ANTRIKSH TOWERS
RG-MH-42579 · RERA P52100019454 · Last updated on MahaRERA portal: 4 Aug 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 36 months
- 3 extensions taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- All 9 earlier projects delivered on promise
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
ANTRIKSH TOWERS is a Others project by AUM CITYSCAPES LLP in Pune, Maharashtra, registered with MahaRERA as P52100019454 on 1 Feb 2019. Possession is promised by 31 Dec 2026. The completion date has moved by 36 months from the original filing. 176 of the 215 units on this registration are recorded sold or booked, and 12 of 22 construction stages are filed complete.
At a glance
Project
- NameANTRIKSH TOWERS
- TypeOthers
- Location
- STATION ROAD
- MANGALWAR PETH
- Pune (M Corp.)
- Pune City
- Pune
- 411011
- Pincode411011
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100019454
- ReraGenie IDRG-MH-42579
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on1 Feb 2019
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 30 Dec 2023)
- Buildings2 building records
- Documents filed114 files
Current status
Figures as on 4 Aug 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| BUILDING A | NA | 17 | 17 | 15 | 7 | 22 |
| BUILDING B | NA | 30 | 30 | 80 | 113 | 193 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 4 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
12 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is External plumbing and external plaster, at 90%.
BUILDING A94%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 80% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 80% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 80% |
BUILDING B90%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 90% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 80% |
| Sanitary Fittings within the flats / premises | 80% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 80% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 80% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 80% |
Progress on shared amenities15
As on 4 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 70% |
| Water Supply | Yes | 60% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 70% |
| Storm Water Drains | Yes | 80% |
| Landscaping & Tree Planting | Yes | 50% |
| Street Lighting | Yes | 70% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 70% |
| Solid Waste Management And Disposal | Yes | 70% |
| Water conservation /Rain water harvesting | Yes | 70% |
| Energy managemcnt | Yes | 50% |
| Fire protection and fire safety requirements | Yes | 80% |
| Electrical meter room, sub-station, receiving station | Yes | 60% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed30
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| BUILDING B | NA | Rs 124.13 cr | Rs 104.17 cr |
| BUILDING A | NA | Rs 6.89 cr | Rs 6.89 cr |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | MANGESH BHANDEKAR |
| Engineer | KALPESH ZABAK |
| Chartered Accountant | FORM V SAC AND CO LLP |
| Chartered Accountant | FORM III PRIYANKA CHORDIYA AND ASSOCIATES |
| Partner | Role in project |
|---|---|
| AUM CITYSCAPES LLP | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe work is almost completed but due revision in the PMC rule, excess FSI is received and additional floor sanctioned (separate registration is taken for the same) but finishing work is pending so applying for extension.
Reason as filed by the promoterMore than one registration is taken for a single building Construction project and to get the Completion certificate of the full project we require an extension. Construction of the project is ongoing but in the slow movement, as non-availability of labour in the past now we are on track to complete the project. Also there is a revision in the Development rules for Slum rehabilitation projects accordingly we are eligible for additional sanction of three floors and the permission for sanction of the same is in process, to complete the construction with additional sanction we have applied for ex
Reason as filed by the promoterMore than one registration is taken for a single building Construction project and to get the Completion certificate of the full Occupancy certificate project we require an extension. Construction of the project is ongoing but in the slow movement, as non-availability of labour in the past now we are on track to complete the project. Also, there is a revision in the Development rules for Slum rehabilitation projects accordingly we are eligible for additional sanction of three floors and the permission for sanction of the same is in process, to complete the construction with additional sanction
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 19 Jan 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 8 Oct 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 25 Jan 2019 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 25 Nov 2020Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2026
Documents filed114
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 114 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 5 (FY 2021-2022)File: Form 5 2021-2022.pdf | 4 Aug 2026 |
| Form 5 (FY 2022-2023)File: Form 5 2022-23.pdf | 4 Aug 2026 |
| Form 5 (FY 2023-2024)File: Form 5 2022-23.pdf | 4 Aug 2026 |
| Form 2A (FY 2025-2026)File: Form 2A Antriksh Tower 2025-2026.pdf | 1 Aug 2026 |
| Withdrawal Update Form 1File: FORM 1 ANTARIKSH TOWER as on 30062026.pdf | 22 Jul 2026 |
| Withdrawal Update Form 2File: Antriksh Towers Form-2.pdf | 22 Jul 2026 |
| Withdrawal Update Form 3File: Antariksh towers FORM 3 3002026 sign.pdf | 22 Jul 2026 |
| Withdrawal Update Form 1File: FORM 1 ANTARIKSH TOWER as on 31032026.pdf | 18 Apr 2026 |
| Withdrawal Update Form 2File: Form-2 Antriksh Towers.pdf | 18 Apr 2026 |
| Withdrawal Update Form 3File: Form_3 Antriksh Towers 31032026 sign_compressed.pdf | 18 Apr 2026 |
| Withdrawal Update Form 1File: Form 1 sign 31122025.pdf | 5 Feb 2026 |
| Withdrawal Update Form 2File: Form 2 Antriksh Tower sign 31122025.pdf | 5 Feb 2026 |
| Withdrawal Update Form 3File: Form 3 Antariksh 31122025 sign_compressed.pdf | 5 Feb 2026 |
| Form 2A (FY 2024-2025)File: form 2A Antariksh Towers FY 24-25.pdf | 25 Dec 2025 |
| Withdrawal Update Form 1File: FORM 1 ANTARIKSH TOWER as on 30-06-2025.pdf | 17 Oct 2025 |
| Withdrawal Update Form 1File: FORM 1 ANTARIKSH TOWER as on 30-09-2025 (1).pdf | 17 Oct 2025 |
| Withdrawal Update Form 2File: Form -2 ANTRIKSH TOWERS 30-06-2025.pdf | 17 Oct 2025 |
| Withdrawal Update Form 2File: FORM -2 ANTRIKSH TOWERS 30-09-2025.pdf | 17 Oct 2025 |
| Withdrawal Update Form 3File: Form 3 Antariksh 30062025 sign_compressed.pdf | 17 Oct 2025 |
| Withdrawal Update Form 3File: Form 3 Antariksh 30092025_sign copy.pdf | 17 Oct 2025 |
| Form 5 (FY 2024-2025)File: Form 5_Antriksh Tower FY 24-25 sign.pdf | 17 Oct 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 ANTARIKSH TOWER as on 31032025.pdf | 12 Apr 2025 |
| Certificates of CA (Form 3)File: Form 3 Antariksh 31032025 sign_compressed.pdf | 12 Apr 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Antariksh towerwr FORM 2 31032025.pdf | 12 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold and Unsold 31032025 sign.pdf | 12 Apr 2025 |
| Declaration in FORM BFile: New form B_compress.pdf | 1 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 ANTRIKSH TOWER 31122024.pdf | 13 Jan 2025 |
| Certificates of CA (Form 3)File: form 3 Antariksh Towers 31122024 _Closing balance 0_compressed.pdf | 13 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Antriksh Tower.pdf | 13 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: SOld Unsold Antriksh Tower sign.pdf | 13 Jan 2025 |
| Certificates of CA (Form 3)File: Form 3 Antariksh 30092024_sign_final.pdf | 23 Dec 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold and Unsold 30092024_NEW.pdf | 23 Dec 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: aum housing diclosure of interest_Alpesh sir.pdf | 23 Dec 2024 |
| Certificates of CA (Form 3)File: 9 Certificates of CA (Form 3).pdf | 16 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: 2 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24).pdf | 16 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 Antariksh towers as on 30092024.pdf | 17 Oct 2024 |
| Certificates of CA (Form 3)File: Form 3 Antariksh 30092024_sign_compress.pdf | 17 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Antariksh towers MAHA RERA FORM 2 Engineer certificate 30092024.pdf | 17 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold and Unsold 30092024.pdf | 17 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form 5 Antariksh Towers 31032024_compress.pdf | 11 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form 5 Antariksh Towers 31032024_compress.pdf | 11 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold- Unsold Antriksh Towers.pdf | 20 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Antariksh Tower.pdf | 18 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 Antariksh Towers 30-06-2024.pdf | 18 Jul 2024 |
| Certificates of CA (Form 3)File: form 3 Antariksh Towers 30-06-2024_compressed.pdf | 18 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: ANTARIKSH TOWERSSolD Unsold Inventory 31032024.pdf | 28 May 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 ANTRIKSH TOWERS 310324.pdf | 22 May 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: fORM 2 AS ON 31032024 ANTRISH TOWERS.pdf | 22 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: form 2a antariksh towers.pdf | 22 May 2024 |
| Certificates of CA (Form 3)File: Signed form 3 Antariksh Towers 31032024_compressed.pdf | 22 May 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: SEPARATE AC ANTARIKSH TOWERS.pdf | 21 May 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: from1 ANTARIKSH TOWERS 31120223.pdf | 11 Mar 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 antariksh towers 31122023.pdf | 7 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold and Unsold 31122023 antariksh towers.pdf | 7 Feb 2024 |
