Registration lapsed No litigation declared Residential / Group Housing project

SHANKESHWARAM RESIDENCY

By SUREKHA SACHIN GHULE

RG-MH-14631 · RERA P52100022946 · Last updated on MahaRERA portal: 10 Jan 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 22 months past the filed date
  • 2 complaints at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2024Possession promised22 months past this date
22 of 22Construction stages doneacross 2 buildings; every applicable stage filed complete
8 of 96Units unsoldnot recorded sold or booked
2Complaints at MahaRERAon this registration
Jump to the 121 documents Report an error

SHANKESHWARAM RESIDENCY is a Residential / Group Housing project by SUREKHA SACHIN GHULE in Pune, Maharashtra, registered with MahaRERA as P52100022946 on 5 Nov 2019. Possession was promised by 30 Dec 2024 and is now 22 months past that date. 88 of the 96 units on this registration are recorded sold or booked, and 22 of 22 construction stages are filed complete. 2 complaints are on record with the regulator.

At a glance

Project

  • NameSHANKESHWARAM RESIDENCY
  • TypeResidential / Group Housing
  • Location
    • KONDHWA BUDRUK
    • KONDHWA BUDURK
    • kondhwa BK
    • Haveli
    • Pune
    • 411048
  • Pincode411048
  • RERA no.P52100022946
  • ReraGenie IDRG-MH-14631

Builder

  • NameSUREKHA SACHIN GHULE
  • Entity typeIndividual
  • Other registrations1 more →
  • Completed1 of 2
  • No longer live1 lapsed, de-registered or revoked

Key dates

22 months past promisethis monthRegisteredNov 2019PromisedDec 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on5 Nov 2019
  • Promised completion30 Dec 2024
  • Revised completionNone
  • Buildings2 building records
  • Documents filed121 files

Current status

92%88 of 96 units booked

Figures as on 10 Jan 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A WINGNA151248048
B WINGNA151248048

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 10 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

22 of 22 construction stages are filed complete across 2 buildings.

A WING100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
B WING100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities16

As on 10 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingNoNot applicable
Watchman Cabin And Entrance GateYes100%

Parking filed288

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots288
Closed/Covered288
BuildingClosed/CoveredTotal
A WING144144
B WING144144

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,565 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityPMC
Permissible FSI6496.37
Proposed, not sanctioned1,688 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMAHADEO NAGAR MANGARI FARM MANJARI PUNE - 412307

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDilip G Kale & Associates
EngineerKIRAN MOHAN KALKUMBE
Chartered AccountantSheetal M Gadiya
Chartered AccountantAkshay Ramdas Kadam
Chartered AccountantDnyaneshwar Shelar
PartnerRole in project
SUREKHA SACHIN GHULE-

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC005000000157237Suman AnchaliaMRS. SUREKHA SACHIN GHULE16/06/2022
CC005000000147237Prakash AnchaliaSUREKHA SACHIN GHULE16/06/2022

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 17 Oct 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 26 Feb 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 26 Feb 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 26 Feb 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 21 Feb 2025

