Home / Browse projects / Mumbai Suburban, Maharashtra / Satra Business Park

Registration lapsed No litigation declared Commercial project

Satra Business Park

By SATRA DEVELOPERS

RG-MH-47324 · RERA P51800009392 · Last updated on MahaRERA portal: 7 Jun 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 31 months past the filed date
  • 1 complaint at MahaRERA
  • Completion date moved by 72 months
  • 5 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Mar 2024Possession promised31 months past this date
7 of 11Construction stages donefurthest along: Internal walls, 85%
1Complaints at MahaRERAon this registration
Jump to the 35 documents Report an error

Satra Business Park is a Commercial project by SATRA DEVELOPERS in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800009392 on 22 Aug 2017. Possession was promised by 31 Mar 2024 and is now 31 months past that date. The completion date has moved by 72 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameSatra Business Park
  • TypeCommercial
  • Location
    • Kurla
    • Mumbai Suburban
    • 400080
  • Pincode400080
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800009392
  • ReraGenie IDRG-MH-47324

Builder

  • NameSATRA DEVELOPERS
  • Entity typePartnership
  • PartnerPrafulla Rajesh Satra

Key dates

31 months past promisethis monthRegisteredAug 2017First promiseMar 2018Revised toMar 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on22 Aug 2017
  • Promised completion31 Mar 2024
  • Revised completionRevised to 31 Mar 2024 (originally 31 Mar 2018)
  • Buildings1 building record
  • Documents filed35 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Satra Business ParkNA90000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 7 Jun 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 85%.

Satra Business Park: 90% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises85%
Sanitary Fittings within the flats / premises60%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.85%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.60%

Progress on shared amenities15

As on 7 Jun 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes50%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes5%
Open ParkingYes100%

Parking filed74

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots74
Closed/Covered70
Open Space4

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,720 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI3626.96
Proposed, not sanctioned3,627 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchRamdas Tower, Kharkar ali

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSunil R Deole
Chartered AccountantRishabh Motule
PartnerRole in project
SATRA DEVELOPERS-

Extensions applied for5

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800001636Mar 2018 → Apr 2020

Reason as filed by the promoterThe project has been completed to the extent of 80%. Major work pending is the external finishings and sanitary fittings and other related work. Therefore, major funds of the project have been allocated and consumed. Due to the near finishing of the project, prospective buyers in order to avoid GST have withheld their buying. This led a fund crunch in the intervening period till Feb/March 2019. The developer has now negotiated with contractor to complete the work and has started the finishing. The architectural requirements need further 12 months for the completion. The developer has raised th

EXT51800000218Mar 2018 → Apr 2020

Reason as filed by the promoterThe project experienced delay due to following reasons: 1. During the time period from October to December 2017, the project experienced crunch of unskilled and semi-skilled manpower due to festivals, migrant workers heading back home for festival and marriage. The labour contractor was not able to arrange for substitutes in place of the original workers. This has led to slowing of work. 2. The sand extraction was banned in and around Mumbai area for a considerable period during the year. This led to delay in completion.

EXT51800008980Mar 2018 → Dec 2021

Reason as filed by the promoterThe project completion date was 30/04/2020. Due to the Covid-19 pandemic, all work had ceased. There was an automatic extension of 6 months period till October 2020, however, mobilisation of the labour force is presently a challenge due to the migrant labour issue. The reason for delay is the COVID-19 pandemic and migrant labour issue.

EXT51800012168Mar 2018 → Mar 2023

Reason as filed by the promoterThe developer faced covid related issues. There was short supply of glass and aluminium for the facade due to Russia - Ukraine war. The total raw material cost escalated by nearly 50%. The developer has now carried out the development and the project is more than 90%.

EXT51800015228Mar 2018 → Mar 2024

Reason as filed by the promoterThe project is nearing completion. There is a dispute with the Stacked parking vendor. However, there is an on going discussion with the vendor and the matter is expected to resolve

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC006000000192422Prashant ParmarSATRA DEVELOPERS03/02/2020

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 30 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed35

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: CA Certificate.pdf7 Jun 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2024-25)File: CA Certificate.pdf7 Jun 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2_19-12-2024.pdf31 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2_19-12-2024.pdf31 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Satra_Architect Letter_Form4.pdf31 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE.pdf15 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: ENGINEERS CERTIFICATE FORM -2 RERA (1)-1-4.pdf15 May 2023
Certificates of CA (Form 3)File: CA CERTIFICATE.pdf15 May 2023
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory.pdf13 May 2023
Declaration about Commencement CertificateFile: declaration about commencement certificate.pdf20 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2 Satra Plaza.pdf20 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2 Satra Plaza.pdf20 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2 Satra Plaza.pdf20 Apr 2023
Disclosure of sold/ booked inventoryFile: Circular No_ 29 Sold Unsold Flat Details.pdf20 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: CA Statement.pdf20 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: CA Annual Report FY20-21.pdf27 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: CA Annual Report FY21-22.pdf24 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: CA 2017-18.pdf27 Dec 2019
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: CA 2018-19.pdf27 Dec 2019
Layout approvalFile: Copy of layout approval.pdf31 Jul 2017
Building plan approvalFile: IOD UP.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: Copy of layout approval.pdf31 Jul 2017
Building Plan Approval (IOD)File: IOD UP.pdf31 Jul 2017
Declaration in FORM BFile: Form B Edited.pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Artitect.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf31 Jul 2017
Certificates of CA (Form 3)File: CA certificate (2).pdf31 Jul 2017
Proforma of Allotment letterFile: Update Proforma and RERA Sale Agreement -ilovepdf-compressed (1).pdf31 Jul 2017
Layout approvalFile: Compressed.pdf30 Jul 2017
Building plan approvalFile: IMG_-ilovepdf-compressed (1).pdf30 Jul 2017
Copy of the legal title reportFile: Certificate of Title-ilovepdf-compressed.pdf30 Jul 2017
Details of encumbrancesFile: Details of Encumbrance With property of schedule.pdf30 Jul 2017
Copy of Layout Approval (in case of layout)File: Compressed.pdf30 Jul 2017
Building Plan Approval (IOD)File: IMG_-ilovepdf-compressed (1).pdf30 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf30 Jul 2017

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 72 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Satra Business Park on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kurla6,700+ in Mumbai Suburban

2 kmSatra Business ParkCompleted 125Lapsed / revoked 96Other 153Dot size: filed unitsN

Filed coordinates, straight-line distance. 374 registered projects within 2 km.

Builder: SATRA DEVELOPERS

SATRA DEVELOPERS has 1 registration on MahaRERA, including Satra Business Park. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that Satra Business Park shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Satra Business Park is delayed beyond 31 Mar 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Satra Business Park?

The registered promoter entity is SATRA DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Satra Business Park?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Satra Business Park?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Satra Business Park?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Satra Business Park?

The professionals named in the filing: Architect: Sunil R Deole; Chartered Accountant: Rishabh Motule. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Satra Business Park?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Satra Business Park. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Satra Business Park to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.