Home / Browse projects / Pune, Maharashtra / Sai Shawas

Registered No litigation declared Residential / Group Housing project

Sai Shawas

By Vilas Tukaram Wadghule

RG-MH-20079 · RERA P52100007646 · Last updated on MahaRERA portal: 3 Jan 2026

Source: official MahaRERA filing

Red flags

  • 2 complaints at MahaRERA
  • Completion date moved by 48 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 48 months from the original
28 of 33Construction stages doneacross 3 buildings; furthest along: Podiums (if any), 0%
30 of 198Units unsoldnot recorded sold or booked
2Complaints at MahaRERAon this registration
Jump to the 108 documents Report an error

Sai Shawas is a Residential / Group Housing project by Vilas Tukaram Wadghule in Pune, Maharashtra, registered with MahaRERA as P52100007646 on 17 Aug 2017. Possession is promised by 23 Dec 2026. The completion date has moved by 48 months from the original filing. 168 of the 198 units on this registration are recorded sold or booked, and 28 of 33 construction stages are filed complete. 2 complaints are on record with the regulator.

At a glance

Project

  • NameSai Shawas
  • TypeResidential / Group Housing
  • Location
    • PUNE RAHU ROAD
    • NEAR PRIMARY HEALTH CARE CENTER
    • Wade Bolhai
    • Haveli
    • Pune
    • 412207
  • Pincode412207
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100007646
  • ReraGenie IDRG-MH-20079

Builder

  • NameVilas Tukaram Wadghule
  • Entity typeIndividual

Key dates

this monthRegisteredAug 2017First promiseDec 2022Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on17 Aug 2017
  • Promised completion23 Dec 2026
  • Revised completionRevised to 23 Dec 2026 (originally 26 Dec 2022)
  • Buildings3 building records
  • Documents filed108 files

Current status

85%168 of 198 units booked
82.4%Work done, per cost certificate

Figures as on 3 Jan 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING ANA8863063
Wing BNA7756056
Wing CNA8879079

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 3 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

28 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Podiums (if any), at 0%.

WING A91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Wing B82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Wing C82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 3 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes70%
Solid Waste Management And DisposalYes70%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes0%

Parking filed216

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots216
Closed/Covered144
Open Space72
BuildingClosed/CoveredOpen SpaceTotal
WING A482472
Wing B482472
Wing C482472

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area8,000 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on15 Dec 2025

Approvals and building plan

Sanctioning authorityPUNE METROPOLITAN REGION DEVELOPMENT AUTHORITY PUNE
Permissible FSI9434.84
Proposed, not sanctioned8,235 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchVIMAN NAGAR,PUNE411014
Estimated costRs 35.80 cr
Cost incurredRs 29.50 cr
Work done82.4%
BuildingWingEstimatedIncurred
WING ANARs 11.15 crRs 9.00 cr
Wing CNARs 11.15 crRs 9.00 cr
Wing BNARs 10.50 crRs 9.50 cr
-NARs 3.00 crRs 2.00 cr

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMr Vishwanath Jagtap
EngineerMr Annirudha Vanarse
Chartered AccountantPradip Kamathe and Associates
PartnerRole in project
Vilas Tukaram Wadghule-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100017859Dec 2022 → Dec 2025

Reason as filed by the promoterContingencies arising during the Corona period made it inevitable to make some changes in the project, so the revised design of A and c wings of the project was delayed by the concerned sanctioning authority, then due to the lack of response from the contractor labors and the customers, the sale was delayed.

EXT52100012656Dec 2022 → Dec 2023

Reason as filed by the promoterOur project namely "Sai Sahawas"situated Gat no-53,in Wadebolhai,Tal-Haweli,Dist-Pune,going to delay because we got revised sanction from PMRDA,which is our sanctioning authority in 27th Oct.2021.And our RERA commitment will be on 24th Dec.2022 in this situation and short time of 12 month it is not possible to construct 2 towers Wing "A"&WING "C".So want to extra time for complete this project.

