saroj sadan CHSL
RG-MH-20860 · RERA P51800012908 · Last updated on MahaRERA portal: 20 Aug 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 6 months past the filed date
- 1 complaint at MahaRERA
- Completion date moved by 88 months
- 5 extensions taken
Clear
- No litigation declared
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
saroj sadan CHSL is a Residential / Group Housing project by Pritesh Damji Savla in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800012908 on 7 Sep 2017. Possession was promised by 15 Apr 2026 and is now 6 months past that date. The completion date has moved by 88 months from the original filing. 14 of the 33 units on this registration are recorded sold or booked, and 10 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.
At a glance
Project
- Namesaroj sadan CHSL
- TypeResidential / Group Housing
- Location
- Daftari Road
- Kurar
- Borivali
- Mumbai Suburban
- 400097
- Pincode400097
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800012908
- ReraGenie IDRG-MH-20860
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on7 Sep 2017
- Promised completion15 Apr 2026
- Revised completionRevised to 15 Apr 2026 (originally 12 Dec 2018)
- Buildings1 building record
- Documents filed132 files
Current status
Figures as on 20 Aug 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SHRI SAROJ SADAN CHSL | NA | 9 | 9 | 33 | 0 | 33 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 20 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
SHRI SAROJ SADAN CHSL: 91% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 20 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed19
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| SHRI SAROJ SADAN CHSL | NA | Rs 4.80 cr | Rs 4.80 cr |
| - | NA | Rs 80.45 lakh | Rs 80.45 lakh |
Certifying professionals and partners8
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | RASIK P HINGOO ASSOCIATES |
| Architect | RASIK HINGOO |
| Engineer | SHAH STRUCTURALS PVT LTD. |
| Engineer | MOHAN MANEKAR |
| Engineer | RAKESH SINGH |
| Chartered Accountant | JAYAVANT R KANASE |
| Chartered Accountant | VIVEK THAR |
| Chartered Accountant | AJAY JHANWAR |
| Partner | Role in project |
|---|---|
| Pritesh Damji Savla | - |
Extensions applied for5
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterReason for delay in completion of project is due to delay caused by supply of materials and services by contractors, market conditions of the Real Estate sector and Prolonged delay in obtaining necessary delay from the Authority. However, we shall endeavor completion of project within extended duration of 24 months.
Reason as filed by the promoterSir, we are not able to complete the project on time due to pending approvals and Covid pandemic. We have initial approvals till 4th floor which has completed and we immediate applied for further approvals on 13-09-2017 to the authority which was rejected on 19-06-2018 as Hon’ble Supreme Court issued guidelines for issuing building permits order to the Authority in SPL (Civil) No. D23708/2017 in Deonar Dumping Ground Case. The authority hold all the further approvals and issued guidelines to comply before submitting for further approvals which took long time. Then after we have completed all t
Reason as filed by the promoterRespected Sir/Madam, This is to Inform you that project “SHRI SAROJ SADAN CHSL” developed by M/s. Vini Developers has been granted registration under MahaRERA vide registration no. dated 31.08.2017, and the completion of work extension was granted till 31.12.2023. We had initial approvals till 4th floor which was completed and after that we immediate applied for further approvals on 13-09-2017 to the authority which was rejected on 19-06-2018 as Hon’ble Supreme Court issued guidelines for issuing building permits order to the Authority in SPL (Civil) No. D23708/2017 in Deonar Dumping Ground Ca
Reason as filed by the promoterThe delay in project completion is primarily due to the application of new directives from the Ministry of Defence, which introduced certain constraints related to the Central Ordnance Depot (COD). These constraints were beyond our control and significantly impacted the project timeline. However, the government has announced that these restrictions will be lifted in December 2024, at which point we anticipate resuming normal progress and completing the project as per the revised schedule
