Sankalp Developers: RERA track record

Partnership ยท attribution by exact filing name, entity resolution in progress

Sankalp Developers has 16 registrations in this build, including Anand Baug Building D and SANKALP HEIGHTS. Its filings disclose 2 earlier MahaRERA projects: 1 of 2 past projects completed on time. Litigation is declared on 1 of its registrations.

16Registrations in this build
2Past projects disclosed
+2 monthsMedian delivery slip
1Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
Anand Baug Building DPune, Maharashtra--Completed
SANKALP HEIGHTSSatara, Maharashtra--Completed
SANKALP SIDDHIThane, Maharashtra5387%Registered
Tilak Nagar Shree Sainath CHS LtdMumbai Suburban, Maharashtra--Registration lapsed
Royal VillasThane, Maharashtra2740%Completed
VRINDAWAN RESIDENCYThane, Maharashtra--Completed
Sankalp ParkAurangabad, Maharashtra--Registered
Sadguru KrupaSindhudurg, Maharashtra--Registration lapsed
SANKALP HEIGHTSSatara, Maharashtra--Registration lapsed
HERAMBH RESIDENCYSatara, Maharashtra--Registered
ANAND BAUG C WINGPune, Maharashtra10%Registered
SANKALP HILIFEPune, Maharashtra51174%Registered
Pushkaraj ApartmentsRaigarh, Maharashtra--Registration lapsed
Shree Omkar Co-Operative Housing Society LTDThane, Maharashtra1414%Registered
Sai SolitairePune, Maharashtra313%Registered
SHRI RAM SANKULSindhudurg, Maharashtra950%Registered

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
Anand Baug Phase I
1 Nov 20121 Mar 2013+4 months
SANKALPA HEIGHTS
31 Mar 202431 Mar 2024On time

Frequently asked questions

How do I verify Sankalp Developers as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with Sankalp Developers?

Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

Does the declared litigation make Sankalp Developers unsafe to buy from?

Not by itself. Litigation on a registration ranges from a boundary dispute to an allottee case about delay; what matters is the case type, which court or forum, and whether it touches the land title of the project you are buying. The case list is in each project's filed documents. Treat litigation as a question to resolve in writing before booking, not as a verdict either way.