ReraGenieLog inGet a buyer report

Home / Browse projects / Palghar, Maharashtra / SANSKRUTI ROSE

Registered No litigation declared Others project

SANSKRUTI ROSE

By SANSKRUTI BUILDER AND DEVELOPER

RG-MH-51958 · RERA P99000049176 · Last updated on MahaRERA portal: 21 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 24 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedmoved 24 months from the original
3 of 11Construction stages donefurthest along: Stilt Floor, 95%
72 of 148Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 65 documents Report an error

SANSKRUTI ROSE is a Others project by SANSKRUTI BUILDER AND DEVELOPER in Palghar, Maharashtra, registered with MahaRERA as P99000049176 on 3 Feb 2023. Possession is promised by 31 Dec 2027. The completion date has moved by 24 months from the original filing. 76 of the 148 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete.

At a glance

Project

  • NameSANSKRUTI ROSE
  • TypeOthers
  • Location
    • Achole
    • Nallasopara East
    • Vasai-Virar City (M Corp)
    • Vasai
    • Palghar
    • 401209
  • Pincode401209
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000049176
  • ReraGenie IDRG-MH-51958

Builder

  • NameSANSKRUTI BUILDER AND DEVELOPER
  • Entity typePartnership
  • GSTIN27AEPFS8662D1ZH
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • PartnersPRADEEPKUMAR ATMAPRASAD CHATURVEDI, PRAMOD ATMAPRASAD CHATURVEDI
  • Other registrations3 more →

Key dates

this monthRegisteredFeb 2023First promiseDec 2025Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on3 Feb 2023
  • Promised completion31 Dec 2027
  • Revised completionRevised to 31 Dec 2027 (originally 31 Dec 2025)
  • Buildings1 building record
  • Documents filed65 files

Current status

51%76 of 148 units booked
96.9%Work done, per cost certificate

Figures as on 21 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SANSKRUTI ROSENA881471148

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 21 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Stilt Floor, at 95%.

SANSKRUTI ROSE: 73% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor95%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%

Progress on shared amenities15

As on 21 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes90%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes95%
Storm Water DrainsYes90%
Landscaping & Tree PlantingYes0%
Street LightingYes50%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes50%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,441 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
NAD-BRAHMA ASVARI CO-OP HSG SOC LTDVasai-Virar City (M Corp)Palghar

Approvals and building plan

Sanctioning authorityVASAI-VIRAR CITY MUNCIPAL CORPORATION
Permissible FSI7876.33
Proposed, not sanctioned7,876 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNALLASOPARA
Estimated costRs 25.14 cr
Cost incurredRs 24.36 cr
Work done96.88%
BuildingWingEstimatedIncurred
SANSKRUTI ROSENARs 22.94 crRs 22.60 cr
-NARs 2.20 crRs 1.76 cr

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectABHAY RAUT
EngineerK C SHAH CONSULTANTS
EngineerAAKASH TIWARI
Chartered AccountantS B JAIN AND ASSOCIATES
Chartered AccountantJPM AND ASSOCIATES
Chartered AccountantManish Shinde & Associates
Chartered AccountantVISHAL P GUPTA
PartnerRole in project
SANSKRUTI BUILDER AND DEVELOPER-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA02012619226Dec 2025 → Dec 2027

Reason as filed by the promoterSlow responce leaded to extend the Rera project deadline

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 19 Oct 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 19 Oct 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 19 Oct 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 19 Oct 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed65

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 1.pdf21 Jul 2026
Withdrawal Update Form 2File: ENG.pdf21 Jul 2026
Withdrawal Update Form 3File: FORM 3 JUNE 2026.pdf21 Jul 2026
Withdrawal Update Form 1File: ARCH.pdf24 Jun 2026
Withdrawal Update Form 2File: ENG.pdf24 Jun 2026
Withdrawal Update Form 3File: form 3.pdf24 Jun 2026
Withdrawal Update Form 1File: FORM-1.pdf23 Jun 2026
Withdrawal Update Form 2File: FORM-2.pdf23 Jun 2026
Withdrawal Update Form 3File: Form 3 Q3.pdf23 Jun 2026
Withdrawal Update Form 1File: form 1-30-6-25.pdf1 Jan 2026
Withdrawal Update Form 1File: FORM 1.pdf1 Jan 2026
Withdrawal Update Form 2File: form 2 30-6-25.pdf1 Jan 2026
Withdrawal Update Form 2File: FORM 2.pdf1 Jan 2026
Withdrawal Update Form 3File: Signed FORM 3.pdf1 Jan 2026
Withdrawal Update Form 3File: FINAL ROSE SEPT FORM 3.pdf1 Jan 2026
Form 5 (FY 2024-2025)File: Form 5 (24-25).pdf1 Jan 2026
Form 2A (FY 2023-2024)File: form 2A Rose23-24.pdf27 Dec 2025
Form 2A (FY 2024-2025)File: Rose Form 2A 24-25.pdf27 Dec 2025
Form 5 (FY 2023-2024)File: Form 5 (23-24).pdf22 Dec 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf20 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf20 Apr 2025
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD.pdf20 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: arch dec24.pdf10 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: eng dec24.pdf10 Mar 2025
Disclosure of sold/ booked inventoryFile: sold unsold dec24.pdf10 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer certificate 23022024 ROSE.pdf26 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SANS ROSE ABHAY RAUT ARCH.pdf8 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: ROSE AUDIT.pdf24 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: sanskruti rose - quality assurance certificate.pdf14 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form-3.pdf14 Oct 2023
Disclosure of sold/ booked inventoryFile: sold - unsold details - for rera update.pdf13 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ROSE FORM 2 JULY23.pdf12 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: july-23 (2).pdf6 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH CERT ROSE.pdf5 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ROSE ENG CER.pdf5 Oct 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: bank a-c declaration.pdf29 May 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_FINAL_compressed.pdf30 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: PRAMOD_compressed.pdf18 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: PRADEEP_compressed.pdf18 Jan 2023
CERSAI detailsFile: CERSAI_Search_Report_200257689079_For_Asset_Based_Search_16_01_2023_19_56_44_613.pdf16 Jan 2023
Building plan approvalFile: WING A.pdf19 Oct 2022
Building plan approvalFile: WING B.pdf19 Oct 2022
Building plan approvalFile: WING C.pdf19 Oct 2022
Building plan approvalFile: WING D.pdf19 Oct 2022
Building plan approvalFile: WING E.pdf19 Oct 2022
Layout approvalFile: LAYOUT PLAN.pdf19 Oct 2022
PAN CardFile: 1 PAN Card.pdf19 Oct 2022
Copy of the legal title reportFile: LEGAL TITLE REPORT_compressed.pdf19 Oct 2022
Details of encumbrances concerned to FinanceFile: no encumbrance finance.pdf19 Oct 2022
Details of encumbrances concerned to LegalFile: no encumbrance legal.pdf19 Oct 2022
Copy of Layout Approval (in case of layout)File: LAYOUT PLAN.pdf19 Oct 2022
Building Plan Approval / NA Order for plotted developmentFile: WING A.pdf19 Oct 2022
Building Plan Approval / NA Order for plotted developmentFile: WING B.pdf19 Oct 2022
Building Plan Approval / NA Order for plotted developmentFile: WING C.pdf19 Oct 2022
Building Plan Approval / NA Order for plotted developmentFile: WING D.pdf19 Oct 2022
Building Plan Approval / NA Order for plotted developmentFile: WING E.pdf19 Oct 2022
Commencement Certificates / NA Order for plotted developmentFile: Nadbrahma cc_compressed.pdf19 Oct 2022
Declaration about Commencement CertificateFile: letter.pdf19 Oct 2022
Declaration in FORM BFile: AFFIDAVIIT CUM DECLARATION builder_compressed.pdf19 Oct 2022
Proforma of Agreement for saleFile: SALE DRAFT.pdf19 Oct 2022
Proforma of Agreement for saleFile: AGREEMENT FOR SALE.pdf19 Oct 2022
Proforma of Allotment letterFile: allotement draft.pdf19 Oct 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: BANK DECLARATION.pdf19 Oct 2022
Deviation Report with respect to Allotment letterFile: no deviation allotement.pdf19 Oct 2022
Deviation Report with respect to model copy of AgreementFile: no deviation agreement.pdf19 Oct 2022

How this compares with Palghar

51%of this project is bookeddistrict median 25%
31%of Palghar projects moved their completion datethis one moved by 24 months
26%of Palghar registrations have lapsed or been cancelledthis one is on the register

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SANSKRUTI ROSE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Nallasopara East3,200+ in Palghar

2 kmSANSKRUTI ROSECompleted 46Lapsed / revoked 37Other 87Dot size: filed unitsN

Filed coordinates, straight-line distance. 170 registered projects within 2 km.

Builder: SANSKRUTI BUILDER AND DEVELOPER

SANSKRUTI BUILDER AND DEVELOPER has 4 registrations on MahaRERA, including SANSKRUTI SAPPHIRE and SANSKRUTI ROSE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if SANSKRUTI ROSE is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SANSKRUTI ROSE?

The registered promoter entity is SANSKRUTI BUILDER AND DEVELOPER, a partnership as per the filing. Its GSTIN 27AEPFS8662D1ZH can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SANSKRUTI ROSE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SANSKRUTI ROSE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SANSKRUTI ROSE?

The professionals named in the filing: Architect: ABHAY RAUT; Engineer: K C SHAH CONSULTANTS; Engineer: AAKASH TIWARI; Chartered Accountant: S B JAIN AND ASSOCIATES; Chartered Accountant: JPM AND ASSOCIATES; Chartered Accountant: Manish Shinde & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SANSKRUTI ROSE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SANSKRUTI ROSE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SANSKRUTI ROSE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.