Reason as filed by the promoterThe delay in completion of the project was primarily caused by the implementation of new directives issued by the Ministry of Defence, which imposed certain restrictions concerning the Central Ordnance Depot (COD). These restrictions were beyond our control and had a significant impact on the project schedule and progress. Subsequently, the Government announced that the said restrictions would be lifted in December 2024, enabling the project to resume normal construction activities thereafter. The project has since been completed, and the Full Occupancy Certificate was issued by the competent
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000196072 | Mr. Rajesh Raghavji Shah | M/s. VINI DEVELOPERS | 17/02/2021 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 25 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 25 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 10 Oct 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 12 Oct 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed132
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 132 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2A (FY 2025-2026)File: Form 2A March 2026.pdf | 20 Aug 2026 |
| Withdrawal Update Form 1File: form1.pdf | 18 Aug 2026 |
| Withdrawal Update Form 1File: form1.pdf | 18 Aug 2026 |
| Withdrawal Update Form 1File: form1.pdf | 18 Aug 2026 |
| Withdrawal Update Form 2File: form2.pdf | 18 Aug 2026 |
| Withdrawal Update Form 2File: form2.pdf | 18 Aug 2026 |
| Withdrawal Update Form 2File: form2.pdf | 18 Aug 2026 |
| Withdrawal Update Form 3File: form331032026.pdf | 18 Aug 2026 |
| Withdrawal Update Form 3File: form3final.pdf | 18 Aug 2026 |
| Withdrawal Update Form 3File: form315042026.pdf | 18 Aug 2026 |
| Withdrawal Update Form 1File: FORM 1 SEPTEMBER 2025.pdf | 3 Jun 2026 |
| Withdrawal Update Form 1File: FORM 1 DECEMBER 2025.pdf | 3 Jun 2026 |
| Withdrawal Update Form 2File: Form2.pdf | 3 Jun 2026 |
| Withdrawal Update Form 2File: Form2 final upload.pdf | 3 Jun 2026 |
| Withdrawal Update Form 3File: form 3 final.pdf | 3 Jun 2026 |
| Withdrawal Update Form 3File: Form 3December Final.pdf | 3 Jun 2026 |
| Form 2A (FY 2024-2025)File: Form 2A Shri Saroj Sadan CHSL March 2025.pdf | 6 Nov 2025 |
| Form 1File: FORM 1 ARCHITECT CERTIFICATE JUNE 2025.pdf | 29 Sep 2025 |
| Form 2File: Form2 (2).pdf | 29 Sep 2025 |
| Form 3File: Form 3 Saroj Sadan CHSL June 2025.pdf | 29 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure Inventory Final.pdf | 29 Sep 2025 |
| Form 1File: Form 1.pdf | 26 May 2025 |
| Form 2File: Form -2.pdf | 26 May 2025 |
| Form 3File: Form -3.pdf | 26 May 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold unsold inventory.pdf | 26 May 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: QUALITY ASSURANCE CERTIFICATE.pdf | 28 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate Signed.pdf | 1 Feb 2025 |
| Certificates of CA (Form 3)File: Signed_compressed.pdf | 1 Feb 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM - 2 as on 31-12-2024 shri saroj sadan Revised cost Signed.pdf | 1 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: Page 1_Page 2_merged.pdf | 1 Feb 2025 |
| CERSAI detailsFile: Undertaking Final.pdf | 1 Feb 2025 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: DECLARATION ABOUT SEPARATE BANK ACCOUNT.pdf | 1 Feb 2025 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: DISCLOSURE OF INTEREST IN OTHER REAL ESTATE ORGANIZATIONS.pdf | 1 Feb 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 23-24 Final.pdf | 1 Feb 2025 |
| Declaration in FORM BFile: Form B.pdf | 24 Dec 2024 |
| Certificates of CA (Form 3)File: Final Form 3.pdf | 24 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 march 24.pdf | 20 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 June 24.pdf | 20 Dec 2024 |
| Certificates of CA (Form 3)File: saroj Sadan march-2024_compressed.pdf | 30 Nov 2024 |
| Certificates of CA (Form 3)File: Saroj Sadan-June-2024_compressed.pdf | 30 Nov 2024 |
| Certificates of CA (Form 3)File: Saroj sadan Sep-2024_compressed.pdf | 30 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 SHRI SAROJ SADAN 30-06-2024.pdf | 30 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 SHRI SAROJ SADAN 30-09-2024.pdf | 30 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 SHRI SAROJ SADAN CHSL 31-03-2024.pdf | 30 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: Saroj Disclouser-Sep-2024.pdf | 30 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: 3112 2023.pdf | 28 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: 31 03 2024.pdf | 28 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: 30 06 2024.pdf | 28 Nov 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form - 2A 12082019.pdf | 5 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form - 2a 05112019.pdf | 5 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form - 2a 07022020.pdf | 5 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form - 2a 15082020.pdf | 5 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form - 2a 15082020.pdf | 5 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form - 2a 15082020.pdf | 5 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form - 2A 08112020.pdf | 5 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form - 2A 24012021.pdf | 5 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form - 2A 01052021.pdf | 5 Dec 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form - 2 Signed_compressed.pdf | 4 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM -2a 08072021.pdf | 4 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: form - 2a 12102021_compressed.pdf | 4 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form - 2a 09012022.pdf | 4 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form- 2a 15042022_compressed.pdf | 4 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: form - 2a 10072022.pdf | 4 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: form - 2a 10072022.pdf | 4 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: form - 2a 09102022.pdf | 4 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: form - 2a 11012023_compressed.pdf | 4 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: form - 2a 11012023-4-6.pdf | 4 Dec 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form - 5 signed 2021-2022.pdf | 4 Dec 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form - 5 signed 2022-23.pdf | 4 Dec 2023 |
| Certificates of CA (Form 3)File: CA CERTIFICATE FORM 3 -SHRI SAROJ SADAN CHSL.pdf | 1 Dec 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: annual report - 2021-22.pdf | 1 Dec 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Annual report - 2022-2023.pdf | 1 Dec 2023 |
| Disclosure of sold/ booked inventoryFile: disclosure of flats - 30112023.pdf | 30 Nov 2023 |
| Declaration in FORM BFile: Affidavit cum Declaration Rose Blossom CHSL.pdf | 9 Nov 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form - 2 sarojsadan chsl.pdf | 9 Nov 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Engineers Certificate for Quality Assurance.pdf | 9 Nov 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Engineers Certificate for Quality Assurance.pdf | 9 Nov 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Engineers Certificate for Quality Assurance.pdf | 9 Nov 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Engineers Certificate for Quality Assurance.pdf | 9 Nov 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Engineers Certificate for Quality Assurance.pdf | 9 Nov 2023 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| RAM KUTIR | NATWAR NAGAR ROAD NO 3JOGESHWARI EAST | 1 | Completed | Oct 2008 | Late, Dec 2008 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 132 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep saroj sadan CHSL on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Kurar6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 383 registered projects within 2 km.
Alta Monte and Signet
ERA REALTORS PRIVATE LIMITED
MAULI OMKAR
MAULI SAI DEVELOPERS PVT LTD
HIVE 97
AMITY CONSTRUCTIONS
MAULI PRIDE
MAULI SAI DEVELOPERS PVT LTD
Aarambh Phase III by group Satellite
Satellite Developers Private Limited
Sethia Imperial Avenue
Sai Enterprises
See every Mumbai Suburban project, with the district possession charts
Builder: Pritesh Damji Savla
Pritesh Damji Savla has 2 registrations on MahaRERA, including saroj sadan CHSL and Bhagwati Ashish. Its filings disclose 3 earlier MahaRERA projects: declares 0 of 3 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What does it mean that saroj sadan CHSL shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if saroj sadan CHSL is delayed beyond 15 Apr 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of saroj sadan CHSL?
The registered promoter entity is Pritesh Damji Savla, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in saroj sadan CHSL?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against saroj sadan CHSL?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for saroj sadan CHSL?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at saroj sadan CHSL?
The professionals named in the filing: Architect: RASIK P HINGOO ASSOCIATES; Architect: RASIK HINGOO; Engineer: SHAH STRUCTURALS PVT LTD.; Engineer: MOHAN MANEKAR; Engineer: RAKESH SINGH; Chartered Accountant: JAYAVANT R KANASE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in saroj sadan CHSL?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback