Home / Developers / ANAND ASSOCIATES
ANAND ASSOCIATES: RERA track record
GSTIN 27AAPFM0496D1Z3 · Partnership · attribution by exact filing name, entity resolution in progress
ANAND ASSOCIATES has 5 registrations on MahaRERA, including SHREE BALAJI RESIDENCY and ANAND BLOSSOM. Its filings disclose 2 earlier MahaRERA projects: declares 0 of 2 past projects completed on time. Litigation is declared on 3 of its registrations.
Projects by this developer
Showing all 5 projects.
Largest first, by the unit count in the filing.
| Project | Location | Units | Booked | Registered | Status |
|---|---|---|---|---|---|
| SAKET WORLDP51700024797 | Near Chetana School, Thane, 421306 | 159 | 87% | 9 Mar 2020 | Completed |
| ANAND BLOSSOMP51600010120 | Nashik (M Corp.), Nashik, 422010 | - | - | 24 Aug 2017 | Registration lapsed |
| SAKET WORLDP51700030224 | Near Chetana School, Thane, 421306 | - | - | 5 Aug 2021 | Registered |
| SAKET WORLD BUILDING TYPE CP51700032180 | Near Chetana School, Thane, 421306 | - | - | 14 Dec 2021 | Registered |
| SHREE BALAJI RESIDENCYP49600000050 | BALAJI TOWNSHIP, Dadra & Nagar Haveli, 396230 | - | - | 11 Apr 2018 | Completed |
What this promoter declares as its own experience
ANAND ASSOCIATES declares experience on 2 earlier projects. None of them carries a registration number we could match on MahaRERA, which is usual for work done before the register existed.
From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| Saket Paradise | 1 Nov 2012 | 20 Nov 2012 | +1 months |
| BALAJI RESIDENCY | 1 May 2014 | 8 Feb 2016 | +21 months |
Frequently asked questions
How do I verify ANAND ASSOCIATES as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. Cross-check its GSTIN 27AAPFM0496D1Z3 on the MCA and GST portals before signing anything. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with ANAND ASSOCIATES?
Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
Does the declared litigation make ANAND ASSOCIATES unsafe to buy from?
Not by itself. Litigation on a registration ranges from a boundary dispute to an allottee case about delay; what matters is the case type, which court or forum, and whether it touches the land title of the project you are buying. The case list is in each project's filed documents. Treat litigation as a question to resolve in writing before booking, not as a verdict either way.
Spotted a project attributed to the wrong developer, or something else wrong on this page? Projects are grouped by the promoter name as filed, so a firm that registers under two spellings can split across two pages. Tell us and we will check it against the filings.
Report an errorShare feedbackData from official MahaRERA filings. How we handle corrections is on the about page.