Registration lapsed No litigation declared Residential / Group Housing project

Saif towers

By Mustanshir Saifuddin Merchant

RG-MH-98229 · RERA P51900012891 · Last updated on MahaRERA portal: 9 Apr 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • 2 complaints at MahaRERA
  • Completion date moved by 72 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: .
Dec 2025Possession promised10 months past this date
5 of 11Construction stages donefurthest along: Internal walls, 98%
45 of 72Units unsoldnot recorded sold or booked
2Complaints at MahaRERAon this registration
Jump to the 85 documents Report an error

Saif towers is a Residential / Group Housing project by Mustanshir Saifuddin Merchant in Byculla, 400010, registered with MahaRERA as P51900012891 on 7 Sep 2017. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 72 months from the original filing. 27 of the 72 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete. 2 complaints are on record with the regulator.

At a glance

Project

  • NameSaif towers
  • TypeResidential / Group Housing
  • Location
    • Rambhau Bhogale Marg
    • Byculla
    • 400010
  • Pincode400010
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900012891
  • ReraGenie IDRG-MH-98229

Builder

  • NameMustanshir Saifuddin Merchant
  • Entity typeIndividual

Key dates

10 months past promisethis monthRegisteredSep 2017First promiseDec 2019Revised toDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on7 Sep 2017
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 31 Dec 2019)
  • Buildings1 building record
  • Documents filed85 files

Current status

38%27 of 72 units booked
93.0%Work done, per cost certificate

Figures as on 9 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Saif TowersNA261867572

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 9 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 98%.

Saif Towers: 89% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises98%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%

Progress on shared amenities15

As on 9 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes80%
Storm Water DrainsYes70%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes90%
Water conservation /Rain water harvestingYes60%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes85%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area380 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on25 Oct 2025

Approvals and building plan

Sanctioning authorityMUNICIPAL CORPORATION OF GREATER MUMBAI
Permissible FSI1838.0
Proposed, not sanctioned1,674 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch116, Dr Mascarenhas Road, Hasnabad, Mazagaon Mumbai 400010
Estimated costRs 12.69 cr
Cost incurredRs 11.81 cr
Work done93.03%
BuildingWingEstimatedIncurred
Saif TowersNARs 12.10 crRs 11.77 cr
-NARs 59.53 lakhRs 4.10 lakh

Certifying professionals and partners8

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAbid Rizvi & Associates
ArchitectSuhel Waghoo
EngineerB Yusuf Amin
EngineerYusuf Amin Burgujar
Chartered AccountantCa Esha Bhanushali
Chartered AccountantIqbal A Sayyid
Chartered AccountantHitendra Panchal
Chartered AccountantSLK and Associates
PartnerRole in project
Mustanshir Saifuddin Merchant-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51900010042Dec 2019 → Dec 2022

Reason as filed by the promoterWe would be requiring an extension as construction is not yet completed and we are planning to complete it by next year and ensure possession with in the time frame.

EXT51900017285Dec 2019 → Dec 2024

Reason as filed by the promoterDue to certain permission issues project could not be completed on time and due to changes in policy and Incentive FSI we were in process of getting approvals upto 22 Habitable floors we got the IOD and are expecting CC by mid of june 2024 (which we were supposed to get by March 24 but due to elections etc were not able to get the same), Hence we request to kindly extend the completion date to 31-12-24

EXT51900027130Dec 2019 → Dec 2025

Reason as filed by the promoterThe construction project is nearing completion, with only a few finishing tasks remaining. Due to funding constraints, there was a delay in the completion of the project. However, work is now back on track and is expected to be finished before December 2025. An extension request has been submitted for a deadline of December 2025. Further as per clause 14 (2) (ii) (Explanation Note) the allottees, irrespective of the number of apartments or plots, as the case may be, booked by him or booked in the name of his family, or companies or firms or any association etc;, booked in its name or its assoc

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC006000000044499Javed Hussain Siddiqui & Ambrin Javed Hussain SiddiquiM M Realtors21/06/2018
CC006000000055411Zulfikar Yusufali KaziM.M.Realtors17/07/2018

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 11 Aug 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 11 Aug 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 11 Aug 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 24 Apr 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed85

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 85 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 June 25.pdf9 Apr 2026
Withdrawal Update Form 1File: Form 1 Sep 25.pdf9 Apr 2026
Withdrawal Update Form 1File: Form 1 Dec 25.pdf9 Apr 2026
Withdrawal Update Form 2File: Form 2 June 25.pdf9 Apr 2026
Withdrawal Update Form 2File: Form 2 Sep 25.pdf9 Apr 2026
Withdrawal Update Form 2File: Form 2 Dec 25.pdf9 Apr 2026
Withdrawal Update Form 3File: MM Realtorss Form 3 310323.pdf9 Apr 2026
Withdrawal Update Form 3File: MM Realtorss Form 3 310323.pdf9 Apr 2026
Withdrawal Update Form 3File: MM Realtorss Form 3 310323.pdf9 Apr 2026
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 23-24.pdf21 Jun 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold Fianl Uplaod.pdf19 Jun 2025
Certificates of CA (Form 3)File: MM Form 3 Mar 2024.pdf6 May 2025
Certificates of CA (Form 3)File: MM Form 3 June 2024.pdf6 May 2025
Certificates of CA (Form 3)File: MM Form 3 Sep 2024.pdf6 May 2025
Certificates of CA (Form 3)File: MM Form 3 Dec 2024.pdf6 May 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Mar 2024.pdf6 May 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 June 2024.pdf6 May 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Sep 2024.pdf6 May 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Dec 2024.pdf6 May 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Mar 2025.pdf6 May 2025
Declaration in FORM BFile: Form B M M.pdf25 Apr 2025
Commencement Certificates / NA Order for plotted developmentFile: New CC.pdf24 Apr 2025
Declaration about Commencement CertificateFile: Declaration About C C.pdf24 Apr 2025
Disclosure for secured/unsecured finance availed for the projectFile: Disclosure for secured.pdf23 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 30-06-2024.pdf22 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 30-09-2024_compressed.pdf22 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 31-12-2024_compressed.pdf22 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 31-03-2024.pdf22 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 31-03-2025_compressed.pdf22 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 310322 MM Realtorss.pdf11 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 310323 Mm Realtorss.pdf11 Jun 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 2022 MM Realtorss.pdf10 Jun 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 2023 MM Realtorss.pdf10 Jun 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 2024 MM Realtorss.pdf10 Jun 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 2022.pdf6 Jun 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 2023.pdf6 Jun 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 2024.pdf6 Jun 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 310321.pdf6 Jun 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 2022.pdf6 Jun 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 2023.pdf6 Jun 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Unsold MM Realtorss.pdf6 Jun 2024
Certificates of CA (Form 3)File: MM Realtorss Form 3 310322.pdf6 Jun 2024
Certificates of CA (Form 3)File: MM Realtorss Form 3 310323.pdf6 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 310322.pdf6 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 310323.pdf6 Jun 2024
Declaration in FORM BFile: fORM b dEC 311224.pdf2 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: fORM 2a 23-24.pdf2 Jun 2024
Details of encumbrances concerned to FinanceFile: non encumbrance legal.pdf3 Aug 2023
Details of encumbrances concerned to FinanceFile: non encumbrance finance.pdf3 Aug 2023
Details of encumbrances concerned to LegalFile: non encumbrance legal.pdf3 Aug 2023
Details of encumbrances concerned to LegalFile: non encumbrance finance.pdf3 Aug 2023
Declaration in FORM BFile: Latest form b declaration.pdf3 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: form 2a 21-22.pdf3 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: form 2a 22-23.pdf3 Aug 2023
CERSAI detailsFile: cersai declaration.pdf3 Aug 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: interest in other organisation.pdf3 Aug 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: bank account declaration.pdf3 Aug 2023
Declaration about Commencement CertificateFile: Latest commencement certificate.pdf11 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form 5 2017-18.pdf3 Sep 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 2018-19.pdf3 Sep 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 2019-20.pdf3 Sep 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 20-21.pdf3 Sep 2021
Declaration about Commencement CertificateFile: Declaration on CC.pdf31 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A C1 pg 1 19.pdf31 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A C2 pg 1 19.pdf31 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A C3 pg 1 19.pdf31 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A C4 pg 2 19.pdf31 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A C1 pg 1 20.pdf31 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A C2 pg 1 20.pdf31 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A C3 pg 1 20.pdf31 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A C4 pg 1 20.pdf31 Aug 2021
Disclosure of sold/ booked inventoryFile: Disclosure of sold Unsold Inventory.pdf31 Aug 2021
Proforma of Allotment letterFile: Mushtaq bhai AFS.pdf12 Aug 2017
Layout approvalFile: LAyout plan.pdf11 Aug 2017
Building plan approvalFile: IOD.pdf11 Aug 2017
PAN CardFile: PAn Card.pdf11 Aug 2017
Copy of the legal title reportFile: TITLE.pdf11 Aug 2017
Details of encumbrancesFile: Encumberence.pdf11 Aug 2017
Copy of Layout Approval (in case of layout)File: LAyout plan.pdf11 Aug 2017
Building Plan Approval (IOD)File: IOD.pdf11 Aug 2017

Keep Saif towers on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Byculla

2 kmSaif towersCompleted 2Lapsed / revoked 12Other 28Dot size: filed unitsN

Filed coordinates, straight-line distance. 42 registered projects within 2 km.

Builder: Mustanshir Saifuddin Merchant

Mustanshir Saifuddin Merchant has 1 registration on MahaRERA, including Saif towers. Its filings disclose no earlier MahaRERA projects. Read the full track record.

Frequently asked questions

What does it mean that Saif towers shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Saif towers is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Saif towers?

The registered promoter entity is Mustanshir Saifuddin Merchant, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Saif towers?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Saif towers?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Saif towers?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Saif towers?

The professionals named in the filing: Architect: Abid Rizvi & Associates; Architect: Suhel Waghoo; Engineer: B Yusuf Amin; Engineer: Yusuf Amin Burgujar; Chartered Accountant: Ca Esha Bhanushali; Chartered Accountant: Iqbal A Sayyid. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Saif towers?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Saif towers. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Saif towers to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.