EA05012619282Dec 2022 → Dec 2026

Reason as filed by the promoterWe respectfully submit that the construction work of the project has been substantially completed as per the sanctioned plans. The application for issuance of the Occupancy Certificate (OC) has already been submitted to the competent planning authority, and the same is under process. The delay in obtaining the Occupancy Certificate is primarily due to procedural requirements, inspections, and administrative processing at the level of the concerned authority, which is beyond the control of the promoter. No major structural work remains pending. Only minor finishing touches and compliance-relate

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC12601431Yogesh Dnyaneshwar EthapeVilas Tukaram Wadghule14/03/2026
CC12602449Prabhakar PatoleVilas Tukaram Wadghule26/04/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 16 May 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 14 Dec 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 14 Dec 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 13 Feb 2025

Documents filed108

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 108 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: fORM 1.pdf3 Jan 2026
Withdrawal Update Form 1File: fORM 1.pdf3 Jan 2026
Withdrawal Update Form 1File: fORM 1.pdf3 Jan 2026
Withdrawal Update Form 2File: ENGINEER (3).pdf3 Jan 2026
Withdrawal Update Form 2File: ENGINEER (3).pdf3 Jan 2026
Withdrawal Update Form 2File: ENGINEER (3).pdf3 Jan 2026
Withdrawal Update Form 3File: CA Certificate SRD (4)_11zon.pdf3 Jan 2026
Withdrawal Update Form 3File: CA Certificate SRD (4)_11zon.pdf3 Jan 2026
Withdrawal Update Form 3File: CA Certificate SRD (4)_11zon.pdf3 Jan 2026
Certificates of CA (Form 3)File: form - 3 2025.pdf20 Feb 2025
Disclosure of sold/ booked inventoryFile: Wing - A.pdf20 Feb 2025
Disclosure of sold/ booked inventoryFile: Wing - C 2025.pdf20 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: From - 5 2025.pdf20 Feb 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: COMPLITION CERTIFICATE B WING.pdf13 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: ENGEENEARS FORM 2A 2023-24.pdf13 Feb 2025
Architect’s Certificate on Completion of Project (Form 4)File: ARCHITECT CERTIFICATE 2023-24.pdf10 Feb 2025
Declaration in FORM BFile: FORM B 2023.pdf20 Nov 2023
Certificates of CA (Form 3)File: CA FORM 3 2023.pdf17 Nov 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE 2023 FORM 1.pdf8 Nov 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineering Certificate 2023 FORM 2.PDF8 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: ENGEENEARS FORM 2A 2023.pdf8 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Shubham dhore degree certificate.pdf8 Nov 2023
Declaration in FORM BFile: Application For Extension of project Completion 2023.pdf6 Nov 2023
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD BOOKED INVENTORY 2023.pdf6 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Engineering Certificate 2023.pdf28 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Annual Report Shree Ram Developers 2022-23.pdf28 Oct 2023
Details of encumbrances concerned to FinanceFile: 53 712.pdf27 Oct 2023
Details of encumbrances concerned to LegalFile: 53 712.pdf27 Oct 2023
CERSAI detailsFile: CERSAI_Search_Report_200284883376_For_Debtor_Based_Search_27_10_2023_15_55_27_690.pdf27 Oct 2023
Building plan approvalFile: 01-09.pdf14 Dec 2022
Building plan approvalFile: 02-09.pdf14 Dec 2022
Building plan approvalFile: 03-09.pdf14 Dec 2022
Building plan approvalFile: 04-09.pdf14 Dec 2022
Building plan approvalFile: 05-09.pdf14 Dec 2022
Building plan approvalFile: 05-09.pdf14 Dec 2022
Building plan approvalFile: 06-09.pdf14 Dec 2022
Building plan approvalFile: 07-09.pdf14 Dec 2022
Building plan approvalFile: 08-09.pdf14 Dec 2022
Building plan approvalFile: 09-09.pdf14 Dec 2022
Building plan approvalFile: 09-09.pdf14 Dec 2022
Building Plan Approval (IOD)File: 01-09.pdf14 Dec 2022
Building Plan Approval (IOD)File: 02-09.pdf14 Dec 2022
Building Plan Approval (IOD)File: 03-09.pdf14 Dec 2022
Building Plan Approval (IOD)File: 04-09.pdf14 Dec 2022
Building Plan Approval (IOD)File: 05-09.pdf14 Dec 2022
Building Plan Approval (IOD)File: 05-09.pdf14 Dec 2022
Building Plan Approval (IOD)File: 06-09.pdf14 Dec 2022
Building Plan Approval (IOD)File: 07-09.pdf14 Dec 2022
Building Plan Approval (IOD)File: 08-09.pdf14 Dec 2022
Building Plan Approval (IOD)File: 09-09.pdf14 Dec 2022
Building Plan Approval (IOD)File: 09-09.pdf14 Dec 2022
Commencement Certificates / NA Order for plotted developmentFile: Document 239 (1).pdf14 Dec 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form 5 CHARTERED ACCOUNT 2017-18.pdf19 Oct 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 CHARTERED ACCOUNTS 2018-19.pdf19 Oct 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: CHARTERED ACCOUNT FORM 5 2019-20.pdf19 Oct 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: CHARTER ACCOUNT FORM 5 2020-21.pdf19 Oct 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: CHARTERED ACCOUNT FORM 5 2021-22.pdf19 Oct 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: sign page ENGINEER.pdf15 Oct 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FA 2019-20.pdf15 Oct 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FA 2020-21.pdf15 Oct 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: sign page ENGINEER.pdf15 Oct 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Engineer 's certificate 2021-22.pdf15 Oct 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: sign page ENGINEER.pdf15 Oct 2022
Disclosure of sold/ booked inventoryFile: Sai Sahavas -Wing - A.pdf15 Oct 2022
Disclosure of sold/ booked inventoryFile: Sai Sahavas- wing -B.pdf15 Oct 2022
Disclosure of sold/ booked inventoryFile: Sai Sahavas -Wing -C.pdf15 Oct 2022
Declaration about Commencement CertificateFile: declaration about commencement certificate.pdf14 Oct 2022
Layout approvalFile: 1-9.pdf16 May 2022
Copy of Layout Approval (in case of layout)File: 1-9.pdf16 May 2022
Commencement Certificates / NA Order for plotted developmentFile: PMRDA REV1 VIKAS PARVANGI V PRAMANPATRA.pdf20 Mar 2021
Layout approvalFile: pmrda rev1 2018.pdf19 Mar 2021
Building plan approvalFile: pmrda rev1 no2.pdf19 Mar 2021
Building plan approvalFile: PMRDA REV1 NO3.pdf19 Mar 2021
Building plan approvalFile: PMRDA REV1 NO4.pdf19 Mar 2021
Building plan approvalFile: PMRDA REV 1 NO5.pdf19 Mar 2021
Building plan approvalFile: PMRDA REV 1 CLUB HOUSE.pdf19 Mar 2021
Copy of Layout Approval (in case of layout)File: pmrda rev1 2018.pdf19 Mar 2021
Building Plan Approval (IOD)File: pmrda rev1 no2.pdf19 Mar 2021
Building Plan Approval (IOD)File: PMRDA REV1 NO3.pdf19 Mar 2021
Building Plan Approval (IOD)File: PMRDA REV1 NO4.pdf19 Mar 2021

How this compares with Pune

85%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 48 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Sai Shawas on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NEAR PRIMARY HEALTH CARE CENTER13,700+ in Pune

2 kmSai ShawasLapsed / revoked 2Other 3Dot size: filed unitsN

Filed coordinates, straight-line distance. 5 registered projects within 2 km.

Builder: Vilas Tukaram Wadghule

Vilas Tukaram Wadghule has 1 registration on MahaRERA, including Sai Shawas. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Sai Shawas is delayed beyond 23 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Sai Shawas?

The registered promoter entity is Vilas Tukaram Wadghule, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Sai Shawas?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Sai Shawas?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Sai Shawas?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Sai Shawas?

The professionals named in the filing: Architect: Mr Vishwanath Jagtap; Engineer: Mr Annirudha Vanarse; Chartered Accountant: Pradip Kamathe and Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Sai Shawas?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Sai Shawas. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Sai Shawas to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.