Home / Browse projects / Pune, Maharashtra / SALISBURY TOWERS
SALISBURY TOWERS
RG-MH-11231 · RERA P52100003712 · Last updated on MahaRERA portal: 8 Jul 2024
Source: official MahaRERA filing
Red flags
- Completion date moved by 42 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
- All 1 earlier projects delivered on promise
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SALISBURY TOWERS is a Residential / Group Housing project by ATUR INDIA PRIVATE LIMITED in Pune, Maharashtra, registered with MahaRERA as P52100003712 on 6 Aug 2017. The registration is recorded completed; possession was promised by 31 Dec 2025. The completion date has moved by 42 months from the original filing.
At a glance
Project
- NameSALISBURY TOWERS
- TypeResidential / Group Housing
- Location
- Gultekadi
- Haveli
- Pune
- 411037
- Pincode411037
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100003712
- ReraGenie IDRG-MH-11231
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on6 Aug 2017
- Promised completion31 Dec 2025
- Revised completionRevised to 31 Dec 2025 (originally 30 Jun 2022)
- Buildings1 building record
- Documents filed175 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SALISBURY TOWERS | NA | 16 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 8 Jul 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
9 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 99%.
SALISBURY TOWERS: 100% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 99% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 99% |
Progress on shared amenities15
As on 8 Jul 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| M/S ATUR SANGTANI AND ASSOCIATES | Pune (CB) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | RAZZAQ SHAIKH |
| Engineer | SATISH MARATE |
| Partner | Role in project |
|---|---|
| ATUR INDIA PRIVATE LIMITED | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe Construction of the said project is 100% completed and accordingly we have applied for Completion certificate. We have received part completion certificate and full Completion certificate is awaited from the authority.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 30 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 30 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 13 Feb 2019 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 12 May 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 5 Jun 2024
Documents filed175
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 175 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Certificates of CA (Form 3)File: Form-3-ST-30 06 2024-2.pdf | 8 Jul 2024 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: DEED BY LAW_0002-rotated-compressed-2.pdf | 6 Jul 2024 |
| Status of ConveyanceFile: DEED BY LAW_0002-rotated-compressed-2.pdf | 6 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-1-ST-30 06 2024.pdf | 5 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2-ST-30 06 2024.pdf | 5 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form-2A-ST-30 06 2024.pdf | 5 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Inventory-ST-30 06 2024.pdf | 5 Jul 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: Form-4-ST-02 07 2024.pdf | 5 Jul 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 5 Completion Part-5- 05 07 2023.pdf | 5 Jun 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 6 Completion Part -6- 09 10 2023.pdf | 5 Jun 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 7 Completion Part-7- 12 12 2023.pdf | 5 Jun 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 8 Completion part-8- 13 03 2024.pdf | 5 Jun 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 9 Full Completion 31 05 2024.pdf | 5 Jun 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2-ST-31 03 24.pdf | 24 Apr 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 ST 31 03 24.pdf | 23 Apr 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A ST 31 03 24.pdf | 23 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Usold Inven ST 31 03 24.pdf | 23 Apr 2024 |
| Certificates of CA (Form 3)File: Form 3 ST 31 03 24.pdf | 23 Apr 2024 |
| Certificates of CA (Form 3)File: ST-FORM-3_compressed.pdf | 16 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ST- FORM-1.pdf | 15 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ST-FORM-2.pdf | 15 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: ST-FORM-2A.pdf | 15 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: ST -SOLD INVENTORY.pdf | 15 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ST FORM-2-30092023_compressed.pdf | 25 Oct 2023 |
| Certificates of CA (Form 3)File: ST FORM-3-30092023_compressed.pdf | 25 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ST FORM-1-30092023.pdf | 19 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: ST-FORM-2A-30092023.pdf | 19 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: ST Sold Inventory 30092023.pdf | 19 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Rera Form-5 - S Towers-2022-23.pdf | 22 Sep 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-1-ST-30-06-2023.pdf | 14 Jul 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2-ST-30-06-2023_compressed.pdf | 14 Jul 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form-2A-ST-30-06-2023.pdf | 14 Jul 2023 |
| Disclosure of sold/ booked inventoryFile: SoldUnsold InVEN-ST-30-06-2023.pdf | 14 Jul 2023 |
| Certificates of CA (Form 3)File: Form-3-ST-30-06-2023.pdf | 14 Jul 2023 |
| Declaration in FORM BFile: Declaration-Affidavit Form B_compressed.pdf | 6 Jul 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: CC-2015.pdf | 12 May 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: CC-2020.pdf | 12 May 2023 |
| Declaration about Commencement CertificateFile: FORM-D Commencement Declaration.pdf | 12 May 2023 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory.pdf | 12 May 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Form-1 ST-31-03-2023.pdf | 13 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Annaual Report ST- Form 5 CA 31-03-2022.pdf | 13 Apr 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 2 Comp -Part 2 14-10-21.pdf | 13 Apr 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 3 Completion part - 3 02-05-2022.pdf | 13 Apr 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 4 Comp Part 4 19-08-2022.pdf | 13 Apr 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-1-ST-31-03-2023.pdf | 12 Apr 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2-ST-31-03-2023.pdf | 12 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form-2A-ST-31-03-2023.pdf | 12 Apr 2023 |
| Disclosure of sold/ booked inventoryFile: Sold Inven-ST-31-03-2023.pdf | 12 Apr 2023 |
| Certificates of CA (Form 3)File: Form-3-ST-31-03-2023.pdf | 12 Apr 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ST-FORM 1.pdf | 9 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ST-FORM 2.pdf | 9 Jan 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: ST-FORM 2A.pdf | 9 Jan 2023 |
| Disclosure of sold/ booked inventoryFile: ST-SOLD INVENTORY.pdf | 9 Jan 2023 |
| Certificates of CA (Form 3)File: ST-FORM 3_compressed.pdf | 9 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect tower ST_compressed.pdf | 17 Oct 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer certificate atur valley vista_compressed.pdf | 17 Oct 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer certificate Salisbury FORM 2_compressed.pdf | 17 Oct 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Engineer certificate for QA atur valley FORM 2A_compressed.pdf | 17 Oct 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: engineer certificate for QA ST_compressed.pdf | 17 Oct 2022 |
| Disclosure of sold/ booked inventoryFile: salibury tower sold INVENTORY.pdf | 17 Oct 2022 |
| Certificates of CA (Form 5)File: Ca Certificate ST_compressed (1).pdf | 17 Oct 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ST- FORM 1.pdf | 13 Oct 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ST- FORM 2.pdf | 13 Oct 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: ST- FORM-2A.pdf | 13 Oct 2022 |
| Certificates of CA (Form 3)File: ST- FORM-3_compressed.pdf | 13 Oct 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ST-FORM 1.pdf | 12 Jul 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ST-FORM 2.pdf | 12 Jul 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: ST-FORM 2A.pdf | 12 Jul 2022 |
| Disclosure of sold/ booked inventoryFile: ST-FORM 3.pdf | 12 Jul 2022 |
| Disclosure of sold/ booked inventoryFile: ST-FORM 3.pdf | 12 Jul 2022 |
| Certificates of CA (Form 3)File: ST-FORM 3.pdf | 12 Jul 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ST-Form 1-Arch.pdf | 2 May 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ST-Form 2 - Engr_compressed.pdf | 2 May 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: ST-Form 2A.pdf | 2 May 2022 |
| Disclosure of sold/ booked inventoryFile: ST- Sold-Booked Inventory.pdf | 2 May 2022 |
| Certificates of CA (Form 3)File: ST- Form 3- CA_compressed.pdf | 2 May 2022 |
| Certificates of CA (Form 5)File: ST- Form 5 -CA.pdf | 2 May 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form1Arch ST31.pdf | 7 Jan 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form2Engr ST.pdf | 7 Jan 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form2A EngrQA ST.pdf | 7 Jan 2022 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| ATUR PARK | CTS NO11 PART1A 5 KOREGAON ROAD PUNE 411 001 | 14 | Completed | Nov 2016 | Nov 2016 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 175 filed documents as one ZIP, foldered, with a manifest
Keep SALISBURY TOWERS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Gultekadi13,700+ in Pune
Filed coordinates, straight-line distance. 46 registered projects within 2 km.
MAHA TRADE MARKET PH- 2
JAIRAJ REALTY LLP
MAHA TRADE MARKET PH- 1
JAIRAJ REALTY LLP
SOLITAIRE BUSINESS HUB PHASE I, SOLITAIRE WORL
Classic Promoters and Builders Private Lim
SOLITAIRE BUSINESS HUB PHASE II, SOLITAIRE WOR
Classic Promoters and Builders Private Lim
World One Solitaire World
Classic Promoters and Builders Private Lim
HILL TOWN A B AND C WING
HILL TOWN CONSTRUCTIONS
Builder: ATUR INDIA PRIVATE LIMITED
ATUR INDIA PRIVATE LIMITED has 2 registrations on MahaRERA, including SALISBURY TOWERS and ATUR VALLY VISTA WING B. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if SALISBURY TOWERS is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SALISBURY TOWERS?
The registered promoter entity is ATUR INDIA PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SALISBURY TOWERS?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for SALISBURY TOWERS?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SALISBURY TOWERS?
The professionals named in the filing: Architect: RAZZAQ SHAIKH; Engineer: SATISH MARATE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SALISBURY TOWERS?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback