Home / Browse projects / Mumbai Suburban, Maharashtra / Sai Radha Complex

Completed No litigation declared Others project

Sai Radha Complex

By G. K. Realtors

RG-MH-25832 · RERA P51800010063 · Last updated on MahaRERA portal: 29 Aug 2023

Source: official MahaRERA filing

Red flags

  • Completion date moved by 37 months
  • 4 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jul 2022Possession promisedregistration recorded completed
18 of 22Construction stages doneacross 2 buildings; furthest along: Installation of Lifts, 95%
0Complaints at MahaRERAon this registration
Jump to the 103 documents Report an error

Sai Radha Complex is a Others project by G. K. Realtors in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800010063 on 23 Aug 2017. The registration is recorded completed; possession was promised by 20 Jul 2022. The completion date has moved by 37 months from the original filing.

At a glance

Project

  • NameSai Radha Complex
  • TypeOthers
  • Location
    • LBS MARG
    • BHANDUP WEST
    • Kurla
    • Mumbai Suburban
    • 400078
  • Pincode400078
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800010063
  • ReraGenie IDRG-MH-25832

Builder

  • NameG. K. Realtors
  • Entity typePartnership
  • PartnersKartik Shiva Thakur HUF, Ganesh Shiva Thakur
  • Other registrations1 more →
  • Completed2 of 2

Key dates

this monthRegisteredAug 2017First promiseJun 2019Revised toJul 2022Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on23 Aug 2017
  • Promised completion20 Jul 2022
  • Revised completionRevised to 20 Jul 2022 (originally 30 Jun 2019)
  • Buildings2 building records
  • Documents filed103 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Sai Indu Tower COMMERCIALNA170000
Sai Radha F Wing RESIDENTIALNA330000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 29 Aug 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

18 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Installation of Lifts, at 95%.

Sai Indu Tower COMMERCIAL82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Sai Radha F Wing RESIDENTIAL90%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%

Progress on shared amenities15

As on 29 Aug 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area12,609 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI15081.88
Proposed, not sanctioned14,090 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGROUND FLOOR, FILIX BUILDING, OPP ASIAN PAINTS, NEAR VIJAY SALES, LBS MARG, BHANDUP WEST, MUMBAI - 4

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectBhupendra Patrawala
ArchitectSuresh Kirtane
ArchitectFarukh Lokhandwalla
EngineerR C Tipnis
PartnerRole in project
G. K. Realtors-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800008688Jun 2019 → Mar 2021

Reason as filed by the promoterWe are extending our completion date from 29/12/2020 to 31/12/2021. As the Building No. 2 - ‘F’ Wing with Parking Tower is ready, but few Mechanical Stack parking's are yet to be erected for Occupation Certificate. The delay is due to lack of labours and professionals on filed. The labour’s of the stacker manufacturing company have gone to their native villages. Due to unavailability of labor’s, the manufacturing process is yet to take place and further delaying installations. The professionals who are also associated with the project have/had been infected and admitted to hospitals due to COV

EXT51800009537Jun 2019 → Dec 2021

Reason as filed by the promoterWe are currently applying for extention due to COVID pandemic and delay of Material of Stacker Parking. We had applied for an extension up to 31 December 2021. However, we were provided an extension up to 31 March 2021. Henceforth we are reapplying for an extension up to 31 December 2021 again.

EXT51800001916Jun 2019 → Jun 2020

Reason as filed by the promoterThe Parking Tower for 'F' Wing - Building No. 2 is ready but few Mechanical Stack parking's are yet to be erected. The delay is because of the objection from few members of the Old Buildings.

EXT51800017192Jun 2019 → Jul 2022

Reason as filed by the promoterOC application was applied; however, the certificate was received 3 weeks post RERA date. So we are applying for post factor extention as per OC certificate. Requesting you to please accept the extention and process the application. We have attached FORM 4 as well.

Litigation declared1

CaseCourtStatus
831/2016High CourtNo orders given

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 25 Sep 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 29 Aug 2023

Documents filed103

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 103 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: SAI INDU TOWER COMMERCIAL - FULL OC - CHE:ES:0548:S:337(NEW)-BCC:Amend(3).pdf29 Aug 2023
Architect’s Certificate on Completion of Project (Form 4)File: FORM 4.pdf29 Aug 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect letter -2 (1).pdf30 Jun 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Sai Radha Engineer Certificate.pdf30 Jun 2023
Certificates of CA (Form 3)File: CA Certificate March 2022.pdf30 Jun 2023
Certificates of CA (Form 3)File: CA Certificate July 2022.pdf30 Jun 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 2019 - 2020.pdf28 Jun 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 2020 - 2021.pdf28 Jun 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 2021 - 2022.pdf28 Jun 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: 2018 - 19.pdf28 Jun 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 2019 - 20.pdf28 Jun 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: 2020 - 21.pdf28 Jun 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: 2021 - 22.pdf28 Jun 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: 2022.pdf28 Jun 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC Certificate 1.pdf22 Jun 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC Certificate 2.pdf22 Jun 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC 1.pdf20 Oct 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC 2.pdf20 Oct 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects certificate sept 21.pdf10 Nov 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng certificate sept 21.pdf10 Nov 2021
Certificates of CA (Form 3)File: CA Certificate sept 2021.pdf10 Nov 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf27 Jul 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf27 Jul 2021
Certificates of CA (Form 3)File: FORM 3.pdf27 Jul 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf30 Mar 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf30 Mar 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Sai Radha_compressed.pdf30 Mar 2021
Certificates of CA (Form 3)File: CA Certificate.pdf30 Mar 2021
Certificates of CA (Form 3)File: CA dec 2020.pdf30 Mar 2021
Certificates of CA (Form 5)File: CA dec 2020.pdf30 Mar 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate f wing.pdf19 Mar 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer CertificatE.pdf19 Mar 2020
Certificates of CA (Form 3)File: CA Certificate.pdf19 Mar 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf14 Jan 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf14 Jan 2020
Certificates of CA (Form 3)File: CA Certificate.pdf14 Jan 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf17 Oct 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Commercial Architect Certificate.pdf17 Oct 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf17 Oct 2019
Certificates of CA (Form 3)File: CA Certificate.pdf17 Oct 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE.pdf14 Jun 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE.pdf14 Jun 2019
Certificates of CA (Form 3)File: CA CERTIFICATE.pdf14 Jun 2019
Certificates of CA (Form 5)File: G K FORM 5.pdf8 Jun 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE.pdf9 Mar 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE.pdf9 Mar 2019
Certificates of CA (Form 3)File: CA CERTIFICATE.pdf9 Mar 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate - Commercial.pdf10 Dec 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate - Residential.pdf10 Dec 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf10 Dec 2018
Certificates of CA (Form 3)File: CA Certificate.pdf10 Dec 2018
Commencement Certificates / NA Order for plotted developmentFile: f Wing - CC-.pdf25 Sep 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate - Residence.pdf25 Sep 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf24 Sep 2018
Certificates of CA (Form 3)File: CA Certificate - GK.pdf24 Sep 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Commercial.pdf27 Jun 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Residence.pdf27 Jun 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer certificate.pdf27 Jun 2018
Certificates of CA (Form 3)File: C A Certificate.pdf27 Jun 2018
Commencement Certificates / NA Order for plotted developmentFile: CC - Commercial Building.pdf10 Apr 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Commercial.pdf10 Apr 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Residence.pdf10 Apr 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer.pdf10 Apr 2018
Certificates of CA (Form 3)File: CA Certificate.pdf10 Apr 2018
Proforma of Allotment letterFile: G K Realtors - Sai Radha - Comm LOA.pdf31 Jul 2017
Proforma of Allotment letterFile: G K Realtors - Sai Radha - Resi LOA.pdf31 Jul 2017
Proforma of Allotment letterFile: Sai Indu COMMERCIAL - G K Realtors - Agreement PART 1.pdf31 Jul 2017
Proforma of Allotment letterFile: Sai Indu COMMERCIAL - G K Realtors - Agreement PART 2.pdf31 Jul 2017
Proforma of Allotment letterFile: Sai Indu COMMERCIAL - G K Realtors - Agreement PART 3.pdf31 Jul 2017
Proforma of Allotment letterFile: Sai Indu COMMERCIAL - G K Realtors - Agreement PART 4.pdf31 Jul 2017
Proforma of Allotment letterFile: Sai Radha (F) RESIDENTIAL - G K Realtors - Agreement PART 1.pdf31 Jul 2017
Proforma of Allotment letterFile: Sai Radha (F) RESIDENTIAL - G K Realtors - Agreement PART 2.pdf31 Jul 2017
Proforma of Allotment letterFile: Sai Radha (F) RESIDENTIAL - G K Realtors - Agreement PART 3.pdf31 Jul 2017
Proforma of Allotment letterFile: Sai Radha (F) RESIDENTIAL - G K Realtors - Agreement PART 4.pdf31 Jul 2017
OtherFile: Amalgamation Information.pdf31 Jul 2017
Building plan approvalFile: IOD - Building No 2 2011.pdf30 Jul 2017
Building plan approvalFile: IOD - Building No 1 2009.pdf30 Jul 2017
Layout approvalFile: Layout Letter.pdf30 Jul 2017
Layout approvalFile: Layout Plan.PDF30 Jul 2017
PAN CardFile: PAN CARD.pdf30 Jul 2017

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 37 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Sai Radha Complex on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near BHANDUP WEST6,700+ in Mumbai Suburban

2 kmSai Radha ComplexCompleted 83Lapsed / revoked 59Other 102Dot size: filed unitsN

Filed coordinates, straight-line distance. 244 registered projects within 2 km.

Builder: G. K. Realtors

G. K. Realtors has 2 registrations on MahaRERA, including Sai Radha Complex and Building No. 1 - Sai Indu Tower. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Sai Radha Complex is delayed beyond 20 Jul 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Sai Radha Complex?

The registered promoter entity is G. K. Realtors, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Sai Radha Complex?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Sai Radha Complex?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Sai Radha Complex?

The professionals named in the filing: Architect: Bhupendra Patrawala; Architect: Suresh Kirtane; Architect: Farukh Lokhandwalla; Engineer: R C Tipnis. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Sai Radha Complex?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Sai Radha Complex. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Sai Radha Complex to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.