Residential / Group Housing project by SHREE SHANKHESHWAR ENTERPRISES in Thane, Maharashtra, registered with MahaRERA as P51700079074 on 3 Feb 2025. Possession is promised by 31 Mar 2027. 3 of the 46 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.

At a glance

Project

  • NameSHANKHESHWAR PUSHP
  • TypeResidential / Group Housing
  • Location
    • Behind R B T School
    • Shankheshwar Road
    • Khambalpada
    • Kalyan-Dombivali (M Corp.)
    • Kalyan
    • Thane
    • 421201
  • Pincode421201
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700079074
  • ReraGenie IDRG-MH-23762

Builder

  • NameSHREE SHANKHESHWAR ENTERPRISES
  • Entity typePartnership
  • PartnersKISHOR MALSI CHHEDA HUF, VASANTI KISHOR CHHEDA, LALJI SHIVJI PATEL, LALJI SHIVJI PATEL HUF, VRUSHALI KISHOR CHHEDA
  • Other registrations2 more →
  • Completed1 of 3
  • Declared earlier projects2 →

Key dates

this monthRegisteredFeb 2025PromisedMar 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on3 Feb 2025
  • Promised completion31 Mar 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed51 files

Current status

7%3 of 46 units booked
72.5%Work done, per cost certificate

Figures as on 9 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SHANKHESHWAR PUSHPNA107351146

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 9 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is External plumbing and external plaster, at 90%.

SHANKHESHWAR PUSHP: 63% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%

Progress on shared amenities15

As on 9 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes70%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed6

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots6
Closed/Covered5
Open Space1

Land and ownership15

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,103 sq m
Land owned byThe promoter, with other names on the file
Named landowners15
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on8 Jul 2025
LandownerVillageDistrict
Sadashiv Raghunath BhoirDOMBIVLIThane
Raghunath Savalaram BhoirDOMBIVLIThane
Gita Sudhakar MhaskarDOMBIVLIThane
Leena Deepak PatilDOMBIVLIThane
Jayshree Ravindra JoshiDOMBIVLIThane
Anup Prahlad BhoirDOMBIVLIThane
Vaishali Sukdev MhatreDOMBIVLIThane
Amol Prahlad BhoirDOMBIVLIThane
Mukta Namdev BhoirDOMBIVLIThane
Subhadra Vasudev MundheDOMBIVLIThane
Bhimabai Namdev MaliDOMBIVLIThane
Anusaya Dattu MhatreDOMBIVLIThane
Dnyaneshwar Raghunath BhoirDOMBIVLIThane
Gopinath Raghunath BhoirDOMBIVLIThane
Prahlad Raghunath BhoirDOMBIVLIThane

Approvals and building plan

Sanctioning authorityKalyan Dombivli Municipal Corporation
Permissible FSI1663.24
Proposed, not sanctioned1,497 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPATKAR BUILDING ,STATION ROAD OPP BUS STAND,DOMBIVLI(E)
Estimated costRs 6.50 cr
Cost incurredRs 4.71 cr
Work done72.45%
BuildingWingEstimatedIncurred
SHANKHESHWAR PUSHPNARs 5.50 crRs 4.71 cr
-NARs 1.00 cr-

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectARCHITEQN ICON P S GOKHALE
EngineerRAJESH THAKARE AND ASSOCIATES RAJESH A THAKARE
Chartered AccountantR V THAKKAR AND ASSOCIATES RAVI VITHALDAS THAKKAR
Chartered AccountantLAXMICHAND KHERAJ DEDHIA
PartnerRole in project
SHREE SHANKHESHWAR ENTERPRISES-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 16 Dec 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Nov 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Nov 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 22 Nov 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2027

