Home / Browse projects / Pune, Maharashtra / Samruddhi Park
Samruddhi Park
RG-MH-10200 · RERA P52100005681 · Last updated on MahaRERA portal: 19 Feb 2024
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 22 months past the filed date
- 19 complaints at MahaRERA
- Completion date moved by 72 months
- 3 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Samruddhi Park is a Others project by B. K. Developers in Pune, Maharashtra, registered with MahaRERA as P52100005681 on 11 Aug 2017. Possession was promised by 31 Dec 2024 and is now 22 months past that date. The completion date has moved by 72 months from the original filing. 19 complaints are on record with the regulator.
At a glance
Project
- NameSamruddhi Park
- TypeOthers
- Location
- Pimpale Saudagar
- Haveli
- Pune
- 411027
- Pincode411027
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100005681
- ReraGenie IDRG-MH-10200
Builder
- NameB. K. Developers
- Entity typePartnership
- PartnerBharat Sitaram Kate
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on11 Aug 2017
- Promised completion31 Dec 2024
- Revised completionRevised to 31 Dec 2024 (originally 31 Dec 2018)
- Buildings2 building records
- Documents filed40 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A Wing | NA | 10 | 0 | 0 | 0 | 0 |
| B Wing | NA | 10 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 19 Feb 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
6 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 95%.
A Wing70%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 95% |
| Sanitary Fittings within the flats / premises | 95% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 95% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 95% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 95% |
B Wing70%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 95% |
| Sanitary Fittings within the flats / premises | 95% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 95% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 95% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 95% |
Progress on shared amenities15
As on 19 Feb 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 85% |
| Water Supply | Yes | 80% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 80% |
| Storm Water Drains | Yes | 80% |
| Landscaping & Tree Planting | Yes | 80% |
| Street Lighting | Yes | 75% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 50% |
| Energy managemcnt | Yes | 50% |
| Fire protection and fire safety requirements | Yes | 50% |
| Electrical meter room, sub-station, receiving station | Yes | 80% |
| Aggregate area of recreational Open Space | Yes | 95% |
| Open Parking | Yes | 90% |
Parking filed148
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| A Wing | 38 | 36 | 74 |
| B Wing | 38 | 36 | 74 |
Land and ownership4
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Balasaheb Damuanna Kate | Pimpale Saudagar | Pune |
| Bhagavan Shivram kate | Pimpri Chinchawad (M Corp.) | Pune |
| Dattatray alias Rajesh Gulab Kate | Pimpale Saudagar | Pune |
| BK DEVELOPERS | Pimpale Saudagar | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Yojana Architect |
| Engineer | Gensys Technologies Pvt ltd |
| Partner | Role in project |
|---|---|
| B. K. Developers | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDue to the Pandamic Covid 19 Shortage Of labour, During & after Covid Period All The Banking Process & transactions Got Slower Whitch Resulted In Shortage Of Finance.we were in finacial crisis so we weren't able to complete the said project on given date.there we few unforeseen circumstance whitch led to our finacial crisis.
Reason as filed by the promoterSanction Plan from concerned department has not obtained in time due to Military road, technical, administrative as well as financial liquidity. We are trying to get sanctions in next 6 months and complete the project in the given stipulated time . Please grant us permission for the same .
Reason as filed by the promoterWe want extension to complete the B building as it was delayed for reasons beyond our control and as sanctions were delayed due to military and other administrative purpose . People have accepted possesion of 'A' building 2 years back and we need extension only for 'B' building . We have taken 75% signatures of customers who have given consent for RERA extension. Also last one year we couldnt work on site because of COVID-19 . We are still facing issues of labours because of COVID. We request you to please give us extension so that we complete the project and handover possession to the custome
Complaints filed with MahaRERA19
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000011030 | Shreyas Sangare | Mr Khemchand Uttamchand Bhojwani | 10/02/2018 |
| CC005000000000336 | vishal parasmal khinvasara | Khemchand Uttamchand Bhojwani | 27/09/2017 |
| CC005000000011035 | Chaitanya Suresh Pimpale | Shri Khemchand Uttamchand Bhojwani | 10/02/2018 |
| CC005000000011036 | Mahesh Algamwar | Shri Khemchand Uttamchand Bhojwani | 10/02/2018 |
| CC005000000022034 | SAGAR AGRAWAL | B.K.Developers | 09/10/2018 |
| CC005000000022252 | Vivek Kumar Agrawal | B.K. Developers | 18/11/2018 |
| CC005000000022253 | SACHIN GABHANE | B K Developers | 02/08/2019 |
| CC005000000022276 | Sujit Suresh Bajare | B K Developer | 20/11/2018 |
| CC005000000022258 | Mayur Balasaheb Deore | B. K. Developers | 18/11/2018 |
| CC005000000022263 | Gulshan Shahare | B. K. Developers | 18/11/2018 |
| CC005000000022264 | Pritesh Gujarathi | B.K. Developers | 18/11/2018 |
| CC005000000023341 | Pritesh Gujarathi | B.K. Developers | 18/08/2019 |
| CC005000000022265 | BHUSHAN PURUSHOTTAM WANI | B. K. Developers | 19/11/2018 |
| CC005000000022266 | Sagar Cheke | B.K.Developers | 18/11/2018 |
| CC005000000023347 | Sagar Cheke | B.K.Developers | 20/08/2019 |
| CC005000000022302 | SAMIR SACHDEVA | B. K. Developers | 28/11/2018 |
| CC005000000022273 | Hrishikesh Vishnu Wattamwar | B. K. Developers | 19/11/2018 |
| CC005000000022898 | Akshay Kale | B K Developers | 04/08/2019 |
| CC12500004 | Sagar Subhash Cheke | B. K. Developers | 01/01/2025 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 20 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 31 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 31 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 20 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed40
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 (4) (1) (1).pdf | 19 Feb 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 19 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold.pdf | 19 Feb 2024 |
| Certificates of CA (Form 3)File: FORM 3_compressed (5).pdf | 19 Feb 2024 |
| Certificates of CA (Form 3)File: Form3.pdf | 19 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold .pdf | 8 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: sold.pdf | 25 Dec 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 (4).pdf | 22 Dec 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: samruddhi park Engineer certificate.pdf | 22 Dec 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: BK- Architect Cert.pdf | 6 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Samruddhi park.pdf | 5 Oct 2023 |
| Certificates of CA (Form 3)File: C A B K Developers.pdf | 5 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: bk developer qu sep 23.pdf | 27 Sep 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Scan26092023211146.pdf | 27 Sep 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2 A_removed.pdf | 25 Sep 2023 |
| Disclosure of sold/ booked inventoryFile: B K Developers.pdf | 23 Sep 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 2019-20.pdf | 8 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 2020-21.pdf | 8 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 2021-22.pdf | 8 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Engineer form 2A 2020.pdf | 7 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Engineer form 2A 2021.pdf | 7 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Engineer form 2A 2022.pdf | 7 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: form 5 18-19.pdf | 6 Apr 2023 |
| Disclosure of sold/ booked inventoryFile: sold booked detail.pdf | 20 Mar 2023 |
| Proforma of Agreement for saleFile: Agreement to sale draft.pdf | 20 Mar 2023 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Society formation certificate.pdf | 20 Mar 2023 |
| Annual Audit Report of Statutory CA (Form 5)File: form 5.pdf | 24 Oct 2019 |
| Layout approvalFile: Building Plan Layout.pdf | 31 Jul 2017 |
| Building plan approvalFile: Building plan Approval.pdf | 31 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: Building Plan Layout.pdf | 31 Jul 2017 |
| Building Plan Approval (IOD)File: Building plan Approval.pdf | 31 Jul 2017 |
| Declaration in FORM BFile: Form B B K DEV.pdf | 31 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Certificate BK.PDF | 31 Jul 2017 |
| Certificates of CA (Form 3)File: Crtificate of CA BK.PDF | 31 Jul 2017 |
| PAN CardFile: BK PAN.pdf | 30 Jul 2017 |
| Details of encumbrancesFile: BK Dev NO Encumbrance Cert.PDF | 30 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: BK Engineers Certificate.PDF | 30 Jul 2017 |
| Copy of the legal title reportFile: Legal Title Report.pdf | 20 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf | 20 Jul 2017 |
| Proforma of Allotment letterFile: Agreement to sale BK.pdf | 20 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 40 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Samruddhi Park on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Pimpale Saudagar13,700+ in Pune
Filed coordinates, straight-line distance. 161 registered projects within 2 km.
VANTAGE TWENTY ONE
VIVANTA REALTY
SHAKTI GARDENS
Grandwell Properties and Leasing Private L
24K OPULA
KOLTE-PATIL DEVELOPERS LIMITED
Sukhwani Minerva
Sukhwani Ramchandani LLP
MIDORI TOWER PHASE 4
VIKRAM DEVELOPERS AND PROMOTERS
Sai Aura
WJV LANDMARKS LLP
Builder: B. K. Developers
B. K. Developers has 1 registration on MahaRERA, including Samruddhi Park. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that Samruddhi Park shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Samruddhi Park is delayed beyond 31 Dec 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Samruddhi Park?
The registered promoter entity is B. K. Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Samruddhi Park?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Samruddhi Park?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Samruddhi Park?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Samruddhi Park?
The professionals named in the filing: Architect: Yojana Architect; Engineer: Gensys Technologies Pvt ltd. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Samruddhi Park?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback