ReraGenieLog inGet a buyer report

Home / Browse projects / Thane, Maharashtra / Savitri Smruti

Completed No litigation declared Others project

Savitri Smruti

By Adwait constructions

RG-MH-28369 · RERA P51700025673 · Last updated on MahaRERA portal: 15 Mar 2024

Source: official MahaRERA filing

Red flags

  • Completion date moved by 11 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
May 2023Possession promisedregistration recorded completed
6 of 11Construction stages donefurthest along: External plumbing and external plaster, 50%
0Complaints at MahaRERAon this registration
Jump to the 46 documents Report an error

Savitri Smruti is a Others project by Adwait constructions in Thane, Maharashtra, registered with MahaRERA as P51700025673 on 1 Jul 2020. The registration is recorded completed; possession was promised by 31 May 2023. The completion date has moved by 11 months from the original filing.

At a glance

Project

  • NameSavitri Smruti
  • TypeOthers
  • Location
    • Pandit malviya Road
    • Ramnagar
    • DOMBIVLI
    • Kalyan
    • Thane
    • 421201
  • Pincode421201
  • RERA no.P51700025673
  • ReraGenie IDRG-MH-28369

Builder

  • NameAdwait constructions
  • Entity typeOthers
  • Named personAnant Karve
  • Other registrations1 more →
  • Completed2 of 2

Key dates

this monthRegisteredJul 2020First promiseJun 2022Revised toMay 2023Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on1 Jul 2020
  • Promised completion31 May 2023
  • Revised completionRevised to 31 May 2023 (originally 30 Jun 2022)
  • Buildings1 building record
  • Documents filed46 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Savitri SmrutiNA90000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 15 Mar 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is External plumbing and external plaster, at 50%.

Savitri Smruti: 65% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises20%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%

Progress on shared amenities15

As on 15 Mar 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed5

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots5
Closed/Covered2
Open Space3

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area457 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
Karve AnantDOMBIVLIThane

Approvals and building plan

Permissible FSI437.16
Proposed, not sanctioned437 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchCity Mall, 1st Floor Near Pendharkar College Dombivli East

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectShirish G Nachane
EngineerRajesh Thakare & Associates
Chartered AccountantA V Khatu & Co Chartered Accountants
Chartered AccountantUDAY DIXIT & CO
PartnerRole in project
Adwait constructions-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700012370Jun 2022 → May 2023

Reason as filed by the promoterDELAY IN PERMISSION FROM CONSENT AUTHORITY TO DEVELOP THE INCREASED THE AREA AS PER UDCPR.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 4 Aug 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 25 Aug 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 4 Aug 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 4 Aug 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 18 May 2023

Documents filed46

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Adwait Construction -Savitri Smruti Form 5 Signed.pdf15 Mar 2024
Layout approvalFile: REVISED PLAN mhaskar compressed.pdf25 Aug 2023
Copy of Layout Approval (in case of layout)File: REVISED PLAN mhaskar compressed.pdf25 Aug 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC MHASKAR.pdf18 May 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Archi Certificate.pdf12 May 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Savitri Smruti.pdf12 May 2023
Disclosure of sold/ booked inventoryFile: Savitri Smruti Sold Unsold.pdf12 May 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Revised_11zon.pdf12 May 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: revised SAVITRI SMRUTI SEPRATE BANK ACCOUNTS DETAILS.pdf12 May 2023
Other - LegalFile: Amt Recvd Date wise from allottes mhaskar_11zon.pdf12 May 2023
Other - LegalFile: Amt withdrwan datewise chandraprabha_11zon.pdf12 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Quality Assurance 31032022.pdf18 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 Savitri Smruti 2020-21.pdf18 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 Savitri Smruti 2021-22.pdf18 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Self Declaration - Savitri.pdf18 Feb 2023
Declaration about Commencement CertificateFile: Declaration About CC.pdf5 Aug 2022
CERSAI detailsFile: Cersai Report.pdf5 Aug 2022
Building plan approvalFile: Revised cc.pdf4 Aug 2022
Copy of the legal title reportFile: Legal Title search.pdf4 Aug 2022
Details of encumbrances concerned to LegalFile: Non Encumbrance.pdf4 Aug 2022
Building Plan Approval / NA Order for plotted developmentFile: Revised cc.pdf4 Aug 2022
Commencement Certificates / NA Order for plotted developmentFile: Revised cc.pdf4 Aug 2022
Declaration in FORM BFile: Affidavit cum Declaration mhaskar_compressed.pdf4 Aug 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Archi Certificate Savitri Smruti.pdf4 Aug 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf4 Aug 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Quality assurance 31032020.pdf4 Aug 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Quality Assurance 31032021.pdf4 Aug 2022
Disclosure of sold/ booked inventoryFile: Sold unsold inventory.pdf4 Aug 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTI Adwait Construction (1).pdf4 Aug 2022
Proforma of Allotment letterFile: model allortment letter (1).pdf4 Aug 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: declaration about Bank details.pdf4 Aug 2022
Proforma of Allotment letterFile: SALE_AGREEMENT_Draft.pdf25 Jun 2020
Layout approvalFile: Approved Plan .pdf24 Jun 2020
Building plan approvalFile: CC.pdf24 Jun 2020
PAN CardFile: Pan Card (Karve Sir).pdf24 Jun 2020
Details of encumbrancesFile: Title search report.pdf24 Jun 2020
Details of encumbrancesFile: Development Agreement Compressed.pdf24 Jun 2020
Copy of Layout Approval (in case of layout)File: Approved Plan .pdf24 Jun 2020
Building Plan Approval / NA Order for plotted developmentFile: CC.pdf24 Jun 2020
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf24 Jun 2020
Declaration in FORM BFile: Affidavite cum declaration.pdf24 Jun 2020
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate mhaskar.pdf24 Jun 2020
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf24 Jun 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate.pdf24 Jun 2020
Proforma of Allotment letterFile: Allotment_letter.pdf24 Jun 2020
Copy of the legal title reportFile: Title search report.pdf23 Jun 2020

How this compares with Thane

24%of Thane projects moved their completion datethis one moved by 11 months
23%of Thane registrations have lapsed or been cancelledthis one is completed

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Savitri Smruti on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Ramnagar7,600+ in Thane

Builder: Adwait constructions

Adwait constructions has 2 registrations on MahaRERA, including Chandraprabha Heights and Savitri Smruti. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if Savitri Smruti is delayed beyond 31 May 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Savitri Smruti?

The registered promoter entity is Adwait constructions, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Savitri Smruti?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Savitri Smruti?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Savitri Smruti?

The professionals named in the filing: Architect: Shirish G Nachane; Engineer: Rajesh Thakare & Associates; Chartered Accountant: A V Khatu & Co Chartered Accountants; Chartered Accountant: UDAY DIXIT & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Savitri Smruti?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Savitri Smruti. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Savitri Smruti to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.