ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / SB Sai Sanskruti

Completed No litigation declared Residential / Group Housing project

SB Sai Sanskruti

By S B SAI ASSOCIATES

RG-MH-22570 · RERA P52100032533 · Last updated on MahaRERA portal: 9 Jun 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 36 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Oct 2027Possession promisedregistration recorded completed
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
1 of 32Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 78 documents Report an error

SB Sai Sanskruti is a Residential / Group Housing project by S B SAI ASSOCIATES in Pune, Maharashtra, registered with MahaRERA as P52100032533 on 10 Jan 2022. The registration is recorded completed; possession was promised by 31 Oct 2027. The completion date has moved by 36 months from the original filing. 31 of the 32 units on this registration are recorded sold or booked, and 10 of 11 construction stages are filed complete.

At a glance

Project

  • NameSB Sai Sanskruti
  • TypeResidential / Group Housing
  • Location
    • GAT NO.1346/1 PART
    • WAGHOLI
    • Haveli
    • Pune
    • 412207
  • Pincode412207
  • RERA no.P52100032533
  • ReraGenie IDRG-MH-22570

Builder

  • NameS B SAI ASSOCIATES
  • Entity typePartnership
  • PartnersSHYAM VENKATRAO LAKHE, SANJAY BALIRAM JADHAV

Key dates

this monthRegisteredJan 2022First promiseOct 2024Revised toOct 2027Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on10 Jan 2022
  • Promised completion31 Oct 2027
  • Revised completionRevised to 31 Oct 2027 (originally 31 Oct 2024)
  • Buildings1 building record
  • Documents filed78 files

Current status

97%31 of 32 units booked
112.6%Work done, per cost certificate

Figures as on 9 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SB Sai SanskrutiNA4432032

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 9 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

SB Sai Sanskruti: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 9 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed36

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots36
Open Space36

Land and ownership6

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,408 sq m
Land owned byThe promoter, with other names on the file
Named landowners6
LandownerVillageDistrict
Sambhaji Jaysingrao LagadMukhaiPune
Jyoti Prashant NanekarPune (M Corp.)Pune
Bhushan Prashant NanekarPune (M Corp.)Pune
Minakshi Shivajirao SakorePune (M Corp.)Pune
Dattaray Yamnappa BhandariKeshavnagar-MundwaPune
Balasaheb Yamnappa BhandariKeshavnagar-MundwaPune

Approvals and building plan

Sanctioning authorityPune Metropolitan Region Development Authority Pune
Permissible FSI3671.88
Proposed, not sanctioned1,572 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPUNE
Estimated costRs 7.50 cr
Cost incurredRs 8.44 cr
Work done112.57%
BuildingWingEstimatedIncurred
SB Sai SanskrutiNARs 7.50 crRs 8.44 cr

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectHEMANT MAHATEKKAR
EngineerNA PAVAN LAKHE
Chartered AccountantYash Nagar
PartnerRole in project
S B SAI ASSOCIATES-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100025684Oct 2024 → Oct 2027

Reason as filed by the promoterWe received permission for construction up to stilt + 4 floors as per the Commencement Certificate (23-07-2024) and Plinth Certificate (18-10-2024). Construction proceeded with a targeted completion date of 31-10-2024. Form 4 was submitted on 25-10-2024, within the required timeline, and the Occupancy Certificate was obtained on 03-10-2023. Revised permissions for construction up to the 7th floor were granted as per the approved plan dated 11-10-2024. We are now requesting an extension for the additional construction.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Nov 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Nov 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 21 Dec 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 21 Dec 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 1 Nov 2023

Documents filed78

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 2025-26 Q2.pdf9 Jun 2026
Withdrawal Update Form 2File: Form 2 2025-26 Q2..pdf9 Jun 2026
Withdrawal Update Form 3File: Form 3 2025-26 Q3.pdf9 Jun 2026
Withdrawal Update Form 1File: Form 1 2025-26 Q2.pdf18 Feb 2026
Withdrawal Update Form 2File: Form 2 2025-26 Q2..pdf18 Feb 2026
Withdrawal Update Form 3File: Form 3 2025-26 Q3.pdf18 Feb 2026
Withdrawal Update Form 1File: Form 1 2025-26 Q2.pdf16 Feb 2026
Withdrawal Update Form 2File: Form 2 2025-26 Q2..pdf16 Feb 2026
Withdrawal Update Form 3File: Form 3 2025-26 Q3.pdf16 Feb 2026
Form 1File: Form 1 2024-25 Q1.pdf25 Aug 2025
Form 2File: Form 2 30-06-2024.pdf25 Aug 2025
Form 3File: Form 3 Q1 24-25 UPLOAD.pdf25 Aug 2025
Disclosure of Sold and Booked InventoryFile: Q1 24_25.pdf25 Aug 2025
Disclosure of Sold and Booked InventoryFile: Q2 24_25.pdf25 Aug 2025
Form 1File: Form 1 2024-25 Q2.pdf25 Aug 2025
Form 2File: Form 2 30-09-2024.pdf25 Aug 2025
Form 3File: Form 3 Q2 24-25 UPLOAD.pdf25 Aug 2025
Form 3File: Form 3 Q3 24-25 UPLOAD.pdf25 Aug 2025
Form 1File: Form 1 2024-25 Q3.pdf25 Aug 2025
Form 2File: Form 2 31-12-2024.pdf25 Aug 2025
Disclosure of Sold and Booked InventoryFile: Q3 24_25.pdf25 Aug 2025
Disclosure of Sold and Booked InventoryFile: Q4 24_25.pdf25 Aug 2025
Form 1File: Form 1 2024-25 Q4.pdf25 Aug 2025
Form 2File: Form 2 31-03-2025.pdf25 Aug 2025
Form 3File: Form 3 Q4 24-25 UPLOAD.pdf25 Aug 2025
Withdrawal Update Form 1File: Form 1 2025-26 Q1.pdf25 Aug 2025
Withdrawal Update Form 2File: form 2 30-06-2025.pdf25 Aug 2025
Withdrawal Update Form 3File: Form 3 Q1 25-26 UPLOAD.pdf25 Aug 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 2023-24 Q4.pdf17 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Q4_SIGN.pdf17 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Q4 23_24.pdf17 Feb 2025
Disclosure of sold/ booked inventoryFile: Q4_23_24.pdf17 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A 2023-24.pdf17 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5_1.pdf17 Feb 2025
Building plan approvalFile: BUILDING PLAN.pdf21 Dec 2024
Commencement Certificates / NA Order for plotted developmentFile: a4 cc wagholi lakhe.pdf21 Dec 2024
Building Plan Approval / NA Order for plotted developmentFile: BUILDING PLAN.pdf21 Dec 2024
Declaration in FORM BFile: form B Upload.pdf20 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Adobe Scan 13 Mar 2024 (2).pdf14 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Adobe Scan 13 Mar 2024 (1).pdf14 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf13 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 21-22.pdf13 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FY 22-23.pdf13 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 22-23.pdf13 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_compressed.pdf13 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FY 21-22.pdf13 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FY 22-23.pdf13 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf12 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf1 Nov 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC.pdf1 Nov 2023
Architect’s Certificate on Completion of Project (Form 4)File: Form 4.pdf1 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Adobe Scan 7 Jul 2023.pdf10 Aug 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Document 90.pdf10 Aug 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Adobe Scan 12-Apr-2023.pdf10 Aug 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Document 89.pdf10 Aug 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Cert.pdf9 Aug 2023
Details of encumbrances concerned to FinanceFile: B Details of encumbrances concerned to Legal _page-0001-1.pdf4 Mar 2023
Details of encumbrances concerned to LegalFile: B Details of encumbrances concerned to Legal _page-0001-1.pdf4 Mar 2023
Deviation Report with respect to Allotment letterFile: Deviation Report with respect to Allotment letter.pdf4 Mar 2023
Deviation Report with respect to model copy of AgreementFile: Deviation Report with respect to model copy of Agreement.pdf4 Mar 2023
CERSAI detailsFile: Asset Based Search_compressed (1).pdf4 Jan 2022
Commencement Certificates / NA Order for plotted developmentFile: Commencement Cert.pdf24 Dec 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_compressed.pdf24 Dec 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Cerificate.pdf24 Dec 2021
Layout approvalFile: 208.pdf29 Nov 2021
Copy of Layout Approval (in case of layout)File: 208.pdf29 Nov 2021
CERSAI detailsFile: No Encmb.pdf29 Nov 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form_3.pdf29 Nov 2021
Copy of the legal title reportFile: LTR-1-merged_compressed (1)_compressed.pdf28 Nov 2021
Details of encumbrancesFile: 2.pdf28 Nov 2021
Declaration in FORM BFile: FORM BAdobe Scan 14 Nov 2021.pdf28 Nov 2021
Building plan approvalFile: Building Plan.pdf21 Oct 2021
PAN CardFile: Firm PAN.pdf21 Oct 2021
Building Plan Approval / NA Order for plotted developmentFile: Building Plan.pdf21 Oct 2021
Commencement Certificates / NA Order for plotted developmentFile: Commmencement Cert_compressed.pdf21 Oct 2021
Declaration about Commencement CertificateFile: RERA docs-1.pdf21 Oct 2021
Proforma of Allotment letterFile: Agreement_for_Sale_Format.pdf21 Oct 2021
Proforma of Allotment letterFile: proforma_allotment_letter.pdf21 Oct 2021

How this compares with Pune

97%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 36 months
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SB Sai Sanskruti on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near WAGHOLI13,700+ in Pune

Builder: S B SAI ASSOCIATES

S B SAI ASSOCIATES has 1 registration on MahaRERA, including SB Sai Sanskruti. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if SB Sai Sanskruti is delayed beyond 31 Oct 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SB Sai Sanskruti?

The registered promoter entity is S B SAI ASSOCIATES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SB Sai Sanskruti?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SB Sai Sanskruti?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SB Sai Sanskruti?

The professionals named in the filing: Architect: HEMANT MAHATEKKAR; Engineer: NA PAVAN LAKHE; Chartered Accountant: Yash Nagar. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SB Sai Sanskruti?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SB Sai Sanskruti. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SB Sai Sanskruti to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.