Documents filed121

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 121 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: Form 1 Dec 24 Shankeshwaram Residency.pdf10 Jan 2026
Form 2File: Form 2 Dec 24 Shankeshwaram Residency.pdf10 Jan 2026
Form 3File: Form 3 Residency Dec 24_11zon.pdf10 Jan 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Dec-24 Shankeshwaram Residency.pdf10 Jan 2026
Form 5 (FY 2024-2025)File: Form 5 FY 24-25_Shankeshwaram Residency.pdf1 Oct 2025
Disclosure of sold/ booked inventoryFile: Sold Booked Inventory Residential March 25.pdf30 Apr 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Final Form 4 Shankeshwaram Residency.pdf21 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Residency Dec 24_11zon.pdf1 Feb 2025
Architect’s Certificate on Completion of Project (Form 4)File: Final Form 4 Shankeshwaram Residency.pdf21 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Dec 24 Shankeshwaram Residency.pdf20 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Dec 24 Shankeshwaram Residency.pdf20 Jan 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold Dec-24 Shankeshwaram Residency.pdf20 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 FY 23-24_Shankeshwaram Residency_Signed.pdf9 Dec 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Full Completion Certificate Kondhwa Site Residency and Plaza.pdf8 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate June24.pdf7 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Residency Form 1 Sept 24.pdf7 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: OB- Residency Form 2 Sept 2024.pdf7 Nov 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory Residency Sept 24.pdf7 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 9 Form 1 March 24 Residency.pdf21 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 10 Form 2 March 24.pdf21 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Quality Engineer FY 23-24.pdf21 May 2024
Disclosure of sold/ booked inventoryFile: 5 Disclosure of Sold Inventory- March 24.pdf21 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 5 Form 3 March 24 Shankeshwaram Residency 11zon.pdf21 May 2024
Layout approvalFile: 1 Complete Plot Revised Layout Merged.pdf26 Feb 2024
Layout approvalFile: 2 Merged Basement Plan.pdf26 Feb 2024
Building plan approvalFile: 3 Merged A WING.pdf26 Feb 2024
Building plan approvalFile: 4 Merged B WING.pdf26 Feb 2024
Details of encumbrances concerned to FinanceFile: 7 Encumberances Details.pdf26 Feb 2024
Details of encumbrances concerned to LegalFile: 7 Encumberances Details.pdf26 Feb 2024
Copy of Layout Approval (in case of layout)File: 1 Complete Plot Revised Layout Merged.pdf26 Feb 2024
Copy of Layout Approval (in case of layout)File: 2 Merged Basement Plan.pdf26 Feb 2024
Building Plan Approval / NA Order for plotted developmentFile: 3 Merged A WING.pdf26 Feb 2024
Building Plan Approval / NA Order for plotted developmentFile: 4 Merged B WING.pdf26 Feb 2024
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate New.pdf26 Feb 2024
Declaration about Commencement CertificateFile: 6 Format D Decleration about commencement Certificate.pdf26 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Form 1 Mar 22 Resi.pdf26 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 2 Form 1 Jun 22 Resi.pdf26 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 3 Form 1 Sept 22 Resi.pdf26 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 4 Form 1 Dec 22 Resi.pdf26 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 5 Form 1 Mar 23 Resi.pdf26 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 6 Form 1 Jun 23 Resi.pdf26 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 7 Form 1 Sept 23 Resi.pdf26 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 8 Form 1 Dec 23 Resi.pdf26 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1 FORM 2 Dec 21.pdf26 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 FORM 2 Mar 22.pdf26 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 3 FORM 2 Jun 22.pdf26 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 4 FORM 2 Sept 22.pdf26 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 5 FORM 2 Dec 22.pdf26 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 6 FORM 2 Mar 23.pdf26 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 7 FORM 2 Jun 23.pdf26 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 8 FORM 2 Sept 23.pdf26 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 9 FORM 2 Dec 23.pdf26 Feb 2024
CERSAI detailsFile: 3 CERSAI Merged.pdf26 Feb 2024
Disclosure of sold/ booked inventoryFile: 1 Disclosure of Sold Inventory- Mar-23.pdf26 Feb 2024
Disclosure of sold/ booked inventoryFile: 2 Disclosure of Sold Inventory- Jun-23.pdf26 Feb 2024
Disclosure of sold/ booked inventoryFile: 3 Disclosure of Sold Inventory- Sep-23.pdf26 Feb 2024
Disclosure of sold/ booked inventoryFile: 4 Disclosure of Sold Inventory- Dec-23.pdf26 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 1 Form 3 March 23 Shankeshwaram Residency 11zon.pdf26 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 2 Form 3 June 23 Shankeshwaram Residency 11zon.pdf26 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3 Form 3 Sept 23 Shankeshwaram Residency 11zon.pdf26 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 4 Form 3 Dec 23 Shankeshwaram Residency 11zon.pdf26 Feb 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: 5 Decleration of Interest in Other Real Estate Org.pdf26 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 FY 21-22_Shankeshwaram Residency.pdf26 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 FY 22-23_Shankeshwaram Residency.pdf26 Feb 2024
Proforma of Agreement for saleFile: 2 Draft Agreement to Sales Resi.pdf26 Feb 2024
Proforma of Allotment letterFile: 1 Proforma For Allotment Letter Resi.pdf26 Feb 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: 4 Bank Account Decleration.pdf26 Feb 2024
Deviation Report with respect to Allotment letterFile: 8 Deviation Report for Allotment Letter.pdf26 Feb 2024
Deviation Report with respect to model copy of AgreementFile: 9 Deviation report for Agreement to Sales.pdf26 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 03-04-2023.pdf21 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Engineer certificate form 2A 19-20.pdf20 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Engineer certificate form 2A 20-21.pdf20 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Engineer certificate form 2A 21-22.pdf20 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Engineer certificate form 2A 22-23.pdf20 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_Residency_Q4_FY2021-22.pdf28 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_Residency_Q1_FY2022-23.pdf28 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_Residency_Q2_FY2022-23.pdf28 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_ResidencyQ3_FY2022-23.pdf28 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5- Signed.pdf10 Mar 2022
Details of encumbrancesFile: Encumberance Certificate-1QTR.pdf3 Mar 2022

How this compares with Pune

92%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SHANKESHWARAM RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KONDHWA BUDURK13,700+ in Pune

Builder: SUREKHA SACHIN GHULE

SUREKHA SACHIN GHULE has 2 registrations on MahaRERA, including SHANKESHWARAM PLAZA and SHANKESHWARAM RESIDENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that SHANKESHWARAM RESIDENCY shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if SHANKESHWARAM RESIDENCY is delayed beyond 30 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHANKESHWARAM RESIDENCY?

The registered promoter entity is SUREKHA SACHIN GHULE, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHANKESHWARAM RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SHANKESHWARAM RESIDENCY?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for SHANKESHWARAM RESIDENCY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHANKESHWARAM RESIDENCY?

The professionals named in the filing: Architect: Dilip G Kale & Associates; Engineer: KIRAN MOHAN KALKUMBE; Chartered Accountant: Sheetal M Gadiya; Chartered Accountant: Akshay Ramdas Kadam; Chartered Accountant: Dnyaneshwar Shelar. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHANKESHWARAM RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHANKESHWARAM RESIDENCY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHANKESHWARAM RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.