Home / Browse projects / Aurangabad, Maharashtra / SAI SPARSH
SAI SPARSH
RG-MH-07882 · RERA P51500016484 · Last updated on MahaRERA portal: 4 Dec 2024
Source: official MahaRERA filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
- All 9 earlier projects delivered on promise
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 13 other registrations and every project registered within 2 km.
See what the report covers Free either way: or have every new Aurangabad registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SAI SPARSH is a Residential / Group Housing project by VIKAS LAXMAN CHAUDHARY in Aurangabad, Maharashtra, registered with MahaRERA as P51500016484 on 18 May 2018. The registration is recorded completed; possession was promised by 30 Apr 2024.
At a glance
Project
- NameSAI SPARSH
- TypeResidential / Group Housing
- Location
- PAITHAN ROAD
- ITKHEDA AURANGABAD
- Aurangabad (M Corp.)
- Aurangabad
- 431002
- Pincode431002
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51500016484
- ReraGenie IDRG-MH-07882
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on18 May 2018
- Promised completion30 Apr 2024
- Revised completionNone
- Buildings1 building record
- Documents filed82 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SAI SPARSH | NA | 5 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 4 Dec 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
SAI SPARSH: 91% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 4 Dec 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Land and ownership2
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Dr ANJALI PRAVINKUMAR WASADIKAR | Aurangabad (M Corp.) | Aurangabad |
| Dr PRAVINKUMAR PRABHAKARRAO WASADIKAR | Aurangabad (M Corp.) | Aurangabad |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | R S JADHAV |
| Engineer | N G KARKHANE |
| Chartered Accountant | JAIDEEP NAVANDAR PARTNER RDJSK & ASSOCIATES |
| Chartered Accountant | NARENDRA NAVANDAR & CO |
| Partner | Role in project |
|---|---|
| VIKAS LAXMAN CHAUDHARY | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 19 Apr 2018 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 19 Apr 2018 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 19 Apr 2018 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 19 Apr 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 2 Dec 2024
Documents filed82
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 82 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Certificates of CA (Form 3)File: SAI SPARSH 20-21 upload.pdf | 4 Dec 2024 |
| Certificates of CA (Form 3)File: SAI SPARSH 21-22 upload.pdf | 4 Dec 2024 |
| Certificates of CA (Form 3)File: SAI SPARSH 22-23 Q1 upload.pdf | 4 Dec 2024 |
| Certificates of CA (Form 3)File: SAI SPARSH 22-23 Q2 upload.pdf | 4 Dec 2024 |
| Certificates of CA (Form 3)File: SAI SPARSH 22-23 Q3 upload.pdf | 4 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 22-23 Q1.pdf | 2 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 22-23 Q2.pdf | 2 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 22-23 Q3.pdf | 2 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 21-22.pdf | 2 Dec 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: Sai Sparsh Form 4.pdf | 2 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 21-22.pdf | 2 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 22-23 Q3.pdf | 2 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 22-23 Q2.pdf | 2 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 22-23 Q1.pdf | 2 Dec 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Sai Sparsh Occupancy.pdf | 2 Dec 2024 |
| Disclosure of sold/ booked inventoryFile: 21-22 Q4.pdf | 2 Dec 2024 |
| Disclosure of sold/ booked inventoryFile: 22-23 Q1.pdf | 2 Dec 2024 |
| Disclosure of sold/ booked inventoryFile: 22-23 Q2.pdf | 2 Dec 2024 |
| Disclosure of sold/ booked inventoryFile: 22-23 Q3.pdf | 2 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 2A 21-22.pdf | 2 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2A 22-23.pdf | 2 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: F-1 SAI SPARSH MARCH'21.pdf | 24 Aug 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: F-1 SAI SPARSH JUNE'21.pdf | 24 Aug 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: F-2 SAI SPARSH -MARCH'21.pdf | 24 Aug 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: F-2 SAI SPARSH JUNE'21.pdf | 24 Aug 2021 |
| Form 2AFile: F-2A SAI SPARSH MARCH'20.pdf | 24 Aug 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: F-2A SAI SPARSH JUNE'21.pdf | 24 Aug 2021 |
| Form 2AFile: F-2A SAI SPARSH MARCH'20.pdf | 23 Aug 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM-2A SAI SPARSH JUNE'20.pdf | 23 Aug 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: F-2A SAI SPARSH SEPT'20.pdf | 23 Aug 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: F-2A SAI SPARSH DEC20.pdf | 23 Aug 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: F-2A SAI SPARSH MARCH'21.pdf | 23 Aug 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: F-1 SAI SPARSH DEC-20.pdf | 29 May 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGG CERT SAI SPARSH DEC-20.pdf | 29 May 2021 |
| Certificates of CA (Form 3)File: SEP20- FORM 3 - CA Certificate SAI SPARSH.pdf | 15 Apr 2021 |
| Certificates of CA (Form 3)File: DEC20- FORM 3 - CA Certificate SAI SPARSH.pdf | 15 Apr 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: F-1 SAI SPARSH JUN-20.pdf | 5 Dec 2020 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: F-1 SAI SPARSH SEP-20.pdf | 5 Dec 2020 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM2 SAI SPARSH.pdf | 5 Dec 2020 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: F-2 SAI SPARSH SEP-20.pdf | 5 Dec 2020 |
| Certificates of CA (Form 3)File: Sai Sparsh CA Certificate.pdf | 22 Sep 2020 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: F-1 SAI SPARSH.pdf | 6 Aug 2020 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: F-2 SAI SPARSH MAR-20.pdf | 6 Aug 2020 |
| Certificates of CA (Form 3)File: Sai Sparsh 30-6-19.pdf | 27 Feb 2020 |
| Certificates of CA (Form 3)File: sai Sparsh 30-9-19.pdf | 27 Feb 2020 |
| Certificates of CA (Form 3)File: sai Sparsh 31-12-19.pdf | 27 Feb 2020 |
| Form 2AFile: SAI SPARSH FORM 2A - DEC-19.pdf | 17 Feb 2020 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: F-2 SAI SPARSH DEC-19.pdf | 16 Jan 2020 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: F-1 SAI SPARSH DEC-19.pdf | 15 Jan 2020 |
| Form 2AFile: F-2A SPARSH 2018-19.pdf | 2 Dec 2019 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: SAI SPARSH F-5 2017-18.pdf | 2 Dec 2019 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: ''Sai sparsh ''.pdf | 29 Nov 2019 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: ''Sai sparsh ''.pdf | 29 Nov 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: f-1 sai sparsh sep-19.pdf | 8 Nov 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: F-2 SAI SPARSH SEP-19.pdf | 8 Nov 2019 |
| Form 2AFile: F-2A SAI SPARSH.pdf | 8 Nov 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer certificate sai sparsh 1507.pdf | 19 Jul 2019 |
| Form 2AFile: engineer certificate sai sparsh 1507.pdf | 19 Jul 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: F-1 SAI SPARSH.pdf | 18 Jul 2019 |
| Form 2AFile: F 2A SAI SPARSH.pdf | 18 Jul 2019 |
| Certificates of CA (Form 3)File: SAI SPARSH.pdf | 20 May 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: F-2 SPARSH M-19.pdf | 30 Apr 2019 |
| Form 2AFile: F-2A SPARSH D-18.pdf | 30 Apr 2019 |
| Form 2AFile: F-2A SPARSH M-19.pdf | 30 Apr 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: F-1 SAI SPRASH M-19.pdf | 29 Apr 2019 |
| Certificates of CA (Form 3)File: Sai Sparsh 31122018.pdf | 22 Feb 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: SAI SPARSH ARCHIT CER 08-1-19.pdf | 19 Feb 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: SAI SPARSH ENG150119-min.pdf | 19 Feb 2019 |
| Certificates of CA (Form 3)File: Sai Sparsh.pdf | 4 Dec 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGG SAI SPARSH.pdf | 28 Nov 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: arch sai sparsh.pdf | 27 Nov 2018 |
| Certificates of CA (Form 3)File: SAI SPARSH.pdf | 7 May 2018 |
| Declaration in FORM BFile: FORM B SAI SPARSH.pdf | 5 May 2018 |
| Details of encumbrancesFile: non encumbrance sai sparsh.pdf | 23 Apr 2018 |
| Proforma of Allotment letterFile: RERA AGREEMENT TO SALE SAI SPARSH.pdf | 21 Apr 2018 |
| Building plan approvalFile: MYSCAN_20180417_0002.PDF | 19 Apr 2018 |
| Layout approvalFile: MYSCAN_20180417_0002.PDF | 19 Apr 2018 |
| PAN CardFile: PAN CARD.pdf | 19 Apr 2018 |
| Copy of the legal title reportFile: search - sai sparsh.pdf | 19 Apr 2018 |
| Copy of Layout Approval (in case of layout)File: MYSCAN_20180417_0002.PDF | 19 Apr 2018 |
Promoter's earlier projects9
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| SILVER PEARLSS | PLOT NO 1 CTS NO 15735 -30-2 ULKANAGARI AURANGABAD | 53 | Completed | Nov 2018 | Jun 2018 |
| SAI SAMPADA PARK PHASE 1 | GUT NO 158 PART VILLAGE SATARA TALUKA DIST AURANGABAD | 60 | Completed | Jun 2017 | Jun 2017 |
| SAI SHRADDHA PARK PHASE 1 | GUT NO 22 P WADGAON KOLHATI WALUJ MAHANAGAR AURANGABAD | 169 | Completed | Apr 2017 | Apr 2017 |
| SAI EXOTICA | PLOT NO 21 4 CTS NO 20758 BEHIND SANT EKNATH RANGMANDIR NEW OSMANPURA AURANGABAD | 11 | Completed | Dec 2015 | Dec 2015 |
| SAI SANKET PARK | GUT NO 106 PART SATARA TQ.DIST. AURANGABAD | 127 | Completed | Jun 2014 | Jun 2014 |
| SAI HERITAGE | Plot No 2 CTS No 15735 30 Garkheda Tq Dist Aurangabad. | 33 | Completed | Apr 2014 | Apr 2014 |
| SAI RAM ENCLAVE | PLOT NO 69 & 70 CTS NO 18349 1 77 & 18349 1 78 VEDANT NAGAR AURANGABAD | 12 | Completed | Aug 2012 | Aug 2012 |
| SANKALP PARK | Gut No 106 Village Satara Tq Dist Aurangabad. | 38 | Completed | Aug 2012 | Aug 2012 |
| SAI SHRUSHTI PARK | Gut No 44 CIDCO Waluj Mahanagar IV Golwadi Tq Dist Aurangabad. | 69 | Completed | Aug 2012 | Aug 2012 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Aurangabad
Computed across the 1,400+ Aurangabad projects on ReraGenie, from their own filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 13 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 82 filed documents as one ZIP, foldered, with a manifest
Keep SAI SPARSH on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near ITKHEDA AURANGABAD1,400+ in Aurangabad
Filed coordinates, straight-line distance. 50 registered projects within 2 km.
Construction of 1056 EWS Tenements on Gut No 9
AURANGABAD HOUSING AND AREA DEVELOPMENT BO
PMAY U PADEGAON
M/s Laxmi JV
Khinvasara City
Ravindra Champalal Khinvasara
SHRI GOVINDAM HEIGHTS
SHREE VYANKATESHA INFRA
GANGOTRI VIHAR PHASE I
INSPIRA REALTY LLP
VIYAAN ANANTA PHASE II
RIDDHI VIYAAN VENTURES
See every Aurangabad project, with the district possession charts
Builder: VIKAS LAXMAN CHAUDHARY
VIKAS LAXMAN CHAUDHARY has 14 registrations on MahaRERA, including SAI ASPIRE and SILVER PEARLSS. Its filings disclose 11 earlier MahaRERA projects: declares 10 of 11 past projects completed on time. Read the full track record. See more projects on the Aurangabad district page.
Frequently asked questions
What are my rights if SAI SPARSH is delayed beyond 30 Apr 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SAI SPARSH?
The registered promoter entity is VIKAS LAXMAN CHAUDHARY, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SAI SPARSH?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for SAI SPARSH?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SAI SPARSH?
The professionals named in the filing: Architect: R S JADHAV; Engineer: N G KARKHANE; Chartered Accountant: JAIDEEP NAVANDAR PARTNER RDJSK & ASSOCIATES; Chartered Accountant: NARENDRA NAVANDAR & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SAI SPARSH?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback