ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / Sai Solitaire

Registered No litigation declared Commercial project

Sai Solitaire

By Sankalp Developers

RG-MH-23386 · RERA P52100078698 · Last updated on MahaRERA portal: 2 Jun 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 16 other registrations.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Nov 2027Possession promisedno revision filed
5 of 11Construction stages donefurthest along: Staircases, 90%
30 of 31Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 57 documents Report an error

Sai Solitaire is a Commercial project by Sankalp Developers in Pune, Maharashtra, registered with MahaRERA as P52100078698 on 7 Jan 2025. Possession is promised by 8 Nov 2027. 1 of the 31 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete.

At a glance

Project

  • NameSai Solitaire
  • TypeCommercial
  • Location
    • Mangalwar Peth
    • Pune (M Corp.)
    • Pune City
    • Pune
    • 411011
  • Pincode411011
  • RERA no.P52100078698
  • ReraGenie IDRG-MH-23386

Builder

  • NameSankalp Developers
  • Entity typePartnership
  • GSTIN27ADBFS8959G1ZJ
  • PartnersKamlesh Manohar Dadlani, PRAVIN Kanayalal RAMCHANDANI, Sunil Naraindas Lalchandani
  • Other registrations16 more →
  • Completed4 of 17
  • No longer live4 lapsed, de-registered or revoked
  • Declared earlier projects4 →

Key dates

this monthRegisteredJan 2025PromisedNov 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on7 Jan 2025
  • Promised completion8 Nov 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed57 files

Current status

3%1 of 31 units booked
91.3%Work done, per cost certificate

Figures as on 2 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Sai SolitaireNA131303131

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 2 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 90%.

Sai Solitaire: 55% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises15%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 2 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes80%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed144

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots144
Closed/Covered144

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area979 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on24 May 2025

Approvals and building plan

Sanctioning authorityPune Municipal corporation
Permissible FSI3044.2
Proposed, not sanctioned3,044 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGROUND FLOOR,G O SQUARE, SURVEY NO.249(P),240(P),251(P), HINJEWADI ROAD,WAKAD,PUNE, MAHARASHTRA,PIN 411057
Estimated costRs 14.33 cr
Cost incurredRs 13.09 cr
Work done91.34%
BuildingWingEstimatedIncurred
Sai SolitaireNARs 11.46 crRs 10.47 cr
-NARs 2.87 crRs 2.62 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAhmad Yar Chaudhary
EngineerShahnoor Ilahi Shaikh
Chartered AccountantV S A P AND COMPANY
Chartered AccountantS C
Chartered AccountantSnehal G Patil
PartnerRole in project
Sankalp Developers-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Nov 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 16 Nov 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 5 May 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 5 May 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 8 Nov 2027

Documents filed57

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 1 FY 2025-26 Q4 Final.pdf2 Jun 2026
Withdrawal Update Form 2File: Form 2 FY2025-26 Q4 Final.pdf2 Jun 2026
Withdrawal Update Form 3File: Form 3 FY 2025 -26 Q4 Final.pdf2 Jun 2026
Form 2A (FY 2025-2026)File: Form 2A FY 2025-26 Q4 Final.pdf22 May 2026
Withdrawal Update Form 1File: Form 1 for FY 2025-26 Q3 Sankalp Developers.pdf31 Mar 2026
Withdrawal Update Form 2File: Form 2 for FY 2025-26 Q3 Sankalp Developers.pdf31 Mar 2026
Withdrawal Update Form 3File: Form 3 for FY 2025-26 Q3 Sankalp Developers.pdf31 Mar 2026
Form 2A (FY 2024-2025)File: Form 2A for FY 2024-25- Sankalp Developers.pdf16 Mar 2026
Form 5 (FY 2024-2025)File: Form 5 for FY 2024-25 final.pdf24 Feb 2026
Withdrawal Update Form 1File: FORM 1 for FY 2025-26 -Q2.pdf6 Dec 2025
Withdrawal Update Form 2File: FORM 2 for FY 2025-26 -Q2.pdf6 Dec 2025
Withdrawal Update Form 3File: Form 3 for FY 2025-26-Q2.pdf6 Dec 2025
Withdrawal Update Form 1File: FORM 1 10-09-2025.pdf16 Sep 2025
Withdrawal Update Form 2File: FORM 2 10-09-2025.pdf16 Sep 2025
Withdrawal Update Form 3File: Form 3 CA certificate.pdf16 Sep 2025
Form 1File: Form 1.pdf24 May 2025
Form 2File: Form 2.pdf24 May 2025
Form 3File: Form 3 Q4 FY 2024-15.pdf24 May 2025
Disclosure of Sold and Booked InventoryFile: Promoter Disclosure.pdf24 May 2025
Other - TechnicalFile: Apartment Details Rera.pdf10 May 2025
Other - TechnicalFile: Declaration about comm sign copy.pdf9 May 2025
Building plan approvalFile: PlanCopy032025Merged.pdf5 May 2025
Commencement Certificates / NA Order for plotted developmentFile: 20250424074108.pdf5 May 2025
Building Plan Approval / NA Order for plotted developmentFile: PlanCopy032025Merged.pdf5 May 2025
Other - TechnicalFile: ReraMailScreenshot.pdf5 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Final.pdf26 Dec 2024
Other - TechnicalFile: Apartment Details (1).pdf26 Dec 2024
Other - TechnicalFile: PMC MAIL.pdf17 Dec 2024
Other - TechnicalFile: Declaration about Commencement Certificate.pdf17 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf13 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architech Certificate_Compressed.pdf12 Dec 2024
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: FORMAT_B_BANK ACCOUNT.pdf12 Dec 2024
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf5 Dec 2024
Building plan approvalFile: Building Plans_Compressed.pdf29 Nov 2024
Copy of the legal title reportFile: Legal Title Report (RERA)_Sankalp.pdf29 Nov 2024
Details of encumbrances concerned to FinanceFile: Details of encumbrances concerned to Finance.pdf29 Nov 2024
Details of encumbrances concerned to FinanceFile: Legal Encumberance Report.pdf29 Nov 2024
Building Plan Approval / NA Order for plotted developmentFile: Building Plans_Compressed.pdf29 Nov 2024
Other - LegalFile: SHANKAR Parkhe to SANKALP SALE DEED_Compressed.pdf29 Nov 2024
Other - LegalFile: AKSHAYA SALE DEED_Compressed.pdf29 Nov 2024
Other - LegalFile: RABBANI to SANKALP_Sale Deed-compressed.pdf29 Nov 2024
CERSAI detailsFile: UNDERTAKING_CERSAI.pdf29 Nov 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: FORMAT_A_BANK ACCOUNT.pdf29 Nov 2024
Details of encumbrances concerned to LegalFile: Details of encumbrances concerned to Finance.pdf29 Nov 2024
Details of encumbrances concerned to LegalFile: Legal Encumberance Report.pdf29 Nov 2024
Proforma of Agreement for saleFile: Annexure A_Model Form of Agreement to be entered into between Promoter and Allottee(s)_Com29 Nov 2024
Disclosure for secured/unsecured finance availed for the projectFile: Disclosure of Secured_Unsecured Finance.pdf29 Nov 2024
Layout approvalFile: Plan Layout.pdf16 Nov 2024
PAN CardFile: PAN_Sankalp Developers.pdf16 Nov 2024
Copy of Layout Approval (in case of layout)File: Plan Layout.pdf16 Nov 2024
Proforma of Allotment letterFile: ANNEXURE_1_MODEL FORM OF ALLOTMENT LETTER.pdf16 Nov 2024
Declaration in FORM BFile: Form B Affidavit.pdf16 Nov 2024
Declaration about Commencement CertificateFile: FORMAT_D_Circular 32_2021.pdf16 Nov 2024
Deviation Report with respect to Allotment letterFile: Deviation Report with respect to Allotment letter.pdf16 Nov 2024
Other - TechnicalFile: Annexure-A_Declaration Cum Undertaking.pdf16 Nov 2024
Deviation Report with respect to model copy of AgreementFile: Deviation Report with respect to model copy of Agreement.pdf16 Nov 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Self Declaration_Disclosure of Interest in Other Real Estate Org.pdf16 Nov 2024

How this compares with Pune

3%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Sai Solitaire on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Mangalwar Peth13,700+ in Pune

Builder: Sankalp Developers

Sankalp Developers has 17 registrations on MahaRERA, including Anand Baug Building D and SANKALP HEIGHTS. Its filings disclose 4 earlier MahaRERA projects: declares 2 of 3 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Sai Solitaire is delayed beyond 8 Nov 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Sai Solitaire?

The registered promoter entity is Sankalp Developers, a partnership as per the filing. Its GSTIN 27ADBFS8959G1ZJ can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Sai Solitaire?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Sai Solitaire?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Sai Solitaire?

The professionals named in the filing: Architect: Ahmad Yar Chaudhary; Engineer: Shahnoor Ilahi Shaikh; Chartered Accountant: V S A P AND COMPANY; Chartered Accountant: S C; Chartered Accountant: Snehal G Patil. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Sai Solitaire?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Sai Solitaire. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Sai Solitaire to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.