Home / Browse projects / Aurangabad, Maharashtra / SAI SANSKRUTI BUILDING D PHASE II
SAI SANSKRUTI BUILDING D PHASE II
RG-MH-00971 · RERA P51500015360 · Last updated on MahaRERA portal: 15 Apr 2021
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 22 months past the filed date
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Aurangabad registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SAI SANSKRUTI BUILDING D PHASE II is a Residential / Group Housing project by VIKAS INFRASTRUCTURE in Aurangabad, Maharashtra, registered with MahaRERA as P51500015360 on 20 Feb 2018. Possession was promised by 30 Dec 2024 and is now 22 months past that date.
At a glance
Project
- NameSAI SANSKRUTI BUILDING D PHASE II
- TypeResidential / Group Housing
- Location
- SATARA
- AURANGABAD
- Satara (CT)
- 431001
- Pincode431001
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51500015360
- ReraGenie IDRG-MH-00971
Builder
- NameVIKAS INFRASTRUCTURE
- Entity typePartnership
- PartnerLAXMAN DAGADU CHAUDHARY
- Declared earlier projects1 →
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on20 Feb 2018
- Promised completion30 Dec 2024
- Revised completionNone
- Buildings1 building record
- Documents filed49 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SAI SANSKRUTI BUILDING D | NA | 6 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 15 Apr 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
SAI SANSKRUTI BUILDING D: 91% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities16
As on 15 Apr 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
| COVER PARKING | No | Not applicable |
Parking filed26
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | R S JADHAV OF J B & ASSOCIATES |
| Engineer | N G KARKHANE |
| Partner | Role in project |
|---|---|
| VIKAS INFRASTRUCTURE | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 8 Aug 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 8 Aug 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 8 Aug 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 8 Aug 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed49
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Certificates of CA (Form 3)File: SEP2020 - FORM 3 - CA Cert SAI SANSKRUTI BUILDING D- PHASE II udin.pdf | 15 Apr 2021 |
| Certificates of CA (Form 3)File: DEC20 - FORM 3 - CA Cert SAI SANSKRUTI BUILDING D- PHASE II udin.pdf | 15 Apr 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: F-2 SAI SANSKRUTI JUN20.pdf | 7 Dec 2020 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: F-2 SAI SANSKRUTI.pdf | 7 Dec 2020 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: F-1 SAI SANSKRUTI.pdf | 1 Aug 2020 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: F-2 SAI SANSKRUTI MAR-20.pdf | 1 Aug 2020 |
| Form 2AFile: F2A SAI SANSKRUTI.pdf | 17 Feb 2020 |
| Certificates of CA (Form 3)File: Sai Sankruti Building D- Phase.pdf | 4 Feb 2020 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: F-2 SAI SANSKRUTI DEC-19.pdf | 16 Jan 2020 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: F-1 SAI SANSKRUTI DEC-19.pdf | 15 Jan 2020 |
| Certificates of CA (Form 3)File: Sai sanskruti buld-D P -II 30-09-19.pdf | 11 Dec 2019 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: ''sai sanskruti phase ii building d ''.pdf | 29 Nov 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: f-1 sai sanskruti sep-19.pdf | 8 Nov 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: F-2 SANSKRUTI D SEP19.pdf | 8 Nov 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: F-2 SANSKRUTI D SEP19.pdf | 8 Nov 2019 |
| Form 2AFile: F-2A SAI SANSKRUTI D.pdf | 8 Nov 2019 |
| Certificates of CA (Form 3)File: Sai Sanskruti Building D-Phase II.pdf | 13 Aug 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: F1 SAI SANSKRUTI.pdf | 19 Jul 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer certificate sai sanskruti 1507.pdf | 19 Jul 2019 |
| Form 2AFile: F 2A SAI SANSKRUTI.pdf | 19 Jul 2019 |
| Certificates of CA (Form 3)File: SAI SANSKRUTI AS ON 31-12-2018.pdf | 20 May 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: F-2 SANSKRUTI M-19.pdf | 30 Apr 2019 |
| Form 2AFile: F-2A SANSKRUTI D-18.pdf | 30 Apr 2019 |
| Form 2AFile: F-2A SANSKRUTI M-19.pdf | 30 Apr 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: F-1 SAI SANSKRUTI M-19.pdf | 29 Apr 2019 |
| Certificates of CA (Form 3)File: Sai Sanskruti Building D Phese ii.pdf | 22 Feb 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: SAI SANSKRUTI ARCHIT CER 18-2-19-min.pdf | 19 Feb 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: SAI SANKSRUTI ENGINER 150119-min.pdf | 19 Feb 2019 |
| Certificates of CA (Form 3)File: Sai sanskruti Building D Phase II.pdf | 4 Dec 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engg sai sanskruti D.pdf | 28 Nov 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: arch sai sanskruti.pdf | 27 Nov 2018 |
| Certificates of CA (Form 5)File: Sai sanskruti Building D Phase 2.pdf | 4 Nov 2018 |
| Certificates of CA (Form 3)File: Sai Sanskruti Building.pdf | 24 Aug 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: JB SAI SANSKRUTI 2.pdf | 11 Aug 2018 |
| Certificates of CA (Form 3)File: Sai Sanskruti Building D- Phase - II.pdf | 26 Jul 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: enginner cert-sai sanskruti.pdf | 7 Jul 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects certificate sai Sanskruti 290618.pdf | 29 Jun 2018 |
| Declaration in FORM BFile: form b VI.pdf | 2 Feb 2018 |
| Certificates of CA (Form 3)File: SAI SANSKRUTI.pdf | 1 Feb 2018 |
| Details of encumbrancesFile: Scan.pdf | 24 Jan 2018 |
| Proforma of Allotment letterFile: SAI SANSKRUTI AGREEMENT TO SALE.pdf | 23 Jan 2018 |
| OtherFile: occpancy phase I sai sanskruti.pdf | 22 Aug 2017 |
| Layout approvalFile: Sai 2.pdf | 8 Aug 2017 |
| Building plan approvalFile: sai.PDF | 8 Aug 2017 |
| Copy of the legal title reportFile: SAI SANSKRUTI SEARCH REPORT.pdf | 8 Aug 2017 |
| Copy of Layout Approval (in case of layout)File: Sai 2.pdf | 8 Aug 2017 |
| Building Plan Approval (IOD)File: sai.PDF | 8 Aug 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: commencement dtype sai sanskruti.pdf | 8 Aug 2017 |
| PAN CardFile: 10 x 15 cm.pdf | 26 Jul 2017 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| SAI SANSKRUTI A B AND C BUILDING PHASE ONE | GUT NO 164 PART VILLAGE SATARA DIST AURANGABAD | 70 | Completed | Sep 2017 | Jun 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Aurangabad
Computed across the 1,400+ Aurangabad projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 49 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep SAI SANSKRUTI BUILDING D PHASE II on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near AURANGABAD1,400+ in Aurangabad
Capital Trade Centre
KRK Landmark LLP
AQ TOWN
AQ INFRASTRUCTURE PRIVATE LIMITED
KALYANI SAI VISHWA
RAJASHREE UDYOG
AMRUT SAI PLAZA PH 2
Shree Amrut Sai Developer Pvt.Ltd
PRASSANA HIGH CLASS CITY PHASE - I
SHRI KRISHNA NAGAR SAHAKARI GRAH NIRMAN SA
SHRIRAM RESIDENCY
UNIQUE BUILDCON
See every Aurangabad project, with the district possession charts
Builder: VIKAS INFRASTRUCTURE
VIKAS INFRASTRUCTURE has 1 registration on MahaRERA, including SAI SANSKRUTI BUILDING D PHASE II. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Aurangabad district page.
Frequently asked questions
What does it mean that SAI SANSKRUTI BUILDING D PHASE II shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if SAI SANSKRUTI BUILDING D PHASE II is delayed beyond 30 Dec 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SAI SANSKRUTI BUILDING D PHASE II?
The registered promoter entity is VIKAS INFRASTRUCTURE, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SAI SANSKRUTI BUILDING D PHASE II?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for SAI SANSKRUTI BUILDING D PHASE II?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SAI SANSKRUTI BUILDING D PHASE II?
The professionals named in the filing: Architect: R S JADHAV OF J B & ASSOCIATES; Engineer: N G KARKHANE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SAI SANSKRUTI BUILDING D PHASE II?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback