Home / Browse projects / Aurangabad, Maharashtra / SAI SANKUL

Registered No litigation declared Residential / Group Housing project

SAI SANKUL

By SHREE BALAJI BUILDERS

RG-MH-43497 · RERA P51500081095 · Last updated on MahaRERA portal: 27 Jun 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.

See what the report covers Free either way: or have every new Aurangabad registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedno revision filed
72 of 132Construction stages doneacross 12 buildings; furthest along: Internal walls, 80%
12 of 12Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 45 documents Report an error

SAI SANKUL is a Residential / Group Housing project by SHREE BALAJI BUILDERS in Aurangabad, Maharashtra, registered with MahaRERA as P51500081095 on 17 Feb 2026. Possession is promised by 31 Dec 2027. 0 of the 12 units on this registration are recorded sold or booked, and 72 of 132 construction stages are filed complete.

At a glance

Project

  • NameSAI SANKUL
  • TypeResidential / Group Housing
  • Location
    • GUT NO 213 PART
    • TISGAON CHOUFULI
    • Tisgaon
    • Aurangabad
    • 431136
  • Pincode431136
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51500081095
  • ReraGenie IDRG-MH-43497

Builder

  • NameSHREE BALAJI BUILDERS
  • Entity typePartnership
  • GSTIN27BBBPM7789M1ZS
  • Declared earlier projects1 →

Key dates

this monthRegisteredFeb 2026PromisedDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on17 Feb 2026
  • Promised completion31 Dec 2027
  • Revised completionNone
  • Buildings12 building records
  • Documents filed45 files

Current status

0%0 of 12 units booked
73.6%Work done, per cost certificate

Figures as on 27 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
R1 -LAND OWNERS SHARE ROW HOUSENA42101
R2-LAND OWNERS SHARE ROW HOUSENA42101
R3-DEVELOPERS SHARE ROW HOUSENA42101
R4-LAND OWNERS SHARE ROW HOUSENA42101
R5-LAND ONWERS SHARE ROW HOUSENA42101
R6 JOINTLY ONWED ROW HOSUE OF DEVELOPER AND LAND OWNERNA42101
R7-DEVELOPERS SHARE ROW HOUSENA42101
R8-DEVELOPERS SHARE ROW HOUSENA42101
R9-DEVELOPERS SHARE ROW HOSUENA42101
R10-DEVELOPERS SHARE ROW HOSUENA42101
R11-DEVELOPERS SHARE ROW HOUSENA42101
R12-DEVELOPERS SHARE ROW HOUSENA42101

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building12

As on 27 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

72 of 132 construction stages are filed complete across 12 buildings. The stage furthest along is Internal walls, at 80%.

R1 -LAND OWNERS SHARE ROW HOUSE80%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises70%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
R2-LAND OWNERS SHARE ROW HOUSE81%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises70%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.60%
R3-DEVELOPERS SHARE ROW HOUSE80%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises70%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
R4-LAND OWNERS SHARE ROW HOUSE80%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises70%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
R5-LAND ONWERS SHARE ROW HOUSE80%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises70%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
R6 JOINTLY ONWED ROW HOSUE OF DEVELOPER AND LAND OWNER80%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises70%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
R7-DEVELOPERS SHARE ROW HOUSE80%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises70%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
R8-DEVELOPERS SHARE ROW HOUSE80%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises70%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
R9-DEVELOPERS SHARE ROW HOSUE80%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises70%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
R10-DEVELOPERS SHARE ROW HOSUE80%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises70%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
R11-DEVELOPERS SHARE ROW HOUSE80%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises70%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
R12-DEVELOPERS SHARE ROW HOUSE80%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises70%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%

Progress on shared amenities15

As on 27 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area896 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on5 May 2026
LandownerVillageDistrict
RAJU BABURAO DABHADEWadgaon Kh.Aurangabad

Approvals and building plan

Sanctioning authorityCITY AND INDUSTRIAL DEVELOPMENT CORPORATION OF MAHARASHTRA LIMITED (CIDCO)
Permissible FSI2542.1
Proposed, not sanctioned1,241 sq m
Buildings approved12
Buildings sanctioned12

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPLOT NO 29 SERVICE INDUSTRY ZONE CIDCO AURANGABAD AURANGABAD MAHARASHTRA 431210
Estimated costRs 3.26 cr
Cost incurredRs 2.40 cr
Work done73.62%
BuildingWingEstimatedIncurred
R1 -LAND OWNERS SHARE ROW HOUSENARs 27.17 lakhRs 20.00 lakh
R2-LAND OWNERS SHARE ROW HOUSENARs 27.17 lakhRs 20.00 lakh
R3-DEVELOPERS SHARE ROW HOUSENARs 27.17 lakhRs 20.00 lakh
R4-LAND OWNERS SHARE ROW HOUSENARs 27.17 lakhRs 20.00 lakh
R5-LAND ONWERS SHARE ROW HOUSENARs 27.17 lakhRs 20.00 lakh
R6 JOINTLY ONWED ROW HOSUE OF DEVELOPER AND LAND OWNERNARs 27.17 lakhRs 20.00 lakh
R7-DEVELOPERS SHARE ROW HOUSENARs 27.17 lakhRs 20.00 lakh
R8-DEVELOPERS SHARE ROW HOUSENARs 27.17 lakhRs 20.00 lakh
R9-DEVELOPERS SHARE ROW HOSUENARs 27.17 lakhRs 20.00 lakh
R10-DEVELOPERS SHARE ROW HOSUENARs 27.17 lakhRs 20.00 lakh
R11-DEVELOPERS SHARE ROW HOUSENARs 27.17 lakhRs 20.00 lakh
R12-DEVELOPERS SHARE ROW HOUSENARs 27.17 lakhRs 20.00 lakh

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectR B RAUT AND ASSOCIATES
EngineerV B SABLE
EngineerTADEEBUDDIN TAUFIQUDDIN SIDDIQUI
Chartered AccountantKEDAR JOSHI & ASSOCAITES
Chartered AccountantMOHD FAIZAN KHALID KHAN
PartnerRole in project
SHREE BALAJI BUILDERS-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 24 Mar 2025
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 24 Mar 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 24 Mar 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 30 Oct 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed45

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1Sai Sankul.pdf27 Jun 2026
Withdrawal Update Form 2File: Form 2 Sai Sankul.pdf27 Jun 2026
Withdrawal Update Form 3File: shree balaji builders form 3.pdf27 Jun 2026
Form 2A (FY 2025-2026)File: Form 2 A Sai Sankul.pdf27 Jun 2026
Form 5 (FY 2025-2026)File: shree balaji builders form 5.pdf16 May 2026
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: DECLARATION FOR NOT OPENING SEPERATE ACCOUNT.pdf3 Feb 2026
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ROW HOUSE NO 6 DECLARATION.pdf3 Feb 2026
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 FINAL_compressed.pdf3 Feb 2026
Declaration about all RERA Designated Bank Accounts (Format A)File: DECLARATION FOR NOT OPENING SEPERATE ACCOUNT.pdf10 Jan 2026
Declaration about all RERA Designated Bank Accounts (Format A)File: ROW HOUSE NO 6 DECLARATION.pdf10 Jan 2026
Other - FinanceFile: ROW HOUSE NO 6 DECLARATION.pdf10 Jan 2026
Other - FinanceFile: DECLARATION FOR NOT OPENING SEPERATE ACCOUNT.pdf10 Jan 2026
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: DECLARATION FOR NOT OPENING SEPERATE ACCOUNT.pdf10 Jan 2026
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: ROW HOUSE NO 6 DECLARATION.pdf10 Jan 2026
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: development agreement_compressed.pdf22 Dec 2025
Other - FinanceFile: DECLARATION ABOUT JOINTLY ROW HOUSE-1.pdf22 Dec 2025
Other - FinanceFile: development agreement_compressed.pdf22 Dec 2025
Commencement Certificates / NA Order for plotted developmentFile: APPENDIX F SUBMISSION.pdf30 Oct 2025
Declaration in FORM BFile: NEW FORM B MORALE.pdf20 Sep 2025
Commencement Certificates / NA Order for plotted developmentFile: CC MAIL.pdf20 Sep 2025
Declaration about Commencement CertificateFile: Format - D.pdf20 Sep 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: FORMAT A FINAL.pdf20 Sep 2025
Other - TechnicalFile: ANNEXURE A DECLARATION CUM UNDERTING.pdf20 Sep 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: ANNEXURE A INTEREST IN OTHER MORALE.pdf20 Sep 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: ANNEXURE A INTEREST IN OTHER PROJECT CHAKKARWAR NEW.pdf20 Sep 2025
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: format B.pdf20 Sep 2025
Layout approvalFile: Sanction Layout_compressed.pdf24 Mar 2025
Building plan approvalFile: PLAN_compressed.pdf24 Mar 2025
PAN CardFile: FIRM PAN.pdf24 Mar 2025
Copy of the legal title reportFile: Search Report.pdf24 Mar 2025
Details of encumbrances concerned to FinanceFile: NO ENCUMBRANCES COMBINED.pdf24 Mar 2025
Copy of Layout Approval (in case of layout)File: Sanction Layout_compressed.pdf24 Mar 2025
Proforma of Allotment letterFile: MODEL FORM OF ALLOTMENT LETTER_compressed.pdf24 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form-01 Gut No-213_page-0001 (1).pdf24 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form-02 Gut No-213_page-0001 (1).pdf24 Mar 2025
Commencement Certificates / NA Order for plotted developmentFile: BUILDING PERMISSION_compressed.pdf24 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: PLAN_compressed.pdf24 Mar 2025
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD BOOK INVENTRY .pdf24 Mar 2025
CERSAI detailsFile: CERSAI.pdf24 Mar 2025
Deviation Report with respect to Allotment letterFile: DEVIATION REPORT ALLOTMENT LETTER.pdf24 Mar 2025
Details of encumbrances concerned to LegalFile: NO ENCUMBRANCES COMBINED.pdf24 Mar 2025
Deviation Report with respect to model copy of AgreementFile: DEVIATION REPORT AGREEMENT.pdf24 Mar 2025
Proforma of Agreement for saleFile: MODEL FORM OF AGREEMENT TO BE ENTERED INTO BETWEEN PROMOTER AND ALLOTTEE_compressed.pdf24 Mar 2025
Disclosure for secured/unsecured finance availed for the projectFile: DISCLOSURE FOR SECURED UNSECURED FINANCE AVAILED FOR THE PORJECT.pdf24 Mar 2025
Disclosure for secured/unsecured finance availed for the projectFile: INTEREST IN OTHER PROJECT MORALE.pdf24 Mar 2025

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 under way, not due yet
ProjectLocationFlatsRegisteredStatusPromisedDelivered
SAI NAKSHTRAPM1040002502306WALUJ MAHANAGAR, Aurangabad25Feb 2026OngoingDec 2030Not due yet

How this compares with Aurangabad

0%of this project is bookeddistrict median 6%
14%of Aurangabad projects moved their completion datethis one has not
32%of Aurangabad registrations have lapsed or been cancelledthis one is on the register

Computed across the 1,400+ Aurangabad projects on ReraGenie, from their own filings.

Keep SAI SANKUL on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near TISGAON CHOUFULI1,400+ in Aurangabad

2 kmSAI SANKULCompleted 22Lapsed / revoked 10Other 24Dot size: filed unitsN

Filed coordinates, straight-line distance. 56 registered projects within 2 km.

Builder: SHREE BALAJI BUILDERS

SHREE BALAJI BUILDERS has 1 registration on MahaRERA, including SAI SANKUL. Its filings disclose 1 earlier MahaRERA project, none completed yet. Read the full track record. See more projects on the Aurangabad district page.

Frequently asked questions

What are my rights if SAI SANKUL is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SAI SANKUL?

The registered promoter entity is SHREE BALAJI BUILDERS, a partnership as per the filing. Its GSTIN 27BBBPM7789M1ZS can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SAI SANKUL?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SAI SANKUL?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SAI SANKUL?

The professionals named in the filing: Architect: R B RAUT AND ASSOCIATES; Engineer: V B SABLE; Engineer: TADEEBUDDIN TAUFIQUDDIN SIDDIQUI; Chartered Accountant: KEDAR JOSHI & ASSOCAITES; Chartered Accountant: MOHD FAIZAN KHALID KHAN. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SAI SANKUL?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SAI SANKUL. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SAI SANKUL to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.