Home / Browse projects / Raigarh, Maharashtra / Sakasi Park III
Sakasi Park III
By Jindal Builders and Developers
RG-MH-21732 · RERA P52000023426 · Last updated on MahaRERA portal: 12 Dec 2024
Source: official MahaRERA filing
Red flags
- 1 complaint at MahaRERA
Clear
- No litigation declared
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
- All 4 earlier projects delivered on promise
1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Sakasi Park III is a Residential / Group Housing project by Jindal Builders and Developers in Raigarh, Maharashtra, registered with MahaRERA as P52000023426 on 12 Dec 2019. The registration is recorded completed; possession was promised by 30 Dec 2023. 1 complaint is on record with the regulator.
At a glance
Project
- NameSakasi Park III
- TypeResidential / Group Housing
- Location
- Near Kakaji Vadi
- Akurli
- Panvel
- Raigarh
- 410206
- Pincode410206
- RERA no.P52000023426
- ReraGenie IDRG-MH-21732
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on12 Dec 2019
- Promised completion30 Dec 2023
- Revised completionNone
- Buildings3 building records
- Documents filed47 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Building 1 | NA | 5 | 0 | 0 | 0 | 0 |
| Building 2 | NA | 5 | 0 | 0 | 0 | 0 |
| Building 3 | NA | 5 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 12 Dec 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
30 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Podiums (if any), at 0%.
Building 191%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building 291%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building 391%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 12 Dec 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed1
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | AN Arch |
| Engineer | Structcon |
| Chartered Accountant | Vallabh Joshi |
| Partner | Role in project |
|---|---|
| Jindal Builders and Developers | - |
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12504095 | Suhas Jadhav | Jindal Builders and Developers | 20/11/2025 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 7 Dec 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 7 Dec 2019 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 7 Dec 2019 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 7 Dec 2019Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 30 Mar 2023
Documents filed47
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect’s Certificate on Completion of Project (Form 4)File: Form 4 JBD Akurli.pdf | 12 Dec 2024 |
| OtherFile: Screenshot from NAINA to PMC.pdf | 12 Dec 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: Form 4 JBD Akurli.pdf | 8 Nov 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Sakasi Park III FY 22 23.pdf | 19 Aug 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A Sakasi Park III.pdf | 10 Apr 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: BP 383 OCC Order.pdf | 30 Mar 2023 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Sakasi Park III Soc Reg Certificate.pdf | 22 Mar 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC G no 16.pdf | 28 Dec 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: JBD Akurli Form 5_compressed.pdf | 13 Oct 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: JBD Akurli Form 5_compressed.pdf | 22 Aug 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 16no 140522_compressed.pdf | 8 Jul 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 16 no 140522_compressed.pdf | 8 Jul 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 JBD Akurli 140522_compressed.pdf | 8 Jul 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 16no 140522_compressed.pdf | 14 May 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 16 no 140522_compressed.pdf | 14 May 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 JBD Akurli 140522_compressed.pdf | 14 May 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Sakasi Park III, Form 2A.pdf | 16 Apr 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 JBD Akurli.pdf | 30 Mar 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 G 16_compressed.pdf | 30 Mar 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 JBD Akurli.pdf | 30 Mar 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A G no 16.pdf | 21 Oct 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Sakasi Park III_compressed (1).pdf | 6 Sep 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: JBD Akurli 19-20.pdf | 9 Aug 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: JBD Akurli_compressed.pdf | 9 Aug 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A G no 16.pdf | 2 Aug 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 JBD AKurli_compressed.pdf | 29 Apr 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: JBD Akurli.pdf | 14 Apr 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form-2A, Sakasi Park III_compressed.pdf | 14 Oct 2020 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 Sakasi Park.pdf | 7 Sep 2020 |
| OtherFile: Form 5 Sakasi Park.pdf | 7 Sep 2020 |
| Details of Restarting of Construction work post lockdownFile: Sakasi PArk3.pdf | 20 Jun 2020 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form-2A- 16.pdf | 26 Feb 2020 |
| Proforma of Allotment letterFile: Akurli 16 Agg Draft.pdf | 26 Feb 2020 |
| Layout approvalFile: akurli 16 plan.pdf | 7 Dec 2019 |
| Building plan approvalFile: building 1 16.pdf | 7 Dec 2019 |
| Building plan approvalFile: building 2 16.pdf | 7 Dec 2019 |
| Building plan approvalFile: building 3 16.pdf | 7 Dec 2019 |
| Copy of the legal title reportFile: Title Certi.pdf | 7 Dec 2019 |
| Details of encumbrancesFile: 16 letter.pdf | 7 Dec 2019 |
| Copy of Layout Approval (in case of layout)File: akurli 16 plan.pdf | 7 Dec 2019 |
| Building Plan Approval / NA Order for plotted developmentFile: building 1 16.pdf | 7 Dec 2019 |
| Building Plan Approval / NA Order for plotted developmentFile: building 2 16.pdf | 7 Dec 2019 |
| Building Plan Approval / NA Order for plotted developmentFile: building 3 16.pdf | 7 Dec 2019 |
| Commencement Certificates / NA Order for plotted developmentFile: Akurli 16 - CC.pdf | 7 Dec 2019 |
| Declaration in FORM BFile: Form B Jindal.pdf | 7 Dec 2019 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA 16.pdf | 7 Dec 2019 |
| Proforma of Allotment letterFile: Akurli 16 Agg Draft.pdf | 7 Dec 2019 |
Promoter's earlier projects4
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| Jindal LegacyP52000054929 | Sai Nagar, Raigarh | 189 | Feb 2024 | Certificate Signed | Mar 2027 | Jan 1970 |
| Jindal ImperiaP52000053510 | Kasbe, Raigarh | 133 | Nov 2023 | Certificate Signed | Mar 2027 | Jan 1970 |
| Jindal EnclaveP52000054516 | Kasbe, Raigarh | 153 | Jan 2024 | Certificate Signed | Mar 2027 | Jan 1970 |
| Jindal AvenueP52000031962 | PANVEL, Raigarh | - | Nov 2021 | Certificate Signed | Dec 2024 | Jan 1970 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Raigarh
Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.
Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 1 condition on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 6 other registrations, which the RERA portal never shows together
- All 47 filed documents as one ZIP, foldered, with a manifest
Keep Sakasi Park III on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Akurli5,900+ in Raigarh
SHREE RAM DELTA
Shreenathji Enterprises
Brillante
Callista Realty Limited
SAI SUNCITY PHASE 3
Chariot Properties LLP
ANANDAM PHASE - II
TODAY GLOBAL HOMES
Maximus Residency Phase-I
Superb Maa Developers LLP
Sai Vrindavan Dham
KT & LK SWEET HOMES
See every Raigarh project, with the district possession charts
Builder: Jindal Builders and Developers
Jindal Builders and Developers has 7 registrations on MahaRERA, including JINDAL RESIDENCY and Sakasi Park III. Its filings disclose 4 earlier MahaRERA projects: declares 4 of 4 past projects completed on time. Read the full track record. See more projects on the Raigarh district page.
Frequently asked questions
What are my rights if Sakasi Park III is delayed beyond 30 Dec 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Sakasi Park III?
The registered promoter entity is Jindal Builders and Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Sakasi Park III?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Sakasi Park III?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Sakasi Park III?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Sakasi Park III?
The professionals named in the filing: Architect: AN Arch; Engineer: Structcon; Chartered Accountant: Vallabh Joshi. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Sakasi Park III?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback