Home / Browse projects / Aurangabad, Maharashtra / SALASAR BLISS
SALASAR BLISS
By RAMESHKUMAR JEETMAL BAGARIA
RG-MH-52104 · RERA P51500034407 · Last updated on MahaRERA portal: 5 Sep 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 48 months
- 3 extensions taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Aurangabad registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SALASAR BLISS is a Others project by RAMESHKUMAR JEETMAL BAGARIA in Aurangabad, Maharashtra, registered with MahaRERA as P51500034407 on 5 Apr 2022. Possession is promised by 31 Dec 2029. The completion date has moved by 48 months from the original filing. 0 of the 53 units on this registration are recorded sold or booked, and 4 of 22 construction stages are filed complete.
At a glance
Project
- NameSALASAR BLISS
- TypeOthers
- Location
- BASSIYEIN NAGAR
- OPP GANGA HOSPITAL
- AURANGABAD
- Aurangabad (M Corp.)
- 431001
- Pincode431001
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51500034407
- ReraGenie IDRG-MH-52104
Builder
- NameRAMESHKUMAR JEETMAL BAGARIA
- Entity typeIndividual
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on5 Apr 2022
- Promised completion31 Dec 2029
- Revised completionRevised to 31 Dec 2029 (originally 31 Dec 2025)
- Buildings2 building records
- Documents filed90 files
Current status
Figures as on 5 Sep 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| TOWER A | NA | 12 | 12 | 40 | 7 | 47 |
| TOWER B | NA | 7 | 6 | 6 | 0 | 6 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 5 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
4 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Stilt Floor, at 90%.
TOWER A66%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 86% |
| Plinth | 85% |
| Stilt Floor | 90% |
| Slabs of Super Structure | 80% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 80% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 87% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 15% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
TOWER B66%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 86% |
| Plinth | 85% |
| Stilt Floor | 90% |
| Slabs of Super Structure | 80% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 80% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 87% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 15% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 5 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 30% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed134
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| TOWER A | NA | Rs 11.79 cr | Rs 10.83 cr |
| TOWER B | NA | Rs 11.79 cr | Rs 10.83 cr |
| - | NA | Rs 1.98 cr | Rs 1.98 lakh |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | MANOJ KALA |
| Engineer | NAMDEV KARKHANE |
| Chartered Accountant | Yash Nagar |
| Chartered Accountant | Pratik Dilip Agrawal And Associates |
| Partner | Role in project |
|---|---|
| RAMESHKUMAR JEETMAL BAGARIA | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterOwing to the absence of bookings, the project is experiencing a slowdown in fund inflow, resulting in delayed progress. In view of this situation, we kindly request an extension to ensure successful completion of the project
Reason as filed by the promotero There are no bookings since start of the project. o Due to lack of demand and bookings, there is a slight slack of funds, which has temporarily impacted the project's progress, Please refer Attached Declaration for detail
Reason as filed by the promoterNA
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 23 Mar 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 23 Mar 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 2 Aug 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 25 Jul 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2029
Documents filed90
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 90 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2A (FY 2025-2026)File: 2A 25-26.pdf | 5 Sep 2026 |
| Withdrawal Update Form 1File: Form 1 2026-27 Q1_.pdf | 14 Jul 2026 |
| Withdrawal Update Form 2File: Form 2 2026-27 Q1.pdf | 14 Jul 2026 |
| Withdrawal Update Form 3File: Form 3 2026-27 Q1.pdf | 14 Jul 2026 |
| Withdrawal Update Form 1File: RERA ARCHITECT CERTIFICATE Q4 DATE 09-04.pdf | 30 Apr 2026 |
| Withdrawal Update Form 1File: RERA ARCHITECT CERTIFICATE Q4 DATE 09-04.pdf | 30 Apr 2026 |
| Withdrawal Update Form 2File: RERA STRUCTURE ENG Q4 CERTIFICATE DATED .pdf | 30 Apr 2026 |
| Withdrawal Update Form 2File: RERA STRUCTURE ENG Q4 CERTIFICATE DATED .pdf | 30 Apr 2026 |
| Withdrawal Update Form 3File: Form 3 CA Certi.pdf | 30 Apr 2026 |
| Withdrawal Update Form 3File: Form 3 CA Certi.pdf | 30 Apr 2026 |
| Form 5 (FY 2025-2026)File: FORM_5.pdf | 30 Apr 2026 |
| Withdrawal Update Form 1File: RERA ARCHITECT CERTIFICATE DATED 09-10-25.pdf | 27 Oct 2025 |
| Withdrawal Update Form 2File: RERA STRUCTURE ENG CERTIFICATE 09-10-2025.pdf | 27 Oct 2025 |
| Withdrawal Update Form 3File: RERA CA CERTIFICATE DATED 15-10-2025 Q2.pdf | 27 Oct 2025 |
| Form 1File: RERA ARCHITECT CERTIFICATE Q1 DATED 08-07-2025.pdf | 26 Aug 2025 |
| Form 2File: RERA STRUCTURE ENG CERTIFICATED Q1 dated 10-07-2025.pdf | 26 Aug 2025 |
| Form 3File: CA_Certificate_Form 3.pdf | 26 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: RERA DISCLOSURE OF SOLD INVENTORY DATED 30-06-2025_1.pdf | 26 Aug 2025 |
| Form 5 (FY 2024-2025)File: Form 5 - Annual Report Statement of Accounts - Chaoveera Infratech..pdf | 26 Jun 2025 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: RERA DECLARATION ABOUT SEPARATE BANK ACCOUNT Q4 DATED 31-03-2025.pdf | 8 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 11 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf | 30 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 2024-25 Q3.pdf | 21 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 2024-25 Q3.pdf | 21 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 2024-25 Q3.pdf | 21 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold.pdf | 11 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 2023-24.pdf | 10 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RERA FORM 3 dated 06-12-2024 Duly signed.pdf | 9 Dec 2024 |
| Declaration in FORM BFile: Form B.pdf | 6 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: RERA FORM 2A M 24.pdf | 6 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA ARCHITECT CERTIFICATE DATED 10-10-2.pdf | 23 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 23 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold.pdf | 23 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 24-25 Q1 .pdf | 12 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 24-25 Q1.pdf | 12 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 23-24 Q4.pdf | 11 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF UNSOLD PROPERTY 30-06.pdf | 11 Jul 2024 |
| Details of encumbrances concerned to FinanceFile: RERA DETAILS OF ENCUMBRANCES CONCERNED TO LEGAL DATED 12-04-24.pdf | 18 Apr 2024 |
| Details of encumbrances concerned to LegalFile: RERA DETAILS OF ENCUMBRANCES CONCERNED TO LEGAL DATED 12-04-24.pdf | 18 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf | 12 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: From 2.pdf | 12 Apr 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: RERA FORM 2A M 23.pdf | 12 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: From 3.pdf | 12 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD AND UNSOLD INVENTORY 31-03-24.pdf | 5 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf | 24 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory.pdf | 24 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Signed_11zon.pdf | 24 Jan 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 ANNUAL REPORT STATEMENT OF ACCOUN.pdf | 5 Dec 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA ARCHITECT CERTIFICATE DATED 10-10-2023_compressed.pdf | 20 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RERA S ENGINEER CERTIFICATE DATED 05-10-2023_compressed.pdf | 20 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: RERA DISCLOSURE OF SOLD - UNSOLD INVENTORY.pdf | 20 Oct 2023 |
| Building plan approvalFile: Epson463_11zon.pdf | 2 Aug 2023 |
| Building plan approvalFile: Epson465_11zon.pdf | 2 Aug 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Epson463_11zon.pdf | 2 Aug 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Epson465_11zon.pdf | 2 Aug 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: BASSIYEIN NAGAR COMMNCEMENT CERTIFICATE FOR REVISED PERMISSION ON 20-07-2023.pdf | 25 Jul 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA ARCHITECT CERTIFICATE TILL 30-06-2023.pdf | 12 Jul 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RERA STRUCTURE ENG CERTIFICATE DATED 30-_compressed.pdf | 12 Jul 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: RERA 22-23 DECLARATION ABOUT SEPERATE BANK ACCOUNT FOR REAL ESTATE PROJECT.pdf | 22 Apr 2023 |
| Deviation Report with respect to Allotment letterFile: RERA 22-23 DEVIATION REPORT WITH RESPECT TO ALLOTMENT LETTER.pdf | 22 Apr 2023 |
| Deviation Report with respect to model copy of AgreementFile: RERA 22-23 DEVIATION REPORT WITH RESPECT TO MODEL COPY OF AGREEMENT.pdf | 22 Apr 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Signed Form 3 MARCH 2023_compressed (1).pdf | 20 Apr 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA_Form 1_compressed.pdf | 18 Apr 2023 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD BOOKED INV 31-03-2023.pdf | 18 Apr 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: DISCLOSURE OF INT IN OTHER REAL ESTATE ORG 04-04-2023.pdf | 18 Apr 2023 |
| Disclosure of sold/ booked inventoryFile: RERA DISCLOSURE UNSOLD INVENTORY 31-12-2022.pdf | 20 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA ARCHITECT CERTIFICATE 10-01-2023.pdf | 23 Jan 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RERA ARCHITECT CERTIFICATE 10-01-2023.pdf | 23 Jan 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RERA STRUCTURAL ENG CERTIFICATE Till 31-12-2022.pdf | 23 Jan 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: DISCLOSURE OF INTREDT IN OTHER REAL ESTATE ORG 31-12-22.pdf | 23 Jan 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: RERA DISCLOSURE UNSOLD INVENTORY 31-12-2022.pdf | 23 Jan 2023 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD AND BOOKED INVENTORY DATED 30-09-2022.pdf | 27 Oct 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA CERTIFICATE ARCHITECT DATED 06-10-22_11zon.pdf | 22 Oct 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RERA STRUCTURAL ENGINEER CERTIFICATE dated 06-10-2022_11zon.pdf | 22 Oct 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA RERA CERTIFICATE DATED 08-08-22_11zon.pdf | 10 Aug 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Cert Compress.pdf | 9 Aug 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Cert Compress.pdf | 9 Aug 2022 |
| Declaration in FORM BFile: Form B.pdf | 25 Mar 2022 |
| Details of encumbrancesFile: encrabance cer.pdf | 24 Mar 2022 |
| Declaration about Commencement CertificateFile: decleration of commencment (2).pdf | 24 Mar 2022 |
| Layout approvalFile: Lay_out_plan.pdf | 23 Mar 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Aurangabad
Computed across the 1,400+ Aurangabad projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 90 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep SALASAR BLISS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near AURANGABAD1,400+ in Aurangabad
Filed coordinates, straight-line distance. 86 registered projects within 2 km.
Capital Trade Centre
KRK Landmark LLP
AQ TOWN
AQ INFRASTRUCTURE PRIVATE LIMITED
KALYANI SAI VISHWA
RAJASHREE UDYOG
AMRUT SAI PLAZA PH 2
Shree Amrut Sai Developer Pvt.Ltd
PRASSANA HIGH CLASS CITY PHASE - I
SHRI KRISHNA NAGAR SAHAKARI GRAH NIRMAN SA
SHRIRAM RESIDENCY
UNIQUE BUILDCON
See every Aurangabad project, with the district possession charts
Builder: RAMESHKUMAR JEETMAL BAGARIA
RAMESHKUMAR JEETMAL BAGARIA has 1 registration on MahaRERA, including SALASAR BLISS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Aurangabad district page.
Frequently asked questions
What are my rights if SALASAR BLISS is delayed beyond 31 Dec 2029?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SALASAR BLISS?
The registered promoter entity is RAMESHKUMAR JEETMAL BAGARIA, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SALASAR BLISS?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for SALASAR BLISS?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SALASAR BLISS?
The professionals named in the filing: Architect: MANOJ KALA; Engineer: NAMDEV KARKHANE; Chartered Accountant: Yash Nagar; Chartered Accountant: Pratik Dilip Agrawal And Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SALASAR BLISS?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback