ReraGenieLog inGet a buyer report

Home / Browse projects / SANGHVI PARSSSVA EXCELLENSEA

Registered No litigation declared Others project

SANGHVI PARSSSVA EXCELLENSEA

By SANGHVI PARSSSVA ENTERPRISE LLP

RG-MH-75012 · RERA P51900020397 · Last updated on MahaRERA portal: 19 Jun 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 39 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: .
Mar 2027Possession promisedmoved 39 months from the original
4 of 11Construction stages donefurthest along: Slabs of Super Structure, 70%
8 of 16Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 151 documents Report an error

SANGHVI PARSSSVA EXCELLENSEA is a Others project by SANGHVI PARSSSVA ENTERPRISE LLP in Charni Road (D ward), 400004, registered with MahaRERA as P51900020397 on 9 Apr 2019. Possession is promised by 31 Mar 2027. The completion date has moved by 39 months from the original filing. 8 of the 16 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.

At a glance

Project

  • NameSANGHVI PARSSSVA EXCELLENSEA
  • TypeOthers
  • Location
    • Raja Ram Mohan Roy Road
    • Charni Road (D ward)
    • 400004
  • Pincode400004
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900020397
  • ReraGenie IDRG-MH-75012

Builder

  • NameSANGHVI PARSSSVA ENTERPRISE LLP
  • Entity typePartnership
  • PartnerRISHABH RAMESH SANGHVI
  • Other registrations1 more →
  • Declared earlier projects2 →

Key dates

this monthRegisteredApr 2019First promiseDec 2023Revised toMar 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on9 Apr 2019
  • Promised completion31 Mar 2027
  • Revised completionRevised to 31 Mar 2027 (originally 30 Dec 2023)
  • Buildings1 building record
  • Documents filed151 files

Current status

50%8 of 16 units booked
81.5%Work done, per cost certificate

Figures as on 19 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SANGHVI PARSSSVA EXCELLENSEANA242214216

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 19 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 70%.

SANGHVI PARSSSVA EXCELLENSEA: 65% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure70%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises63%
Sanitary Fittings within the flats / premises40%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.40%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.39%

Progress on shared amenities15

As on 19 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyNoNot applicable
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes90%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area929 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
ARIF HUSSAIN PATELMumbai CityMumbai City

Approvals and building plan

Sanctioning authorityMUNICIPAL CORPORATION OF GREATER MUMBAI
Permissible FSI3731.02
Proposed, not sanctioned3,731 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSAMACHAR MARG FORT MUMBAI 400001
Estimated costRs 25.88 cr
Cost incurredRs 21.11 cr
Work done81.55%
BuildingWingEstimatedIncurred
SANGHVI PARSSSVA EXCELLENSEANARs 20.14 crRs 18.36 cr
-NARs 5.74 crRs 2.75 cr

Certifying professionals and partners8

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMandwiwala Qutub Associates
ArchitectNARENDRA CHITRODA
EngineerRavindra Kumar
EngineerSunil Vasant Tayde
EngineerMahimtura Consultants Pvt. Ltd.
Chartered AccountantVSC & ASSOCIATES
Chartered AccountantPRIYA BAJAJ & ASSOCIATES
Chartered AccountantAbhishek Bajaj
PartnerRole in project
SANGHVI PARSSSVA ENTERPRISE LLP-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51900018547Dec 2023 → Dec 2024

Reason as filed by the promoterDue to delay in approvals, we need time extension of one year for completion of the project.

EXT51900028258Dec 2023 → Mar 2026

Reason as filed by the promoterThe project was started prior to outbreak of COVID-19, which had an impact on real estate project for nearly 2 years, from March 2020 to February 2022 which has severely impacted the availability of labor and disrupted the supply chain, causing significant delays in the construction activities. This has resulted in slow progress in construction. However, we are trying to complete the project at the earliest. Kindly process our application and grant us the extension till 31-03-2026. After careful consideration of the current circumstances and the challenges faced, we propose a revised completio

EA31032620481Dec 2023 → Mar 2027

Reason as filed by the promoter1. Grounds for Extension: a. The progress of the project was significantly impacted by a series of unforeseen challenges, primarily arising from the COVID-19 pandemic and its aftermath. Between March 2020 and February 2022, construction activities were severely disrupted due to nationwide lockdowns, movement restrictions, and mandatory safety measures. These conditions led to acute shortages of skilled and unskilled labour, disruptions in the supply chain for essential materials and equipment, and prolonged periods of inactivity on site. Despite these obstacles, the developer made continuous e

Litigation declared6

CaseCourtStatus
1321/2017Bombay High CourtCorporation to file their Reply
1895/2012City Civil CourtFor evidence
170/2020Bombay High CourtPending
214/2020Bombay High CourtPending
15669/2020Bombay High CourtPending
27078/2021Bombay High CourtPending

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 10 Feb 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 26 Mar 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 24 Apr 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 24 Apr 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2027

Documents filed151

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 151 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: Form -2A.pdf19 Jun 2026
Form 2A (FY 2024-2025)File: Form 2A.pdf13 Mar 2026
Withdrawal Update Form 1File: Form 1.pdf12 Mar 2026
Withdrawal Update Form 2File: Form 2.pdf12 Mar 2026
Withdrawal Update Form 3File: Form 3.pdf12 Mar 2026
Withdrawal Update Form 1File: Form 1.pdf11 Mar 2026
Withdrawal Update Form 1File: Form 1 Sept 25.pdf11 Mar 2026
Withdrawal Update Form 1File: Form 1.pdf11 Mar 2026
Withdrawal Update Form 2File: Form 2.pdf11 Mar 2026
Withdrawal Update Form 2File: Form 2 Sept 25.pdf11 Mar 2026
Withdrawal Update Form 2File: Form-2.pdf11 Mar 2026
Withdrawal Update Form 3File: Form - 3.pdf11 Mar 2026
Withdrawal Update Form 3File: Form - 3.pdf11 Mar 2026
Withdrawal Update Form 3File: Form 3.pdf11 Mar 2026
Form 5 (FY 2024-2025)File: Form 5.pdf11 Mar 2026
Withdrawal Update Form 1File: Form 1.pdf10 Mar 2026
Withdrawal Update Form 2File: Form 2.pdf10 Mar 2026
Withdrawal Update Form 3File: Form - 3.pdf10 Mar 2026
Form 5 (FY 2019-2020)File: Form 5.pdf10 Mar 2026
Form 5 (FY 2020-2021)File: Form 5.pdf10 Mar 2026
Form 5 (FY 2021-2022)File: Form 5.pdf10 Mar 2026
Form 5 (FY 2022-2023)File: Form - 5.pdf10 Mar 2026
Form 5 (FY 2023-2024)File: FORM -5.pdf10 Mar 2026
Form 1File: Form - 1.pdf8 Jan 2026
Form 2File: Form - 2.pdf8 Jan 2026
Form 3File: Form 3.pdf8 Jan 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold booked inventory.pdf8 Jan 2026
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Unsold.pdf2 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form - 1.pdf8 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf8 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form - 1.pdf8 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form - 1.pdf8 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf8 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form - 2.pdf8 May 2025
Certificates of CA (Form 3)File: Form 3_Sanghvi Parsssva Excellensea.pdf6 May 2025
Building plan approvalFile: Amended Plan part 1.pdf24 Apr 2025
Building plan approvalFile: Amended Plan part 3.pdf24 Apr 2025
Commencement Certificates / NA Order for plotted developmentFile: Further full CC.pdf24 Apr 2025
Building Plan Approval (IOD)File: Amended Plan part 1.pdf24 Apr 2025
Building Plan Approval (IOD)File: Amended Plan part 3.pdf24 Apr 2025
Declaration about Commencement CertificateFile: Declaration about CC.pdf24 Apr 2025
Details of encumbrances concerned to FinanceFile: Declaration for No legal encumbrances.pdf23 Apr 2025
Declaration in FORM BFile: FORM B.pdf23 Apr 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Unsold inventory.pdf23 Apr 2025
Deviation Report with respect to Allotment letterFile: No deviation report for allotment letter.pdf23 Apr 2025
Details of encumbrances concerned to LegalFile: Declaration for No legal encumbrances.pdf23 Apr 2025
Deviation Report with respect to model copy of AgreementFile: No deviation report for sale agreement.pdf23 Apr 2025
Proforma of Agreement for saleFile: Draft Agreement.pdf23 Apr 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest.pdf23 Apr 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Unsold Inventory.pdf3 Apr 2025
Disclosure of sold/ booked inventoryFile: Excellensea 31-03-2024.pdf26 Feb 2025
Disclosure of sold/ booked inventoryFile: Excellensea 30-09-2024.pdf26 Feb 2025
Disclosure of sold/ booked inventoryFile: Excellensea 31-12-2024.pdf26 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form - 2.pdf22 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf22 Feb 2025
Certificates of CA (Form 3)File: Form - 3.pdf5 Feb 2025
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration about RERA Designated Bank.pdf25 Dec 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in Other Real estate Org.pdf25 Dec 2024
Certificates of CA (Form 3)File: FORM - 3.pdf19 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form-2A.pdf19 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM -5.pdf19 Dec 2024
Declaration in FORM BFile: Form B.pdf12 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM - 1.pdf12 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM - 2.pdf12 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM - 2A.pdf12 Jan 2024
Disclosure of sold/ booked inventoryFile: Sold and Unsold Inventory.pdf12 Jan 2024
Certificates of CA (Form 3)File: Form - 3.pdf12 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form - 5.pdf12 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-.pdf18 Apr 2023
Disclosure of sold/ booked inventoryFile: Excellensea Sold-Unsold Inventory.pdf18 Apr 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank Account.pdf12 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A.pdf23 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A.pdf20 Feb 2023
Disclosure of sold/ booked inventoryFile: Disclosure of sold unsold pdf.pdf24 Nov 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 Architects Certificate_Sanghvi Excellensea.pdf21 Nov 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 Engineer Certificate_Sanghvi Excellensea.pdf21 Nov 2022
Certificates of CA (Form 3)File: Form 3 Signed.pdf21 Nov 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 Signed.pdf21 Nov 2022
Commencement Certificates / NA Order for plotted developmentFile: Further CC .pdf10 Oct 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate.pdf9 Mar 2022

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date
ProjectLocationFlatsRegisteredStatusPromisedDelivered
SANGHVI PARSSSVA ETERNITYP51900046223KHETWADI 13TH LANE51Jun 2022OngoingJun 2026Not delivered

Keep SANGHVI PARSSSVA EXCELLENSEA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Charni Road (D ward)

2 kmSANGHVI PARSSSVA EXCELLECompleted 13Lapsed / revoked 24Other 33Dot size: filed unitsN

Filed coordinates, straight-line distance. 70 registered projects within 2 km.

Builder: SANGHVI PARSSSVA ENTERPRISE LLP

SANGHVI PARSSSVA ENTERPRISE LLP has 2 registrations on MahaRERA, including SANGHVI PARSSSVA EXCELLENSEA and SANGHVI PARSSSVA ETERNITY. Its filings disclose 2 earlier MahaRERA projects, none completed yet. Read the full track record.

Frequently asked questions

What are my rights if SANGHVI PARSSSVA EXCELLENSEA is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SANGHVI PARSSSVA EXCELLENSEA?

The registered promoter entity is SANGHVI PARSSSVA ENTERPRISE LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SANGHVI PARSSSVA EXCELLENSEA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SANGHVI PARSSSVA EXCELLENSEA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SANGHVI PARSSSVA EXCELLENSEA?

The professionals named in the filing: Architect: Mandwiwala Qutub Associates; Architect: NARENDRA CHITRODA; Engineer: Ravindra Kumar; Engineer: Sunil Vasant Tayde; Engineer: Mahimtura Consultants Pvt. Ltd.; Chartered Accountant: VSC & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SANGHVI PARSSSVA EXCELLENSEA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SANGHVI PARSSSVA EXCELLENSEA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SANGHVI PARSSSVA EXCELLENSEA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.