Red flags
- Litigation declared, 6 cases
- Rs 30.00 crore secured on the land, in favour of Aditya Birla Finance Ltd
Clear
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SAKET WORLD is a Others project by Anand Associates in Thane, Maharashtra, registered with MahaRERA as P51700024797 on 9 Mar 2020. The registration is recorded completed; possession was promised by 30 Jun 2026. 138 of the 159 units on this registration are recorded sold or booked, and 5 of 66 construction stages are filed complete.
At a glance
Project
- NameSAKET WORLD
- TypeOthers
- Location
- Hajimalang Road
- Near Chetana School
- PISAVALI
- Kalyan
- Thane
- 421306
- Pincode421306
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700024797
- ReraGenie IDRG-MH-27976
Builder
- NameAnand Associates
- Entity typePartnership
- GSTIN27AAPFM0496D1Z3
- PartnersKuldeep Panchamprasad Dubey, Sunilkumar Premnarayan Mishra, Vijayprakash Sarjuprasad Mishra, Shailesh Vinod Tiwari, Vinod Ramujagar Tiwari
- Other registrations4 more →
- Completed2 of 5
- No longer live1 lapsed, de-registered or revoked
- Declared earlier projects2 →
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on9 Mar 2020
- Promised completion30 Jun 2026
- Revised completionNone
- Buildings6 building records
- Documents filed111 files
Current status
Figures as on 22 Jan 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Building Type A | NA | 27 | 0 | 159 | 0 | 159 |
| Building Type B | NA | 0 | 0 | 0 | 0 | 0 |
| Building Type C | NA | 0 | 0 | 0 | 0 | 0 |
| Building Type D | NA | 0 | 0 | 0 | 0 | 0 |
| Building Type E, Wing A | NA | 0 | 0 | 0 | 0 | 0 |
| Building Type E, Wing B | NA | 0 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building6
As on 22 Jan 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
5 of 66 construction stages are filed complete across 6 buildings. The stage furthest along is Staircases, at 80%.
Building Type A68%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 50% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 50% |
| Sanitary Fittings within the flats / premises | 15% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 80% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 50% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Building Type B0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Building Type C0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Building Type D0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Building Type E, Wing A0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Building Type E, Wing B0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities17
As on 22 Jan 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 5% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
| Fire Protection And Fire Safety Requirements | Yes | 0% |
| Energy management | Yes | 0% |
Parking filed228
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership2
MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
| Landowner | Village | District |
|---|---|---|
| Govind Dunda Shisve & Others | PISAVALI | Thane |
| Saguna Hari Gaikwad & Others | PISAVALI | Thane |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Building Type A | NA | Rs 35.83 cr | Rs 33.80 cr |
| - | NA | Rs 5.89 cr | Rs 1.47 cr |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | DMD Architects |
| Engineer | ACME Management Solutions & Value Engineering |
| Engineer | ABHINEET BAJPAI |
| Chartered Accountant | Attar & Associates |
| Chartered Accountant | M F ATTAR |
| Partner | Role in project |
|---|---|
| Anand Associates | - |
Litigation declared6
| Case | Court | Status |
|---|---|---|
| 349/2015/2015 | Civil Judge Senior Division Kalyan | Ongoing |
| 143/2019/2019 | Civil Judge Junior Division Kalyan | Ongoing |
| 144/2019/2019 | Civil Judge Junior Division Kalyan | Ongoing |
| 154/2019/2019 | Civil Judge Junior Division Kalyan | Ongoing |
| 43/2021/2021 | Civil Judge Junior Division Kalyan | Ongoing |
| 349/2015/2015 | Civil Judge Senior Division Kalyan | Ongoing |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 9 Aug 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 19 Jun 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 19 Jun 2021 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 19 Jun 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 16 Oct 2024
Documents filed111
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 111 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AA Bldg B Form 1 dt 31 12 24.pdf | 22 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: AA Bldg B Form 3 dt 31 12 24_compressed.pdf | 22 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: AA Bldg B Form 2 dt 31 12 24.pdf | 22 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: AA Bldg B Sold Unsold Inventory dt 31 12 24.pdf | 22 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Bldg A Form 5.pdf | 10 Dec 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: Architect Certificate Form 4 Bldg A.pdf | 16 Oct 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Bldg A Occupancy Certificate dt 12 07 2024.pdf | 16 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Building Type A Form 5.pdf | 21 Mar 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sold booked unsold inventory.pdf | 10 Jul 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Building Type A Form 3.pdf | 10 Jul 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Building Type A_compressed.pdf | 10 Jul 2023 |
| Disclosure of sold/ booked inventoryFile: Building Type A Sold Unsold Inventory- ok_compressed (1).pdf | 6 May 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Saket world Building Type A- ok_compressed.pdf | 6 May 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FY 2019-20 - Form 5.pdf | 28 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Building Type A - Form 5.pdf | 31 Jan 2023 |
| Disclosure of sold/ booked inventoryFile: Disclosure Bldg A compressed.pdf | 26 Dec 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: BUILDING TYPE A FORM 3_compressed.pdf | 26 Dec 2022 |
| Disclosure of sold/ booked inventoryFile: Form 3 Bldg A.pdf | 20 Sep 2022 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold unit Bldg A.pdf | 20 Sep 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Bldg A.pdf | 20 Sep 2022 |
| Disclosure of sold/ booked inventoryFile: A Sold Unsold Inventory.pdf | 26 Aug 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: A FORM 3.pdf | 26 Aug 2022 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sold unsold inventory Building type A.pdf | 9 May 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Building Type A.pdf | 9 May 2022 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Society Registration Document Building Type A.pdf | 9 May 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Quality Assurance Certificate Building Type A.pdf | 5 May 2022 |
| CERSAI detailsFile: CERSAI Report 1.pdf | 5 May 2022 |
| CERSAI detailsFile: CERSAI Report.pdf | 5 May 2022 |
| Disclosure of sold/ booked inventoryFile: BLDG TYPE A SOLD UNSOLD LIST compressed.pdf | 13 Apr 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: BLDG TYPE A Form 3 compressed.pdf | 13 Apr 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: CA Form 5.pdf | 15 Mar 2022 |
| CERSAI detailsFile: Cersai Declaration - Building Type A.pdf | 3 Dec 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Engineer Form 2A on Quality Assurance.pdf | 25 Nov 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Disclosure of sold booked Inventory- Building Type A.pdf | 25 Nov 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Building Type A Engineer Certificate on Quality Assurance Form 2A.pdf | 25 Nov 2021 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sold booked Inventory- Building Type A.pdf | 24 Nov 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Form 3.pdf | 24 Nov 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Engineers Form 2A.pdf | 17 Aug 2021 |
| Copy of the legal title reportFile: Title_compressed.pdf | 9 Aug 2021 |
| Proforma of Allotment letterFile: Revised Draft sale agreement A - new.pdf | 9 Aug 2021 |
| OtherFile: Declaration regarding Independent RERA number.pdf | 9 Aug 2021 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold- Booked- Unsold Inventory.pdf | 21 Jul 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Type A.pdf | 16 Jul 2021 |
| Proforma of Allotment letterFile: Revised Draft sale agreement.pdf | 23 Jun 2021 |
| Declaration about Commencement CertificateFile: Declaration about Commencement Certificate- Format D.pdf | 22 Jun 2021 |
| Building plan approvalFile: Building Type A- Plan 2.pdf | 19 Jun 2021 |
| Building plan approvalFile: Building Type A- Plan 3.pdf | 19 Jun 2021 |
| Building plan approvalFile: Building Type A -Plan 4.pdf | 19 Jun 2021 |
| Building plan approvalFile: Building Type A- Plan 5.pdf | 19 Jun 2021 |
| Building plan approvalFile: Building Type A- Plan 6.pdf | 19 Jun 2021 |
| Building plan approvalFile: Building Type A- Plan 7.pdf | 19 Jun 2021 |
| Building plan approvalFile: Building Type B- Plan 8.pdf | 19 Jun 2021 |
| Building plan approvalFile: Building Type B- Plan 9.pdf | 19 Jun 2021 |
| Building plan approvalFile: Building Type B- Plan 10.pdf | 19 Jun 2021 |
| Building plan approvalFile: Building Type B- Plan 11.pdf | 19 Jun 2021 |
| Building plan approvalFile: Building Type B- Plan 12.pdf | 19 Jun 2021 |
| Layout approvalFile: AA-2nd Revision- Building Type A - Layout Plan-1.pdf | 19 Jun 2021 |
| Copy of Layout Approval (in case of layout)File: AA-2nd Revision- Building Type A - Layout Plan-1.pdf | 19 Jun 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: Building Type A- Plan 2.pdf | 19 Jun 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: Building Type A- Plan 3.pdf | 19 Jun 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: Building Type A -Plan 4.pdf | 19 Jun 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: Building Type A- Plan 5.pdf | 19 Jun 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: Building Type A- Plan 6.pdf | 19 Jun 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: Building Type A- Plan 7.pdf | 19 Jun 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: Building Type B- Plan 8.pdf | 19 Jun 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: Building Type B- Plan 9.pdf | 19 Jun 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: Building Type B- Plan 10.pdf | 19 Jun 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: Building Type B- Plan 11.pdf | 19 Jun 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: Building Type B- Plan 12.pdf | 19 Jun 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf | 19 Jun 2021 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold- Booked- Unsold Inventory compressed.pdf | 27 May 2021 |
| OtherFile: Disclosure of Sold- Booked- Unsold Inventory compressed.pdf | 30 Apr 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: AA CA Form 3.pdf | 16 Jan 2021 |
| Details of Restarting of Construction work post lockdownFile: Restarting Construction Post Lockdown.pdf | 28 Aug 2020 |
| OtherFile: Declaration Plot Area.pdf | 28 Aug 2020 |
| OtherFile: Declaration BuiltUp Area.pdf | 28 Aug 2020 |
| OtherFile: Declaration Cost of Construction.pdf | 28 Aug 2020 |
| Proforma of Allotment letterFile: Allotment ltr.pdf | 27 Aug 2020 |
| Proforma of Allotment letterFile: AA Sale Agreement final.pdf | 27 Aug 2020 |
| Layout approvalFile: Layout -1.pdf | 11 Aug 2020 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Saket Paradise | Saket Paradise Near Adharwadi Jail Road Kalyan West 421301 | 340 | Completed | Nov 2012 | Late, Nov 2012 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 4 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 111 filed documents as one ZIP, foldered, with a manifest
Keep SAKET WORLD on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Near Chetana School7,600+ in Thane
Filed coordinates, straight-line distance. 179 registered projects within 2 km.
Kohinoor Eden
KGI REALTY PRIVATE LIMITED
Olympia City Phase 1
Balaji Rattan Lifespaces
Krishna Trident
Sonawane Infrastructure Private Limited
Rai s Heaven
RAI RESIDENCY Private Limited
Metro Grande Tower C and D
West Pioneer Properties India Pvt Ltd
SEASON SAHARA BUILDING NO 4 AND 5
SAMARTH SAI BUILDERS & DEVELOPERS
See every Thane project, with the district possession charts
Builder: Anand Associates
ANAND ASSOCIATES has 5 registrations on MahaRERA, including SHREE BALAJI RESIDENCY and ANAND BLOSSOM. Its filings disclose 2 earlier MahaRERA projects: declares 0 of 2 past projects completed on time. Litigation is declared on 3 of its registrations. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What are my rights if SAKET WORLD is delayed beyond 30 Jun 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SAKET WORLD?
The registered promoter entity is Anand Associates, a partnership as per the filing. Its GSTIN 27AAPFM0496D1Z3 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SAKET WORLD?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for SAKET WORLD?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SAKET WORLD?
The professionals named in the filing: Architect: DMD Architects; Engineer: ACME Management Solutions & Value Engineering; Engineer: ABHINEET BAJPAI; Chartered Accountant: Attar & Associates; Chartered Accountant: M F ATTAR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SAKET WORLD?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback