Home / Browse projects / Thane, Maharashtra / Metro Grande Tower C and D

Completed Litigation declared Residential / Group Housing project

Metro Grande Tower C and D

By West Pioneer Properties India Pvt Ltd

RG-MH-24693 · RERA P51900004149 · Last updated on MahaRERA portal: 17 Jun 2025

Source: official MahaRERA filing

Red flags

  • Litigation declared, 1 case
  • 1 complaint at MahaRERA
  • Completion date moved by 6 months
  • 1 extension taken

Clear

  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Jun 2025Possession promisedregistration recorded completed
22 of 22Construction stages doneacross 2 buildings; every applicable stage filed complete
140 of 414Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 173 documents Report an error

Metro Grande Tower C and D is a Residential / Group Housing project by West Pioneer Properties India Pvt Ltd in Thane, Maharashtra, registered with MahaRERA as P51900004149 on 8 Aug 2017. The registration is recorded completed; possession was promised by 30 Jun 2025. The completion date has moved by 6 months from the original filing. 274 of the 414 units on this registration are recorded sold or booked, and 22 of 22 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameMetro Grande Tower C and D
  • TypeResidential / Group Housing
  • Location
    • Kalyan Shill Road
    • Metro Junction Mall
    • NETIVALI
    • Kalyan
    • Thane
    • 421306
  • Pincode421306
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900004149
  • ReraGenie IDRG-MH-24693

Builder

  • NameWest Pioneer Properties India Pvt Ltd
  • Entity typeCompany
  • Sr DirectorNitin Vasant Mhatre
  • Declared earlier projects2 →

Key dates

this monthRegisteredAug 2017First promiseDec 2024Revised toJun 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on8 Aug 2017
  • Promised completion30 Jun 2025
  • Revised completionRevised to 30 Jun 2025 (originally 30 Dec 2024)
  • Buildings2 building records
  • Documents filed173 files

Current status

66%274 of 414 units booked

Figures as on 17 Jun 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower CNA32282060206
Tower DNA32292062208

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 17 Jun 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

22 of 22 construction stages are filed complete across 2 buildings.

Tower C100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Tower D100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities16

As on 17 Jun 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes95%
Water SupplyYes80%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes95%
Street LightingYes95%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingNoNot applicable
Club HouseYes100%

Parking filed387

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots387
Closed/Covered387
BuildingClosed/CoveredTotal
Tower C193193
Tower D194194

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area8,937 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on26 Jun 2025

Approvals and building plan

Sanctioning authorityKalyan Dombivali Municipal Corporation
Permissible FSI32466.2
Proposed, not sanctioned32,466 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchOne Indiabulls Centre 3rd floor Mumbai 400013

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNirmaan Architects
ArchitectLewis & Hickey Design
EngineerAbrar Ali Sayed
Chartered AccountantRavi A Shah & Associates Chartered Accountants
Chartered AccountantF R G Company Chartered Accountants
PartnerRole in project
West Pioneer Properties India Pvt Ltd-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700024408Dec 2024 → Jun 2025

Reason as filed by the promoterDear Sir, 1. This is to inform you that we have obtained the captioned registration certification bearing no. P51900004149 in respect of our Project Metro Grande (comprising of 2 towers i.e. Tower C & Tower D). 2. Said 2 towers (Tower C & Tower D) have common podium parking & other amenities. We have completed Tower C in all respect & have obtained occupancy certificate for Tower C on 5th June 2023. We have also completed the podium, parking & amenities which are common to both Tower C & Tower D. We are enclosing herewith the copy of OC for Tower C & photographs showing present status of podiu

Litigation declared1

CaseCourtStatus
44/2011KalyanOngoing

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC006000000197179Mahesh Laxman BurangeM/s. West Pioneer Properties (India) Pvt. Ltd.08/06/2021

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Mar 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 30 Mar 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 30 Jun 2023

