A. M. Residency

By ALFA MANA REALTORS PVT LTD

RG-MH-00541 · RERA P51900000070 · Last updated on MahaRERA portal: 24 Jul 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 14 cases
  • Completion date moved by 75 months
  • 6 extensions taken

Clear

  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: .
Dec 2026Possession promisedmoved 75 months from the original
14 of 22Construction stages doneacross 3 buildings; furthest along: Internal walls, 95%
218 of 346Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 85 documents Report an error

A. M. Residency is a Mixed project by ALFA MANA REALTORS PVT LTD in NEXT TO DIAMOND JUBILEE SCHOOL, 400010, registered with MahaRERA as P51900000070 on 22 Jun 2017. Possession is promised by 31 Dec 2026. The completion date has moved by 75 months from the original filing. 128 of the 346 units on this registration are recorded sold or booked, and 14 of 22 construction stages are filed complete.

At a glance

Project

  • NameA. M. Residency
  • TypeMixed
  • Location
    • MAZGAON
    • NEXT TO DIAMOND JUBILEE SCHOOL
    • 400010
  • Pincode400010
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900000070
  • ReraGenie IDRG-MH-00541

Builder

  • NameALFA MANA REALTORS PVT LTD
  • Entity typeOthers
  • GSTIN27AAICA1342A1ZB
  • ChairpersonISHKAY SUHAIL AHMED
  • Named personsMuhammad Saleem Iqbal Motorwala, SALEHA FARHAT SUHAIL AHMED ISHKAY, SUHAIL AHMED ABDUL KADER ISHKAY

Key dates

this monthRegisteredJun 2017First promiseSep 2020Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on22 Jun 2017
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 29 Sep 2020)
  • Buildings2 building records
  • Documents filed85 files

Current status

37%128 of 346 units booked

Figures as on 24 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING NO 1NA902325237
BUILDING NO 2NA901080108

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 24 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

14 of 22 construction stages are filed complete across 3 buildings. The stage furthest along is Internal walls, at 95%.

BUILDING NO 190%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUILDING NO 290%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
NA Plot Without StructureNot stated
ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities15

As on 24 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes90%
Water SupplyYes90%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes75%
Storm Water DrainsYes90%
Landscaping & Tree PlantingYes75%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes75%
Water conservation /Rain water harvestingYes75%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes90%
Electrical meter room, sub-station, receiving stationYes90%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed81

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots81
Open Space81
BuildingOpen SpaceTotal
BUILDING NO 16565
BUILDING NO 21616

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area3,654 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on27 Sep 2024

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI15489.6
Proposed, not sanctioned13,052 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchM R A Marg Opp Crawford Market, Mumbai - 400001

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
Chartered AccountantABDUL RAZZAQ
Chartered AccountantMAHENDRA V VANZARA
PartnerRole in project
ALFA MANA REALTORS PVT LTD-

Extensions applied for6

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51900002381Sep 2020 → Sep 2020

Reason as filed by the promoterThe CC for building no. 1 A & B upto 4th floor was not issued by MCGM minor amendment of building no 2 since last 1 year as there were complaints by RTI Activities and same went upto MC office, UD Mantralay office, Hon UD Minister office, and CM office and after investigation clean chits was given to our project by all the departments. we submitted our application for further CC and revised CC for building no. 2 was given on 16.5.19 and for building no. 1 is approved by MC on 7.9.19, and further CC will be issued shortly by AE practically almost 1 year is wasted in this and hence we were unabl

EXT51900012563Sep 2020 → Dec 2023

Reason as filed by the promoterDUE TO COVID 19, LOCKDOWN SITUATION 18TH MARCH TO 31ST JULY 2020, WE WERE UNABLE TO COMPLETE THE PROJECT AND FINAL IOD SUBMITTED ON 17TH NOVEMBER 2020, BUT ISSUE OF THE SAME IS AWAITED (THE POLICY FOR PREMIUM REDUCTION IS FINALIZED. NOW VIDE NOTIFICATION NO. TPS-1820/ANO.27/PR.NO. 80/20/NOV 13 DATED 14.01.2021. WE MADE OUR PAYMENT ON 5TH MARCH 2021. THE IOD IS EXPECTED TO BE ISSUED ON 12TH MARCH 2021 AND FURTHER CC IS YET AWAITED, HENCE EXTENSION IS REQUIRED.

EXT51900009298Sep 2020 → Mar 2022

Reason as filed by the promoterDUE TO COVID 19, LOCKDOWN SITUATION 18TH MARCH TO 31ST JULY 2020, WE WERE UNABLE TO COMPLETE THE PROJECT AND FINAL IOD SUBMITTED ON 17TH NOVEMBER 2020, BUT ISSUE OF THE SAME IS AWAITED (THE POLICY FOR PREMIUM REDUCTION IS FINALIZED. NOW VIDE NOTIFICATION NO. TPS-1820/ANO.27/PR.NO. 80/20/NOV 13 DATED 14.01.2021. WE MADE OUR PAYMENT ON 5TH MARCH 2021. THE IOD IS EXPECTED TO BE ISSUED ON 12TH MARCH 2021 AND FURTHER CC IS YET AWAITED, HENCE EXTENSION IS REQUIRED.

EXT51900018793Sep 2020 → Dec 2024

Reason as filed by the promoterThe Approval i.e. BMC IOD & CC which was issued till that level the project is completed & Occupation Certificate is obtained & handed over Flats to all buyers , old Rehab tenants & Government reserve Flats to Government. the balance approval IOD is issued CC is awaited and same is expected to be issued in January 2024 hence the delay is due to delay in approval.

EXT51900025937Sep 2020 → Dec 2025

Reason as filed by the promoterThe Approval i.e. BMC IOD & CC which was issued till that level the project is completed & Occupation Certificate is obtained & handed over Flats to all buyers, old Rehab tenants & Government reserve Flats to Government the further balance approval IOD and CC is issued on 4th March 2024 , work is completed 80%. RCC + Bandkaam +Plaster etc only finishing work is in progress expected to be completed by February 2025 and the sale of flat will be done alongwith it.The delay is due to delay in approval by MCGM.

EA07012619342Sep 2020 → Dec 2026

Reason as filed by the promoterIOD AMENDED AND CC ISSUED IN MAR 24 WORK IS IN PROGRESS EXPECTED TO BE COMPLETED BY JUNE 26 AND THE SALE OF FLAT WILL BE DONE ALONG WITH IT. THE DELAYED IN APPROVAL FROM MOEF FINAL NOC SO WE NEED AN EXTENSION.

Litigation declared14

CaseCourtStatus
786/2014HIGH COURTClosed
198/2016HIGH COURTClosed
2913/2015CITY CIVILClosed
1189-90/2016HIGH COURTClosed
1479-80/2016SUPREME COURTClosed
1004/2016CITY CIVILClosed
14503-14504/2016HIGH COURTClosed
15946-15947/2016SUPREME COURTClosed
393-394/2016SUPREME COURTClosed
2703/2018CITY CIVIL COURTOngoing
1999/2016SMALL COURTOngoing
1418/2019SMALL COURTClosed
235/2018SMALL COURTOngoing
2703/2018CITY CIVIL COURT BOMBAYOngoing

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 15 May 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 22 Apr 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 7 May 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 22 Apr 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 9 Jan 2023

Documents filed85

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 85 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Arch_Certificate_bldg_1___2-jan_25-AM.pdf24 Jul 2026
Withdrawal Update Form 2File: form 2-enginer-AM.pdf24 Jul 2026
Withdrawal Update Form 3File: FORM 3 ALFA.pdf24 Jul 2026
Building plan approvalFile: bldg no 1 Final iod 24 mar 21.pdf7 May 2026
Building plan approvalFile: bldg no 2 final iod 6 nov 2023.pdf7 May 2026
Withdrawal Update Form 1File: Arch_Certificate_bldg_1___2-jan_25-AM.pdf7 May 2026
Withdrawal Update Form 2File: form 2-enginer-AM.pdf7 May 2026
Withdrawal Update Form 3File: FORM 3 ALFA.pdf7 May 2026
Withdrawal Update Form 1File: Arch_Certificate_bldg_1___2-jan_25-AM.pdf7 Feb 2026
Withdrawal Update Form 1File: Arch_Certificate_bldg_1___2-jan_25-AM.pdf7 Feb 2026
Withdrawal Update Form 2File: form 2-enginer-AM.pdf7 Feb 2026
Withdrawal Update Form 2File: form 2-enginer-AM.pdf7 Feb 2026
Withdrawal Update Form 3File: FORM 3 ALFA.pdf7 Feb 2026
Withdrawal Update Form 3File: FORM 3 ALFA.pdf7 Feb 2026
Withdrawal Update Form 1File: Arch_Certificate_bldg_1___2-jan_25-AM.pdf6 Jan 2026
Withdrawal Update Form 1File: Arch_Certificate_bldg_1___2-jan_25-AM.pdf6 Jan 2026
Withdrawal Update Form 2File: form 2-enginer-AM.pdf6 Jan 2026
Withdrawal Update Form 2File: form 2-enginer-AM.pdf6 Jan 2026
Withdrawal Update Form 3File: FORM-ilovepdf-compressed.pdf6 Jan 2026
Withdrawal Update Form 3File: FORM-ilovepdf-compressed.pdf6 Jan 2026
Other - TechnicalFile: BUYESR CONSENT.pdf31 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2-enginer-AM.pdf14 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2-enginer-AM.pdf14 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch_Certificate_bldg_1___2-jan_25-AM.pdf13 Jan 2025
Other - TechnicalFile: PERT CHART.pdf13 Jan 2025
Other - TechnicalFile: REASON LETTER.pdf13 Jan 2025
Other - TechnicalFile: LETTER-2025.pdf13 Jan 2025
Declaration in FORM BFile: AM_FORM_B_2024.pdf6 Jan 2025
Disclosure of sold/ booked inventoryFile: AM_RERA_SOLD_UNSOLD_LIST_2024.pdf6 Jan 2025
Other - TechnicalFile: SALE CONSENT-DEC 24.pdf6 Jan 2025
Other - TechnicalFile: Agreement of PAKH.pdf6 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: form_2A _23-24.pdf6 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5-23-24.pdf6 Jan 2025
Building plan approval or NA orderFile: IOD-LATEST-AM.pdf22 Apr 2024
Layout approvalFile: 11zon_JPEG-to-PDF (7).pdf22 Apr 2024
Copy of Layout Approval (in case of layout)File: 11zon_JPEG-to-PDF (7).pdf22 Apr 2024
Building Plan Approval (IOD)File: IOD-LATEST-AM.pdf22 Apr 2024
Commencement Certificates / NA Order for plotted developmentFile: AM CC-LATEST.pdf22 Apr 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM-5-21-22.pdf30 Jan 2024
Building plan approval or NA orderFile: Drawing_page-0001 (2).pdf25 Jan 2024
Building plan approval or NA orderFile: 2370286Amendletter_signed.pdf25 Jan 2024
Building plan approval or NA orderFile: 2263493Amendletter_signed.pdf25 Jan 2024
Building Plan Approval (IOD)File: Drawing_page-0001 (2).pdf25 Jan 2024
Building Plan Approval (IOD)File: 2370286Amendletter_signed.pdf25 Jan 2024
Building Plan Approval (IOD)File: 2263493Amendletter_signed.pdf25 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: form_2A _22-23.pdf23 Jan 2024
Declaration in FORM BFile: FORM B-NEW.pdf18 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: form_2A _22-23.pdf18 Jan 2024
CERSAI detailsFile: LETTER TO RERA.pdf18 Jan 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: ANNEXURE A.pdf18 Jan 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: FORMAT A-BANK DECLARATION.pdf18 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: form_2A _21-22.pdf15 Jan 2024
Disclosure of sold/ booked inventoryFile: SOLDUNSOLD LIST_compressed.pdf15 Jan 2024
Details of encumbrances concerned to FinanceFile: LETTER.pdf31 Mar 2023
Details of encumbrances concerned to LegalFile: LETTER.pdf31 Mar 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 2343147_OC_signed occupancy 1.pdf9 Jan 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 2343149_OC_signed occupancy.pdf9 Jan 2023
Declaration about Commencement CertificateFile: Form_D.pdf28 Sep 2022
Disclosure of sold/ booked inventoryFile: Sold.pdf28 Sep 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5- 18-19.pdf28 Sep 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5- 19-20.pdf28 Sep 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5- 20-21.pdf28 Sep 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: ilovepdf_merged (1).pdf5 Jul 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: form_2A_April_19_to_Mar_20.pdf3 Sep 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: form_2A_April_20_to_Mar_21.pdf3 Sep 2021
Certificates of CA (Form 5)File: FORM 5_RERA.pdf10 Jan 2019
Commencement Certificates / NA Order for plotted developmentFile: furthercc_signed-bldg 2.pdf22 Oct 2018
Commencement Certificates / NA Order for plotted developmentFile: 2136893_furthercc_signed-bldg 1.pdf15 May 2018
Commencement Certificates / NA Order for plotted developmentFile: 2095902_furthercc_signed-bldg 2.pdf15 May 2018
Layout approvalFile: approved plan 01.pdf2 Jun 2017
Layout approvalFile: approved plan 02.pdf2 Jun 2017
Layout approvalFile: approved plan bldg 1.pdf2 Jun 2017
Copy of Layout Approval (in case of layout)File: approved plan 01.pdf2 Jun 2017
Copy of Layout Approval (in case of layout)File: approved plan 02.pdf2 Jun 2017
Copy of Layout Approval (in case of layout)File: approved plan bldg 1.pdf2 Jun 2017
Proforma of Allotment letterFile: 01-ilovepdf-compressed.pdf2 Jun 2017
Declaration in FORM BFile: Form - B-ilovepdf-compressed.pdf31 May 2017
Certificates of CA (Form 3)File: FORM-ilovepdf-compressed.pdf19 May 2017
Building plan approval or NA orderFile: Amended condition Letter Bldg. No.2.pdf18 May 2017
Details of encumbrancesFile: Letter - RERA.pdf18 May 2017

Keep A. M. Residency on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NEXT TO DIAMOND JUBILEE SCHOOL

2 kmA. M. ResidencyCompleted 2Lapsed / revoked 13Other 27Dot size: filed unitsN

Filed coordinates, straight-line distance. 42 registered projects within 2 km.

Builder: ALFA MANA REALTORS PVT LTD

ALFA MANA REALTORS PVT LTD has 1 registration on MahaRERA, including A. M. Residency. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record.

Frequently asked questions

What are my rights if A. M. Residency is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of A. M. Residency?

The registered promoter entity is ALFA MANA REALTORS PVT LTD, an others as per the filing. Its GSTIN 27AAICA1342A1ZB can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in A. M. Residency?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for A. M. Residency?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at A. M. Residency?

The professionals named in the filing: Chartered Accountant: ABDUL RAZZAQ; Chartered Accountant: MAHENDRA V VANZARA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in A. M. Residency?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About A. M. Residency. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save A. M. Residency to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.