Home / Browse projects / Pune, Maharashtra / Sai Sankul

Registered No litigation declared Residential / Group Housing project

Sai Sankul

By UNICORN HOMES

RG-MH-12156 · RERA P52100011321 · Last updated on MahaRERA portal: 25 Apr 2025

Source: official MahaRERA filing

Red flags

  • Completion date moved by 91 months
  • 5 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Nov 2026Possession promisedmoved 91 months from the original
19 of 110Construction stages doneacross 10 buildings; furthest along: Staircases, 80%
0Complaints at MahaRERAon this registration
Jump to the 58 documents Report an error

Sai Sankul is a Residential / Group Housing project by UNICORN HOMES in Pune, Maharashtra, registered with MahaRERA as P52100011321 on 31 Aug 2017. Possession is promised by 10 Nov 2026. The completion date has moved by 91 months from the original filing.

At a glance

Project

  • NameSai Sankul
  • TypeResidential / Group Housing
  • Location
    • Shiraswadi Road
    • Shiraswadi
    • Haveli
    • Pune
    • 412207
  • Pincode412207
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100011321
  • ReraGenie IDRG-MH-12156

Builder

  • NameUNICORN HOMES
  • Entity typePartnership
  • PartnersMandar Mahendra Pawar, Ashok Rambhau Dhawale, Bhaskar Kisanrao Bhosale

Key dates

this monthRegisteredAug 2017First promiseApr 2019Revised toNov 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on31 Aug 2017
  • Promised completion10 Nov 2026
  • Revised completionRevised to 10 Nov 2026 (originally 15 Apr 2019)
  • Buildings10 building records
  • Documents filed58 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing ANA50000
Wing BNA50000
Wing CNA50000
Wing DNA50000
Wing ENA40000
Wing FNA40000
Wing GNA40000
Wing HNA40000
Wing INA40000
Wing JNA40000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building10

As on 25 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

19 of 110 construction stages are filed complete across 10 buildings. The stage furthest along is Staircases, at 80%.

Wing A21%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure20%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks10%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing B21%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure20%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks10%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing C36%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises20%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing D36%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises20%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing E39%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.33%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing F39%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.33%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing G39%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.33%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing H0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing I0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing J0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 25 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes20%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes70%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes70%
Street LightingYes100%
Community BuildingsYes15%
Treatment And Disposal Of Sewage And Sullage WaterYes25%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes50%
Energy managemcntYes50%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed72

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots72
Closed/Covered72
BuildingClosed/CoveredTotal
Wing A1212
Wing B1212
Wing C1212
Wing D1212
Wing E44
Wing F44
Wing G44
Wing H44
Wing I44
Wing J44

Land and ownership5

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area6,000 sq m
Land owned byThe promoter, with other names on the file
Named landowners5
LandownerVillageDistrict
Vijaykumar SargarAurangabad (M Corp.)Aurangabad
Ramchandra YadavLoni-kandPune
Digambar DahituleWAGHOLIPune
Surendra PingleChikhali Bk.Pune
Hiraman Kakade-Pune

Approvals and building plan

Permissible FSI4928.21
Proposed, not sanctioned4,928 sq m
Buildings approved10
Buildings sanctioned10

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchViman Nagar,Visionnaire,Plot no 121,Sakorenagar Society,Pune 411014

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMr Vishwanath Jagtap
PartnerRole in project
UNICORN HOMES-

Extensions applied for5

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100012020Apr 2019 → May 2023

Reason as filed by the promoterDue to covid19 pandemic construction work was not in operation. price inflation of raw material restricted us to build remaining buildings H, I and J. meanwhile electrical work is finished. electrical Transformer is installed on the site and individual electrical connections are provided to completed bulidings.

EXT52100008490Apr 2019 → Nov 2021

Reason as filed by the promoterDue to Corona Virus epidemic

EXT52100001703Apr 2019 → Apr 2020

Reason as filed by the promoterDelay in process of Plinth checking and arrangement of water pipeline from gramphanchyat.

EXT52100017735Apr 2019 → Aug 2024

Reason as filed by the promoterafter covid we have not started construction. now we are starting it.

EXT52100025057Apr 2019 → Nov 2026

Reason as filed by the promoterThere are 10 buildings sanctioned in the above mentioned project i.e. Building A, B, C, D, E, F, G, H, I & J. The project was started before existence of RERA. We started construction of 7 buildings i.e. building A to G.As RERA was applied in 2017, we applied for RERA registration with all 10 building. We have mentioned 0% work of building H, I & J in it; as construction of these building was not in process. We were not aware that buildings which were not started construction have not to be mentioned. We completed construction of 7 buildings only and 3 building i.e. H, I & J remained unconstru

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 6 Jun 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 10 Nov 2026

Documents filed58

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration in FORM BFile: Form B.pdf25 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Dec 2024_compressed.pdf25 Apr 2025
Certificates of CA (Form 3)File: Form 3 Dec 20224_compressed.pdf25 Apr 2025
Certificates of CA (Form 5)File: Form 5 17-18.pdf25 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Dec 2024.pdf25 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 19-20.pdf25 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 18-19.pdf25 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 19-20.pdf25 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 20-21.pdf25 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 20-21.pdf25 Apr 2025
Disclosure of sold/ booked inventoryFile: Circular 29.pdf25 Apr 2025
Declaration about Commencement CertificateFile: Format D.pdf25 Apr 2025
CERSAI detailsFile: Cersai Declaration.pdf25 Apr 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A.pdf25 Apr 2025
Other - TechnicalFile: PERT Chart.pdf25 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 21-22.pdf25 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 21-22.pdf25 Apr 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A.pdf25 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 22-23.pdf25 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A 23-24.pdf25 Apr 2025
Certificates of CA (Form 3)File: Form -3 2024.pdf18 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form -5 2024.pdf18 Nov 2024
Certificates of CA (Form 3)File: Form -3 2024.pdf18 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form -5 2024.pdf18 Nov 2024
Declaration in FORM BFile: Form B Affidavit.pdf15 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form- 1.pdf15 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form- 2.pdf15 Nov 2024
Other - TechnicalFile: Booked units,Tasks and Activity.pdf15 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form -2A.pdf15 Nov 2024
Declaration in FORM BFile: RESOLUTION OF ALLOTEES format -B.pdf11 Jan 2024
Declaration in FORM BFile: RESOLUTION OF ALLOTEES format -B.pdf11 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM A.pdf11 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf11 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2-A.pdf11 Jan 2024
Certificates of CA (Form 3)File: form 3.pdf11 Jan 2024
Certificates of CA (Form 5)File: form 5.pdf11 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: form 5.pdf11 Jan 2024
Certificates of CA (Form 5)File: Form 5.pdf11 Jun 2019
Commencement Certificates / NA Order for plotted developmentFile: CC 123.pdf6 Jun 2018
Commencement Certificates / NA Order for plotted developmentFile: CC456.pdf6 Jun 2018
Layout approvalFile: Plan 1.pdf30 Jul 2017
Details of encumbrancesFile: search report 001.pdf30 Jul 2017
Copy of Layout Approval (in case of layout)File: Plan 1.pdf30 Jul 2017
Proforma of Allotment letterFile: Agreement draft SaiSankul.pdf30 Jul 2017
Building plan approvalFile: Plan 1.pdf29 Jul 2017
Building plan approvalFile: plan 2.pdf29 Jul 2017
Building plan approvalFile: Plan 3.pdf29 Jul 2017
Building plan approvalFile: Plan 4.pdf29 Jul 2017
PAN CardFile: Unicorn Homes Pan Card.pdf29 Jul 2017
Copy of the legal title reportFile: Title Search report.pdf29 Jul 2017
Building Plan Approval (IOD)File: Plan 1.pdf29 Jul 2017
Building Plan Approval (IOD)File: plan 2.pdf29 Jul 2017
Building Plan Approval (IOD)File: Plan 3.pdf29 Jul 2017
Building Plan Approval (IOD)File: Plan 4.pdf29 Jul 2017
Declaration in FORM BFile: Form b pdf-ilovepdf-compressed.pdf29 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arichtect certificate 1.pdf29 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer ceertificate 1.pdf29 Jul 2017
Certificates of CA (Form 3)File: CA Certificate.pdf29 Jul 2017

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 91 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Sai Sankul on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Shiraswadi13,700+ in Pune

2 kmSai SankulCompleted 1Lapsed / revoked 2Other 2Dot size: filed unitsN

Filed coordinates, straight-line distance. 5 registered projects within 2 km.

Builder: UNICORN HOMES

UNICORN HOMES has 1 registration on MahaRERA, including Sai Sankul. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Sai Sankul is delayed beyond 10 Nov 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Sai Sankul?

The registered promoter entity is UNICORN HOMES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Sai Sankul?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Sai Sankul?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Sai Sankul?

The professionals named in the filing: Architect: Mr Vishwanath Jagtap. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Sai Sankul?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Sai Sankul. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Sai Sankul to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.