Home / Browse projects / SANGHVI PARSSSVA ETERNITY

Registered No litigation declared Others project

SANGHVI PARSSSVA ETERNITY

By SANGHVI PARSSSVA ENTERPRISE LLP

RG-MH-81551 · RERA P51900046223 · Last updated on MahaRERA portal: 1 Aug 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 30 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: .
Dec 2028Possession promisedmoved 30 months from the original
6 of 22Construction stages doneacross 2 buildings; furthest along: Slabs of Super Structure, 35%
22 of 51Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 81 documents Report an error

SANGHVI PARSSSVA ETERNITY is a Others project by SANGHVI PARSSSVA ENTERPRISE LLP in KHETWADI 13TH LANE, 400004, registered with MahaRERA as P51900046223 on 20 Jun 2022. Possession is promised by 31 Dec 2028. The completion date has moved by 30 months from the original filing. 29 of the 51 units on this registration are recorded sold or booked, and 6 of 22 construction stages are filed complete.

At a glance

Project

  • NameSANGHVI PARSSSVA ETERNITY
  • TypeOthers
  • Location
    • K S DAS MARG
    • KHETWADI 13TH LANE
    • 400004
  • Pincode400004
  • RERA no.P51900046223
  • ReraGenie IDRG-MH-81551

Builder

  • NameSANGHVI PARSSSVA ENTERPRISE LLP
  • Entity typePartnership
  • PartnerRISHABH RAMESH SANGHVI
  • Other registrations1 more →
  • Declared earlier projects2 →

Key dates

this monthRegisteredJun 2022First promiseJun 2026Revised toDec 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on20 Jun 2022
  • Promised completion31 Dec 2028
  • Revised completionRevised to 31 Dec 2028 (originally 30 Jun 2026)
  • Buildings2 building records
  • Documents filed81 files

Current status

57%29 of 51 units booked
57.6%Work done, per cost certificate

Figures as on 1 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TOWER - INA191423225
TOWER - IINA181326026

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 1 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 35%.

TOWER - I36%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure35%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises15%
Sanitary Fittings within the flats / premises5%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks35%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.5%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.5%
TOWER - II36%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure35%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises15%
Sanitary Fittings within the flats / premises5%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks35%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.5%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 1 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes15%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,058 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
Manav Builders Pvt LtdMumbai CityMumbai City

Approvals and building plan

Sanctioning authorityMUNICIPAL CORPORATION OF GREATER MUMBAI
Permissible FSI8587.27
Proposed, not sanctioned7,401 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSAMACHARMARG FORT BRANCH, SIR VITHALDAS THACKERSAY TRUST BLDG, FORT, MUMBAI 400001
Estimated costRs 32.62 cr
Cost incurredRs 18.80 cr
Work done57.64%
BuildingWingEstimatedIncurred
TOWER - INARs 17.69 crRs 10.50 cr
TOWER - IINARs 13.90 crRs 8.25 cr
-NARs 1.04 crRs 6.18 lakh

Certifying professionals and partners9

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectB.N. Shah & Associates
ArchitectSkyline Architects
EngineerStruct Bombay Consultant
EngineerSandeep Chandrapal Patil
EngineerSunil Vasant Tayade
Chartered AccountantASHWIN B SHAH & CO
Chartered AccountantVSC & ASSOCIATES
Chartered AccountantPRIYA BAJAJ & ASSOCIATES
Chartered AccountantS. K. MALVIYA & CO.
PartnerRole in project
SANGHVI PARSSSVA ENTERPRISE LLP-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA03072621664Jun 2026 → Dec 2028

Reason as filed by the promoterFollowing the pandemic, the project continued to face challenges due to widespread labour migration, adverse weather conditions, and economic factors. The return of workers to their native regions caused a persistent shortage of skilled manpower, affecting productivity and delaying progress. Unusually heavy monsoon rainfall further hampered on-site activities, reducing effective working days. Additionally, global economic volatility led to a steep escalation in material costs and inflationary pressures, significantly increasing construction and labour expenses. These combined financial and ope

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 26 May 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 26 May 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 26 May 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 26 May 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2028

Documents filed81

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 81 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: RERA Form 1.pdf1 Aug 2026
Withdrawal Update Form 2File: Form 2.pdf1 Aug 2026
Withdrawal Update Form 3File: Form 3.pdf1 Aug 2026
Form 1File: RERA Form 1.pdf1 Jul 2026
Form 2File: RERA Form 2.pdf1 Jul 2026
Form 3File: RERA Form 3.pdf1 Jul 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold and booked inventory.pdf1 Jul 2026
Form 1File: RERA Form 1.pdf1 Jul 2026
Form 2File: RERA Form 2.pdf1 Jul 2026
Form 3File: RERA Form 3.pdf1 Jul 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold and booked Inventory.pdf1 Jul 2026
Form 1File: RERA Form 1.pdf1 Jul 2026
Form 2File: RERA Form 2.pdf1 Jul 2026
Form 3File: RERA Form 3.pdf1 Jul 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold and booked Inventory.pdf1 Jul 2026
Form 1File: RERA Form 1.pdf1 Jul 2026
Form 2File: RERA Form 2.pdf1 Jul 2026
Form 3File: RERA Form 3.pdf1 Jul 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of sold and Booked Inventory.pdf1 Jul 2026
Form 5 (FY 2025-2026)File: Form 5.pdf29 Jun 2026
Form 2A (FY 2024-2025)File: Form 2A March 2025.pdf18 Jun 2026
Form 2A (FY 2025-2026)File: Form 2A March 2026.pdf18 Jun 2026
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form- 3.pdf22 Jul 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form - 3.pdf22 Jul 2025
Disclosure of sold/ booked inventoryFile: Eternity 31-03-2024.pdf26 Feb 2025
Disclosure of sold/ booked inventoryFile: Eternity 30-09-2024.pdf26 Feb 2025
Disclosure of sold/ booked inventoryFile: Eternity 31-12-2024.pdf26 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM -3.pdf20 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM - 2.pdf20 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form - 2A 2019-20.pdf10 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form - 2A 2020-21.pdf10 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form - 2A 2021-22.pdf10 Jan 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A Declaration.pdf23 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SP Eternity - Skyline - Form 1 - Architects Certificate - Nov 2024.pdf19 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM - 5.pdf19 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form -3.pdf4 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf4 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form -2.pdf4 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf4 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A.pdf4 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A.pdf4 Dec 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Unsold Inventory.pdf2 Feb 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Unsold Inventory.pdf2 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf1 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf1 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf1 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5.pdf1 Feb 2024
CERSAI detailsFile: CERSAI_Search_Report_200239668450_For_Asset_Based_Search_14_06_2022_12_00_21_209.pdf14 Jun 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf6 Jun 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf6 Jun 2022
Proforma of Allotment letterFile: Agreement of Sale_compressed.pdf6 Jun 2022
Proforma of Allotment letterFile: Letter of Allotment.pdf27 May 2022
Layout approvalFile: Layout 1.pdf26 May 2022
Layout approvalFile: Layout 2.pdf26 May 2022
Layout approvalFile: Layout 3.pdf26 May 2022
Layout approvalFile: Layout 4.pdf26 May 2022
Layout approvalFile: Layout 5.pdf26 May 2022
Layout approvalFile: Layout 6.pdf26 May 2022
Layout approvalFile: Layout 7.pdf26 May 2022
Layout approvalFile: Layout 7.pdf26 May 2022
Building plan approvalFile: Plan_compressed-1-5.pdf26 May 2022
Building plan approvalFile: Plan-6.pdf26 May 2022
Building plan approvalFile: Plan_compressed-7.pdf26 May 2022
PAN CardFile: PANCARD.pdf26 May 2022
Copy of the legal title reportFile: Title Report.pdf26 May 2022
Details of encumbrancesFile: Encumbrance Certificate.pdf26 May 2022
Copy of Layout Approval (in case of layout)File: Layout 1.pdf26 May 2022
Copy of Layout Approval (in case of layout)File: Layout 2.pdf26 May 2022
Copy of Layout Approval (in case of layout)File: Layout 3.pdf26 May 2022
Copy of Layout Approval (in case of layout)File: Layout 4.pdf26 May 2022
Copy of Layout Approval (in case of layout)File: Layout 5.pdf26 May 2022
Copy of Layout Approval (in case of layout)File: Layout 6.pdf26 May 2022
Copy of Layout Approval (in case of layout)File: Layout 7.pdf26 May 2022
Copy of Layout Approval (in case of layout)File: Layout 7.pdf26 May 2022
Building Plan Approval / NA Order for plotted developmentFile: Plan_compressed-1-5.pdf26 May 2022
Building Plan Approval / NA Order for plotted developmentFile: Plan-6.pdf26 May 2022
Building Plan Approval / NA Order for plotted developmentFile: Plan_compressed-7.pdf26 May 2022
Commencement Certificates / NA Order for plotted developmentFile: cc.pdf26 May 2022
Declaration about Commencement CertificateFile: Declaration for Commencement Certificate.pdf26 May 2022
Declaration in FORM BFile: Form B.pdf26 May 2022

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date
ProjectLocationFlatsRegisteredStatusPromisedDelivered
SANGHVI PARSSSVA EXCELLENSEAP51900020397Charni Road (D ward)16Apr 2019OngoingMar 2026Registered original: Dec 2023Not delivered

Keep SANGHVI PARSSSVA ETERNITY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KHETWADI 13TH LANE

Builder: SANGHVI PARSSSVA ENTERPRISE LLP

SANGHVI PARSSSVA ENTERPRISE LLP has 2 registrations on MahaRERA, including SANGHVI PARSSSVA EXCELLENSEA and SANGHVI PARSSSVA ETERNITY. Its filings disclose 2 earlier MahaRERA projects, none completed yet. Read the full track record.

Frequently asked questions

What are my rights if SANGHVI PARSSSVA ETERNITY is delayed beyond 31 Dec 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SANGHVI PARSSSVA ETERNITY?

The registered promoter entity is SANGHVI PARSSSVA ENTERPRISE LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SANGHVI PARSSSVA ETERNITY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SANGHVI PARSSSVA ETERNITY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SANGHVI PARSSSVA ETERNITY?

The professionals named in the filing: Architect: B.N. Shah & Associates; Architect: Skyline Architects; Engineer: Struct Bombay Consultant; Engineer: Sandeep Chandrapal Patil; Engineer: Sunil Vasant Tayade; Chartered Accountant: ASHWIN B SHAH & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SANGHVI PARSSSVA ETERNITY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SANGHVI PARSSSVA ETERNITY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SANGHVI PARSSSVA ETERNITY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.