| Certificates of CA (Form 3)File: Form 3 Antariksh 31122023 both sign compressed.pdf | 7 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold and Unsold 30092023.pdf | 27 Dec 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 ANTARIKSH TOWER as on 31032023.pdf | 23 Dec 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 ANTARIKSH TOWER as on 30062023.pdf | 23 Dec 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 ANTARIKSH TOWER as on 30092023.pdf | 23 Dec 2023 |
| Declaration in FORM BFile: form B Aum cityscapes LLp_compressed.pdf | 21 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: form 2A Antariksh Towers 31032021.pdf | 21 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: form 2A Antariksh Towers 31032022.pdf | 21 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: form 2A Antariksh Towers 31032023.pdf | 21 Dec 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 Antriksh towers 30092023_compressed.pdf | 1 Dec 2023 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold and Unsold 30092023.pdf | 1 Dec 2023 |
| Disclosure of sold/ booked inventoryFile: Antariksh Towers disclosure sold unsold 30092023_compressed.pdf | 1 Dec 2023 |
| Certificates of CA (Form 3)File: FORM 3 antariksh tower 30092023 both sign.pdf | 1 Dec 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form f fy 20-21 final antariksh towers.pdf | 31 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5_ ANTRIKSH TOWERS_FY 21_22.pdf | 31 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5_ANTRIKSH TOWERS_FY 22_23_compressed.pdf | 31 Oct 2023 |
| Deviation Report with respect to model copy of AgreementFile: Deviation Report with respect to Allotment letter.pdf | 25 Aug 2023 |
| Details of encumbrancesFile: ENCUMBRANCE MERGED.pdf | 24 Aug 2023 |
| Details of encumbrances concerned to FinanceFile: ENCUMBRANCE MERGED.pdf | 24 Aug 2023 |
| Details of encumbrances concerned to LegalFile: ENCUMBRANCE MERGED.pdf | 24 Aug 2023 |
| Declaration about Commencement CertificateFile: Format D Commencement certificate declaration.pdf | 24 Aug 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in other real estate organisations - Sharad Narayan Mogale.pdf | 24 Aug 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in other real estate organisations-Ajit Zumbarlal Karnawat.pdf | 24 Aug 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in other real estate organisations-Ketan Jayantilal Veera.pdf | 24 Aug 2023 |
| Proforma of Agreement for saleFile: 1 Proforma of Agreement for sale.pdf | 24 Aug 2023 |
| Proforma of Allotment letterFile: 1 Proforma of Allotment letter.pdf | 24 Aug 2023 |
Promoter's earlier projects9
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| THE MINT | BANER | 19 | Completed | Dec 2016 | Dec 2016 |
| QUADRA | BANER | 4 | Completed | Dec 2016 | Dec 2016 |
| ASHIYANA | SHIVAJINAGAR | 58 | Completed | Dec 2016 | Dec 2016 |
| KESHAV SHRUSHTI | RATNAGIRI | 73 | Completed | Dec 2015 | Dec 2015 |
| CASA IMPERIA | WAKAD | 397 | Completed | Jun 2014 | Jun 2014 |
| SLUM REHABILITATION PROJECT | BHAWANI PETH | 428 | Completed | Dec 2012 | Dec 2012 |
| COSMOS REGENCY | BANER | 172 | Completed | Mar 2012 | Mar 2012 |
| CASA POLI | WAKAD | 112 | Completed | Dec 2011 | Dec 2011 |
| LA VALE CASA | SR NO 20 BHAVDHAN | 120 | Completed | Jan 2009 | Jan 2009 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 114 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep ANTRIKSH TOWERS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near MANGALWAR PETH13,700+ in Pune
Filed coordinates, straight-line distance. 366 registered projects within 2 km.
Wyng
Manasara Realty LLP
SARA KASTURI BUILDING C
JAGRUTSARA STRUCTURES LLP
EVOLET TIARA
M/S EVOLET DEVELOPERS
B. T. SQUARE
AJAY JAYAWANT BHOSLE
GIRNAR
SHREE DATTA REALTORS
OPULENT STARLIT
OPULENT DEVELOPERS
Builder: AUM CITYSCAPES LLP
AUM CITYSCAPES LLP has 2 registrations on MahaRERA, including ANTRIKSH TOWERS and ANTRIKSH TOWERS 22-32. Its filings disclose 9 earlier MahaRERA projects: declares 9 of 9 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if ANTRIKSH TOWERS is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of ANTRIKSH TOWERS?
The registered promoter entity is AUM CITYSCAPES LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in ANTRIKSH TOWERS?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for ANTRIKSH TOWERS?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at ANTRIKSH TOWERS?
The professionals named in the filing: Architect: MANGESH BHANDEKAR; Engineer: KALPESH ZABAK; Chartered Accountant: FORM V SAC AND CO LLP; Chartered Accountant: FORM III PRIYANKA CHORDIYA AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in ANTRIKSH TOWERS?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback