Home / Browse projects / Sanghvi Optima

Registered No litigation declared Residential / Group Housing project

Sanghvi Optima

By Suparshwa Homes Private Limited

RG-MH-18615 · RERA P51900077456 · Last updated on MahaRERA portal: 2 Jul 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves.

See what the report covers Free either way: .
May 2028Possession promisedno revision filed
0 of 11Construction stages donefurthest along: Excavation, 60%
0Complaints at MahaRERAon this registration
Jump to the 53 documents Report an error

Sanghvi Optima is a Residential / Group Housing project by Suparshwa Homes Private Limited in Dadar (E), 400014, registered with MahaRERA as P51900077456 on 16 Aug 2024. Possession is promised by 31 May 2028.

At a glance

Project

  • NameSanghvi Optima
  • TypeResidential / Group Housing
  • Location
    • Hindu Colony Road No-3
    • Dadar (E)
    • 400014
  • Pincode400014
  • RERA no.P51900077456
  • ReraGenie IDRG-MH-18615

Builder

  • NameSuparshwa Homes Private Limited
  • Entity typeCompany
  • DirectorsShankesh Prithviraj Sanghvi, Dinesh Babulal Sanghvi, Pakshal Sanghvi, Chintankumar Dineshkumar Sanghavi

Key dates

this monthRegisteredAug 2024PromisedMay 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on16 Aug 2024
  • Promised completion31 May 2028
  • Revised completionNone
  • Buildings1 building record
  • Documents filed53 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Sanghvi OptimaNA150000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 2 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 60%.

Sanghvi Optima: 11% average across the applicable activities

ActivityProgress
Excavation60%
Basement (if any)30%
Podiums (if any)0%
Plinth30%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 2 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyNoNot applicable
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed27

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots27
Closed/Covered27

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area464 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
Ramgumpha Co-Op Housing Society LtdABCD-400001Mumbai City

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI2505.0
Proposed, not sanctioned1,520 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNavsari Building, 240, Dr Dadabhai Naoroji Road, Azad Maidan, Fort, Mumbai - 400001

Certifying professionals and partners

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

PartnerRole in project
Suparshwa Homes Private Limited-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 7 Aug 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 8 Aug 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 8 Aug 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 7 Aug 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 May 2028

Documents filed53

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: Form 1 - Sangvi Optima as on June 2025.pdf2 Jul 2026
Form 2File: Form 2 - Sangvi Optima as on June 2025.pdf2 Jul 2026
Form 3File: Form 3 - Sangvi Optima as on June 2025.pdf2 Jul 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 - Sanghvi optima june 2025.pdf2 Jul 2026
Form 1File: Form 1 - Sanghvi Optima as on Sep 2025.pdf2 Jul 2026
Form 2File: Form 2 - Sanghvi Optima as on Sep 2025.pdf2 Jul 2026
Form 3File: Form 3 - Sanghvi Optima as on Sep 2025.pdf2 Jul 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 - Sanghvi optima sep 2025.pdf2 Jul 2026
Form 1File: Form 1 - Sanghvi Optima as on Dec 2025.pdf2 Jul 2026
Form 2File: Form 2 - Sanghvi Optima as on Dec 2025.pdf2 Jul 2026
Form 3File: Form 3 - Sanghvi Optima as on Dec 2025.pdf2 Jul 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 - Sanghvi optima dec 2025.pdf2 Jul 2026
Form 1File: Form 1 - Sanghvi Optima as on March 2026.pdf2 Jul 2026
Form 2File: Form 2 - Sanghvi Optima as on March 2026.pdf2 Jul 2026
Form 3File: Form 3 - Sanghvi Optima as on March 2026.pdf2 Jul 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 - Sanghvi optima march 2026.pdf2 Jul 2026
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Sanghvi Optima as on March 2025.pdf5 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Sanghvi Optima as on March 2025.pdf5 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Sanghvi Optima as on March 2025.pdf4 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Sanghvi Optima as on December 2024.pdf16 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Sanghvi Optima as on Sep 2024.pdf16 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Sanghvi Optima as on Dec 2024.pdf16 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Sanghvi Optima as on September 2024.pdf16 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Sanghvi Optima as on December 2024.pdf16 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: First Form 3 -Sanghvi Optima_11zon.pdf9 Aug 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Board Resolution - Suparshwa.pdf9 Aug 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A.pdf9 Aug 2024
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format B - Declaration from the bank.pdf9 Aug 2024
Deviation Report with respect to Allotment letterFile: Deviation_AL.pdf9 Aug 2024
Deviation Report with respect to model copy of AgreementFile: Deviation_AFS.pdf9 Aug 2024
Other - TechnicalFile: Annexure A - Order No 50.pdf9 Aug 2024
Layout approvalFile: Layout - Pg 1 (1).pdf8 Aug 2024
Building plan approvalFile: Layout - Pg 1 (1).pdf8 Aug 2024
Building plan approvalFile: Layout - Pg 2 and 3.pdf8 Aug 2024
Building plan approvalFile: Layout - Pg 4 and 5.pdf8 Aug 2024
Copy of Layout Approval (in case of layout)File: Layout - Pg 1 (1).pdf8 Aug 2024
Building Plan Approval / NA Order for plotted developmentFile: Layout - Pg 1 (1).pdf8 Aug 2024
Building Plan Approval / NA Order for plotted developmentFile: Layout - Pg 2 and 3.pdf8 Aug 2024
Building Plan Approval / NA Order for plotted developmentFile: Layout - Pg 4 and 5.pdf8 Aug 2024
Proforma of Agreement for saleFile: AFS_Sanghvi Optima_Suparshwa Homes Pvt Ltd_08082024.pdf8 Aug 2024
Proforma of Allotment letterFile: AL_Sanghvi Optima_Suparshwa Homes Pvt Ltd_08082024.pdf8 Aug 2024
PAN CardFile: Suparshwa Homes PVT ltd Pan card.pdf7 Aug 2024
Copy of the legal title reportFile: Optima Legal Title Report_11zon.pdf7 Aug 2024
Details of encumbrances concerned to FinanceFile: Encumbrance Finance.pdf7 Aug 2024
Details of encumbrances concerned to FinanceFile: Encumbrance Letter - Legal-1.pdf7 Aug 2024
Details of encumbrances concerned to LegalFile: Encumbrance Finance.pdf7 Aug 2024
Details of encumbrances concerned to LegalFile: Encumbrance Letter - Legal-1.pdf7 Aug 2024
Commencement Certificates / NA Order for plotted developmentFile: Optima CC.pdf7 Aug 2024
Declaration about Commencement CertificateFile: Format D.pdf7 Aug 2024
Declaration in FORM BFile: Form B - Promoter.pdf7 Aug 2024
CERSAI detailsFile: Cersai Declaration.pdf7 Aug 2024
Disclosure for secured/unsecured finance availed for the projectFile: Disclosure for secured and unsecured loan.pdf7 Aug 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A - Suparshwa homes.pdf7 Aug 2024

Keep Sanghvi Optima on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Dadar (E)

Builder: Suparshwa Homes Private Limited

Suparshwa Homes Private Limited has 1 registration on MahaRERA, including Sanghvi Optima. Its filings disclose no earlier MahaRERA projects. Read the full track record.

Frequently asked questions

What are my rights if Sanghvi Optima is delayed beyond 31 May 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Sanghvi Optima?

The registered promoter entity is Suparshwa Homes Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Sanghvi Optima?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Sanghvi Optima?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

What should I check before booking in Sanghvi Optima?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Sanghvi Optima. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Sanghvi Optima to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.