Documents filed51

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 1.pdf9 Apr 2026
Withdrawal Update Form 2File: FORM 2.pdf9 Apr 2026
Withdrawal Update Form 3File: RERA FORM 3 QPR.pdf9 Apr 2026
Withdrawal Update Form 1File: 01 FORM 1 25-26 Q1.pdf2 Dec 2025
Withdrawal Update Form 2File: 02 FORM 2 25-26 Q2.pdf2 Dec 2025
Withdrawal Update Form 3File: 03 FORM 3 25-26 Q2_DG.pdf2 Dec 2025
Form 5 (FY 2024-2025)File: FORM 5 SSE_DG.pdf2 Dec 2025
Form 1File: 31 3 2025.pdf19 Nov 2025
Form 2File: FORM-2 31-03-2025.pdf19 Nov 2025
Form 3File: FORM 3_DG_compressed.pdf19 Nov 2025
Disclosure of Sold and Booked InventoryFile: INVENTORY LIST DG.pdf19 Nov 2025
Withdrawal Update Form 1File: 30 06 2025.pdf19 Nov 2025
Withdrawal Update Form 2File: FORM-2 30-06-2025.pdf19 Nov 2025
Withdrawal Update Form 3File: FORM 3_DG_compressed.pdf19 Nov 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 21-01-2025.pdf30 Jan 2025
Other - FinanceFile: Declaration cum undertaking for no sale.pdf7 Jan 2025
Copy of the legal title reportFile: Title pushp new _merged_compressed.pdf16 Dec 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A.pdf16 Dec 2024
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format B_1.pdf16 Dec 2024
Layout approvalFile: MYSCAN_20241125_0009_11zon.pdf29 Nov 2024
Details of encumbrances concerned to FinanceFile: ECUMBRANCE FINANCE.pdf29 Nov 2024
Details of encumbrances concerned to FinanceFile: EUCUMBRANCE LEGAL.pdf29 Nov 2024
Copy of Layout Approval (in case of layout)File: MYSCAN_20241125_0009_11zon.pdf29 Nov 2024
Proforma of Allotment letterFile: ALLOTMENT LETTER FINAL.pdf29 Nov 2024
Other - LegalFile: DECLARATION.pdf29 Nov 2024
CERSAI detailsFile: CERSAI.pdf29 Nov 2024
Details of encumbrances concerned to LegalFile: ECUMBRANCE FINANCE.pdf29 Nov 2024
Details of encumbrances concerned to LegalFile: EUCUMBRANCE LEGAL.pdf29 Nov 2024
Other - TechnicalFile: DECLARATION.pdf29 Nov 2024
Proforma of Agreement for saleFile: AGREEMENT FOR SALE.pdf29 Nov 2024
Building plan approvalFile: MYSCAN_20241125_0009_11zon.pdf27 Nov 2024
Building Plan Approval / NA Order for plotted developmentFile: MYSCAN_20241125_0009_11zon.pdf27 Nov 2024
Other - TechnicalFile: DECLARATION FOR PROJECT.pdf27 Nov 2024
Other - TechnicalFile: Plinth certificate .pdf27 Nov 2024
PAN CardFile: PAN CARD_FINAL.pdf22 Nov 2024
Details of encumbrances concerned to FinanceFile: LEGAL ENCUMBRANCE.pdf22 Nov 2024
Declaration in FORM BFile: FORM B PARTNER.pdf22 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf22 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf22 Nov 2024
Commencement Certificates / NA Order for plotted developmentFile: SHANKESHWAR PUSHP-COMMENCEMENT CERTIFICATE.pdf22 Nov 2024
Declaration about Commencement CertificateFile: DECLARATION ABOUT COMMENCEMENT CERTIFICATE.pdf22 Nov 2024
Deviation Report with respect to Allotment letterFile: DEVIATION - ALLOTMENT LETTER.pdf22 Nov 2024
Details of encumbrances concerned to LegalFile: LEGAL ENCUMBRANCE.pdf22 Nov 2024
Deviation Report with respect to model copy of AgreementFile: DEVIATION - AGREEMENT OF SALE.pdf22 Nov 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: VASANTI CHHEDA DECLARATION.pdf22 Nov 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: VRUSHALI DEDHIA DECLARATION.pdf22 Nov 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: KISHOR CHHEDA HUF.pdf22 Nov 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: HIREN CHHEDA - DISCLOSURE.pdf22 Nov 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: LALJI PATEL.pdf22 Nov 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: LALJI PATEL HUF.pdf22 Nov 2024
Disclosure for secured/unsecured finance availed for the projectFile: DISCLOSURE OF PROJECT FINANCE.pdf22 Nov 2024

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered on promise
ProjectLocationFlatsRegisteredStatusPromisedDelivered
SHANKHESHWAR LAKE VIEWP51700015923KHABALPADA, Thane-Apr 2018Certificate SignedDec 2022Jun 2020
shankheshwer lake viewdombivali E1-CompletedJun 2015May 2015

How this compares with Thane

7%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SHANKHESHWAR PUSHP on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Khambalpada7,600+ in Thane

2 kmSHANKHESHWAR PUSHPCompleted 36Lapsed / revoked 24Other 60Dot size: filed unitsN

Filed coordinates, straight-line distance. 120 registered projects within 2 km.

Builder: SHREE SHANKHESHWAR ENTERPRISES

SHREE SHANKHESHWAR ENTERPRISES has 3 registrations on MahaRERA, including SHANKHESHWAR LAKE VIEW and Ratan Infinia. Its filings disclose 2 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if SHANKHESHWAR PUSHP is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHANKHESHWAR PUSHP?

The registered promoter entity is SHREE SHANKHESHWAR ENTERPRISES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHANKHESHWAR PUSHP?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SHANKHESHWAR PUSHP?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHANKHESHWAR PUSHP?

The professionals named in the filing: Architect: ARCHITEQN ICON P S GOKHALE; Engineer: RAJESH THAKARE AND ASSOCIATES RAJESH A THAKARE; Chartered Accountant: R V THAKKAR AND ASSOCIATES RAVI VITHALDAS THAKKAR; Chartered Accountant: LAXMICHAND KHERAJ DEDHIA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHANKHESHWAR PUSHP?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHANKHESHWAR PUSHP. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHANKHESHWAR PUSHP to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.