Documents filed173

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 173 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupational CertificateFile: Occupancy Certificate for Tower C dated 5th June 2023.pdf17 Jun 2025
Occupational CertificateFile: Occupancy Certificate for Tower D dated 20th May 2025.pdf17 Jun 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Ar Certificate Form 1 for Tower C and D for Period Jan 25 to March 25 dated 9th April19 Apr 2025
Certificates of CA (Form 3)File: Rera CA certificate Form 3 For Jan 25 to March 25 dated 10th April 2025-compressed.pdf19 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA Engineer Certificate Form 2 Jan 25 to March 25 dated 12th April 2025-compressed.pdf19 Apr 2025
Form 2AFile: RERA Engineer Certificate form 2A for period Jan 25 to March 25 dated 12th April 2025-comp19 Apr 2025
Disclosure of sold/ booked inventoryFile: RERA Sold Booked unsold inventory Tower C and D dated 31st March 2025 pdf-compressed.pdf19 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Ar Certificate Form 1 for Tower C and D for Period Oct 24 to Dec 24 dated 2nd Jan 20224 Jan 2025
Certificates of CA (Form 3)File: Rera CA certificate Form 3 For Oct 24 to Dec 24 dated 9th Jan 2025-compressed.pdf24 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA Engineer Certificate Form 2 OCt 24 to Dec 24 dated 10th Jan 2025-compressed.pdf24 Jan 2025
Form 2AFile: RERA Engineer Certificate form 2A for period Oct 24 to Dec 24 dated 10th Jan 2025-compress24 Jan 2025
Disclosure of sold/ booked inventoryFile: RERA Sold Booked unsold inventory Tower C and D dated 31st Dec 2024pdf-compressed.pdf24 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Ar Certificate Form 1 for Tower C and D for Period July 24 to Sep 24 dated 10th Oct 24 Nov 2024
Certificates of CA (Form 3)File: Rera CA certificate Form 3 For July 24 to Sep 24 dated 10th Oct 2024.pdf4 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA Engineer Certificate Form 2 July 24 to Sep 24 dated 10th Oct 2024.pdf4 Nov 2024
Form 2AFile: RERA Engineer Certificate form 2A for period July 24 to Sep 24 dated 10th Oct 2024.pdf4 Nov 2024
Disclosure of sold/ booked inventoryFile: RERA Sold Booked unsold inventory Tower C and D dated 30th Sep 2024pdf.pdf4 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: RERA CA Certificate Form 5 For April 22 to March 23 dated 4th Sep 2023.pdf24 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: RERA CA Certificate Form 5 For April 23 to March 24 dated 20 August 2024.pdf24 Oct 2024
Declaration in FORM BFile: Affidavit cum Declaration Form B revised dated 12th Aug 2024.pdf13 Aug 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Ar Certificate Form 1 for Tower C and D for Period April 24 to June 24 dated 11th Jul16 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA Engineer Certificate Form 2 April 24 to June 24 dated 10th July 2024.pdf16 Jul 2024
Form 2AFile: RERA Engineer Certificate form 2A for period April 24 to June 24 dated 10th July 2024.pdf16 Jul 2024
Disclosure of sold/ booked inventoryFile: RERA Sold Booked unsold inventory Tower C and D dated 30th June 2024pdf.pdf16 Jul 2024
Certificates of CA (Form 3)File: Rera CA certificate Form 3 For April 24 to June 24 dated 8th July 2024.pdf16 Jul 2024
Disclosure of sold/ booked inventoryFile: RERA Sold Booked unsold inventory Tower C and D dated 31st March 2024 pdf.pdf8 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Ar Certificate Form 1 for Tower C and D for Period Jan 24 to March 24 dated 10th Apri22 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA Engineer Certificate Form 2 Jan 24 to March 24 dated 10th April 2024.pdf22 Apr 2024
Form 2AFile: RERA Engineer Certificate Form 2A Jan 24 to March 24 dated 10th April 24.pdf22 Apr 2024
Certificates of CA (Form 3)File: Rera CA certificate Form 3 For Jan 24 to April 24 dated 10th April 2024.pdf22 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Ar Certificate Form 1 for Tower C and D for Period Oct 23 to Dec 23 dated 11 th Jan 218 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA Engineer Certificate Form 2 Oct 23 to Dec 23 dated 11th Jan 2024.pdf18 Jan 2024
Form 2AFile: RERA Engineer Certificate Form 2A Oct 23 to Dec 23 dated 11th jan 24.pdf18 Jan 2024
Disclosure of sold/ booked inventoryFile: RERA Sold Booked unsold inventory Tower C and D dated 31st Dec 2023 pdf.pdf18 Jan 2024
Certificates of CA (Form 3)File: Rera CA certificate Form 3 For Oct 23 to Dec 23 dated 11th Jan 2024.pdf18 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Ar Certificate form 1 for Tower C and D for period July 23 to Sep 23 dated 10 oct 20225 Oct 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA Engineer Certificate form 2 for July 23 to Sep 23 dated 13 Oct 23.pdf25 Oct 2023
Form 2AFile: RERA Enginner Cerificate form 2A for period July 23 to Sep 23 dated 13 Oct 23.pdf25 Oct 2023
Disclosure of sold/ booked inventoryFile: RERA Sold Booked unsold inventory Tower C and D dated 30 Sep 2023pdf.pdf25 Oct 2023
Certificates of CA (Form 3)File: RERA CA Certificate form 3 for period July 23 to Sep 23 dated 17 oct 2023.pdf25 Oct 2023
Certificates of CA (Form 5)File: RERA CA Certificate Form 5 For April 22 to March 23 dated 4th Sep 2023.pdf13 Sep 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Ar Certificate Form 1 for Tower C and D for Period April 23 to June 23 dated 7th July19 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA Engineer Certificate Form 2 April 23 to June 23 dated 13 july 2023.pdf19 Jul 2023
Form 2AFile: RERA Engineer Certificate Form 2A for period April 23 to June 23 dated 13 July 2023.pdf19 Jul 2023
Disclosure of sold/ booked inventoryFile: RERA Sold Booked unsold inventory Tower C and D dated 5 th July 2023.pdf19 Jul 2023
Certificates of CA (Form 3)File: Rera CA certificate Form 3 For April 23 to June 23 dated 13th July 2023.pdf19 Jul 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupancy Certificate for Tower C dated 5 June 23.pdf30 Jun 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Ar Certificate Form 1 for Tower C and D for Period Jan 23 to March 23 dated 6th April17 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA Engineer Certificate Form 2 Jan 23 to March 23 dated 10th April 2023.pdf17 Apr 2023
Form 2AFile: RERA Engineer Certificate Form 2A Jan 23 to March 23 dated 10 th April 2023.pdf17 Apr 2023
Disclosure of sold/ booked inventoryFile: RERA Sold Booked unsold inventory Tower C and D dated 2 April 2023pdf.pdf17 Apr 2023
Certificates of CA (Form 3)File: Rera CA certificate Form 3 For Jan 23 to March 23 dated 8th April 2023.pdf17 Apr 2023
Layout approvalFile: Revised Layout.pdf30 Mar 2023
Copy of Layout Approval (in case of layout)File: Revised Layout.pdf30 Mar 2023
Commencement Certificates / NA Order for plotted developmentFile: Revised Commencement Certificate.pdf30 Mar 2023
Disclosure of sold/ booked inventoryFile: RERA Sold Booked unsold inventory Tower C and D dated 5 Jan 2023 pdf.pdf17 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Ar Certificate Form 1 for Tower C and D for Period July Oct 22 to Dec 22 dated 5 th J13 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA Engineer Certificate Form 2 Oct 22 to Dec 22 dated 11 th Jan 2023.pdf13 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: RERA Engineer Certificate Form 2A Oct 22 to Dec 22 dated 11th Jan 2023.pdf13 Jan 2023
Certificates of CA (Form 3)File: RERA CA Certificate Form 3 For Oct 22 to Dec 22 dated 12 th Jan 2023.pdf13 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: RERA CA Certificate Form 5 For April 21 to March 22 dated 28th Sep 2022.pdf10 Jan 2023
Proforma of Agreement for saleFile: RERA Proforma Agreement for Sale Tower D.pdf10 Jan 2023
OtherFile: RERA reply in Notice in non submission of documents Form 5 dated 9 Jan 23.pdf10 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Ar Certificate Form 1 for Tower C and D for Period July 22 to Sep 22 dated 7 th Oct 227 Oct 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA Engineer Certificate form 2 for July 22 to Sep 22 dated 12 Oct 2022.pdf22 Oct 2022
Form 2AFile: RERA Engineer Certificate Form 2A for Period July 22 to Sep 22 dated 12 Oct 2022.pdf22 Oct 2022
Disclosure of sold/ booked inventoryFile: RERA Sold Booked unsold inventory Tower C and D dated 30 Sep 2022pdf.pdf22 Oct 2022
Certificates of CA (Form 3)File: RERA CA Certificate Form 3 for Period July 22 to Sep 22 dated 10 Oct 2022.pdf22 Oct 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: RERA CA Certificate Form 5 For April 21 to March 22 dated 28th Sep 2022.pdf29 Sep 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Ar Certificate Form 1 for Tower C and D for Period April 22 to June 22 dated 6th July12 Jul 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA Engineer Certificate Form 2 April 22 to June 22 dated 11 july 2022.pdf12 Jul 2022
Form 2AFile: RERA Engineer Certificate Form 2A April 22 to June 22 dated 11th july 2022.pdf12 Jul 2022
Disclosure of sold/ booked inventoryFile: RERA Sold Booked unsold inventory Tower C and D dated 5th July 2022pdf.pdf12 Jul 2022
Certificates of CA (Form 3)File: RERA CA Certificate Form 3 for April 22 to June 22 dated 9 July 2022.pdf12 Jul 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Ar Certificate Form 1 for Tower C and D for Period Jan 22 to March 22 dated 5 April 220 Apr 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Engineer Certificate Form 2 for Jan 22 to March 22 dated 14 April 2022.pdf20 Apr 2022
Form 2AFile: RERA Engineer Certificate form 2A for period Jan 22 to March 22 dated 14 April 2022.pdf20 Apr 2022
Disclosure of sold/ booked inventoryFile: RERA Sold Booked unsold inventory Tower C and D dated 14th April 2022pdf.pdf20 Apr 2022
Certificates of CA (Form 3)File: RERA CA Certificate Form 3 for Jan 22 to March 22 dated 14 April 2022.pdf20 Apr 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Ar Certificate Form 1 for Tower C and D for Period Oct 21 to Dec 21 dated 3 rd Jan 2011 Jan 2022

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Metro PlazaNetivali kalyan Shil Road Kalyan 421 306105CompletedMar 2014Late, Jul 2017
Metro ResidencyNetivali Kalyan Shil Road Kalyan 421 306356CompletedJun 2012Late, Jul 2017

How this compares with Thane

66%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 6 months
23%of Thane registrations have lapsed or been cancelledthis one is completed

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Metro Grande Tower C and D on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Metro Junction Mall7,600+ in Thane

2 kmMetro Grande Tower C andCompleted 50Lapsed / revoked 37Other 84Dot size: filed unitsN

Filed coordinates, straight-line distance. 171 registered projects within 2 km.

Builder: West Pioneer Properties India Pvt Ltd

West Pioneer Properties India Pvt Ltd has 1 registration on MahaRERA, including Metro Grande Tower C and D. Its filings disclose 2 earlier MahaRERA projects: declares 0 of 2 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if Metro Grande Tower C and D is delayed beyond 30 Jun 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Metro Grande Tower C and D?

The registered promoter entity is West Pioneer Properties India Pvt Ltd, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Metro Grande Tower C and D?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Metro Grande Tower C and D?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Metro Grande Tower C and D?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Metro Grande Tower C and D?

The professionals named in the filing: Architect: Nirmaan Architects; Architect: Lewis & Hickey Design; Engineer: Abrar Ali Sayed; Chartered Accountant: Ravi A Shah & Associates Chartered Accountants; Chartered Accountant: F R G Company Chartered Accountants. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Metro Grande Tower C and D?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Metro Grande Tower C and D. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Metro Grande Tower C and D to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.