Home / Browse projects / Raigarh, Maharashtra / SAI DHAM
SAI DHAM
RG-MH-34976 · RERA P52000014830 · Last updated on MahaRERA portal: 7 May 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 10 months past the filed date
- Completion date moved by 36 months
- 3 extensions taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SAI DHAM is a Residential / Group Housing project by Triple 8 Realty Pvt Ltd in Raigarh, Maharashtra, registered with MahaRERA as P52000014830 on 8 Jan 2018. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 36 months from the original filing. 20 of the 20 units on this registration are recorded sold or booked, and 8 of 11 construction stages are filed complete.
At a glance
Project
- NameSAI DHAM
- TypeResidential / Group Housing
- Location
- BOPELE DHAMOTE VILLAGE ROAD
- DHAMOTE
- Karjat
- Raigarh
- 410101
- Pincode410101
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52000014830
- ReraGenie IDRG-MH-34976
Builder
- NameTriple 8 Realty Pvt Ltd
- Entity typeCompany
- Managing DirectorsASHOK KUMAR GANDHI, RAHUL ASHOK GANDHI
- Other registrations1 more →
- No longer live1 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on8 Jan 2018
- Promised completion31 Dec 2025
- Revised completionRevised to 31 Dec 2025 (originally 30 Dec 2022)
- Buildings1 building record
- Documents filed74 files
Current status
Figures as on 7 May 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SAI DHAM | NA | 5 | 5 | 20 | 0 | 20 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 7 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
8 of 11 construction stages are filed complete. The stage furthest along is External plumbing and external plaster, at 99%.
SAI DHAM: 91% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 99% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 99% |
Progress on shared amenities15
As on 7 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 90% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed2
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| SAI DHAM | NA | Rs 1.63 cr | Rs 1.60 cr |
| - | NA | Rs 22.00 lakh | Rs 20.24 lakh |
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | MS THE DESIGN INDIA |
| Engineer | MS THE DESIGN INDIA |
| Chartered Accountant | Hitesh Mulchand shah |
| Partner | Role in project |
|---|---|
| Triple 8 Realty Pvt Ltd | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe promoter has completed 100% work of slab of superstructure and only the finishing work like electrical fittings, plumbing and plaster etc. are near completion.
Reason as filed by the promoterThe project got delayed due to issue with labour Contractor and some construction work pending like Plumbing, Plaster Etc.
Reason as filed by the promoterThe Project got delayed due to pending work of Electrical Meters.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 27 Dec 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 27 Dec 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 27 Dec 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 27 Dec 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed74
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 Sai Dham Q1 25-26.pdf | 7 May 2026 |
| Withdrawal Update Form 1File: Form 1 Q2 25-26.pdf | 7 May 2026 |
| Withdrawal Update Form 1File: Form 1 Q3 25-26.pdf | 7 May 2026 |
| Withdrawal Update Form 2File: Form 2 Sai Dham Q1 25-26.pdf | 7 May 2026 |
| Withdrawal Update Form 2File: Form 2 Q2 25-26.pdf | 7 May 2026 |
| Withdrawal Update Form 2File: Form 2 Q3 25-26.pdf | 7 May 2026 |
| Withdrawal Update Form 3File: Form 3 Sai Dham Q1 25-26.pdf | 7 May 2026 |
| Withdrawal Update Form 3File: Form 2 Q2 25-26.pdf | 7 May 2026 |
| Withdrawal Update Form 3File: Form 3 Q3 25-26.pdf | 7 May 2026 |
| Certificates of CA (Form 3)File: Final FORM 3.pdf | 28 May 2025 |
| Certificates of CA (Form 3)File: Final FORM 3.pdf | 28 May 2025 |
| Certificates of CA (Form 3)File: Final FORM 3.pdf | 28 May 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Final FORM 5.pdf | 28 May 2025 |
| Disclosure of sold/ booked inventoryFile: Inventory Sold Letter.pdf | 23 May 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Final FORM 1.pdf | 22 May 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Final FORM 1.pdf | 22 May 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Final FORM 1.pdf | 22 May 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Final FORM 1.pdf | 22 May 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Final FORM 1.pdf | 22 May 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Final FORM 2.pdf | 22 May 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Final FORM 2.pdf | 22 May 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Final FORM 2.pdf | 22 May 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Final FORM 2.pdf | 22 May 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Final FORM 2.pdf | 22 May 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf | 30 Apr 2025 |
| Certificates of CA (Form 3)File: Form-3-sign.pdf | 30 Apr 2025 |
| Certificates of CA (Form 3)File: Form-3-sign.pdf | 30 Apr 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 30 Apr 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf | 30 Apr 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf | 7 Apr 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf | 7 Apr 2025 |
| Declaration in FORM BFile: 2 Form B new.pdf | 25 Mar 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1.pdf | 28 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1.pdf | 28 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1.pdf | 28 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf | 28 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf | 28 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf | 28 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf | 7 May 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 7 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A.pdf | 7 May 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1.pdf | 26 Dec 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf | 26 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 22-23.pdf | 26 Dec 2023 |
| Disclosure of sold/ booked inventoryFile: SOLD INVENTORY.pdf | 26 Dec 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 2A 22-23.pdf | 26 Dec 2023 |
| Disclosure of sold/ booked inventoryFile: SOLD INVENTORY.pdf | 9 Dec 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM-5 (18-19).pdf | 20 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM-5(19-20).pdf | 20 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM-5(20-21).pdf | 20 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM-5(21-22).pdf | 20 Jan 2023 |
| Declaration about Commencement CertificateFile: DECLARTAION OF CC.pdf | 16 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1.pdf | 16 Jan 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM-2A(19-20).pdf | 16 Jan 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM-2A(20-21).pdf | 16 Jan 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM-2A(21-22).pdf | 16 Jan 2023 |
| Disclosure of sold/ booked inventoryFile: SOLD-UNSOLD INVENTORY.pdf | 16 Jan 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: DECLARTION OF SPRATE BANK.pdf | 16 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Ashok Gandhi Architect's Certificate_Sai Dham.pdf | 16 Jun 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Ashok Gandhi Engineer's Certificate_Sai Dham.pdf | 16 Jun 2021 |
| Certificates of CA (Form 5)File: FORM 5_SAI DHAM.pdf | 22 Oct 2018 |
| Declaration in FORM BFile: Form B compressed.pdf | 28 Dec 2017 |
| Proforma of Allotment letterFile: Maha Rera Agreement for Sale SAI DHAM.pdf | 28 Dec 2017 |
| Building plan approvalFile: CC_PLAN.pdf | 27 Dec 2017 |
| Layout approvalFile: CC_PLAN.pdf | 27 Dec 2017 |
| PAN CardFile: PAN CARD.pdf | 27 Dec 2017 |
| Copy of the legal title reportFile: TITTLE_CERTIFICATE.pdf | 27 Dec 2017 |
| Details of encumbrancesFile: NON ENCUMBRANCE.pdf | 27 Dec 2017 |
| Copy of Layout Approval (in case of layout)File: CC_PLAN.pdf | 27 Dec 2017 |
| Building Plan Approval (IOD)File: CC_PLAN.pdf | 27 Dec 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT_CERTIFICATE (1).pdf | 27 Dec 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE.pdf | 27 Dec 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEERS CERTIFICATE.pdf | 27 Dec 2017 |
| Certificates of CA (Form 3)File: Chartered Accountant CERTIFICATE.pdf | 27 Dec 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Raigarh
Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.
Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 74 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep SAI DHAM on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near DHAMOTE5,900+ in Raigarh
Filed coordinates, straight-line distance. 136 registered projects within 2 km.
ForeverLand
HOABL IMPACTUM LAND PRIVATE LIMITED
Chitrapatjanak Dadasaheb Phalke Township - Pha
Anukarati Homes Pvt Ltd
Olympeo Neo City
PRIZTINE INFRA LLP
DEEPJYOTI CITY
DeepJyoti Infra
VISION AARAMBH
M/s Vision Aarambh ( AOP )
Olympeo Riverside - Phase 3
Olympeo Riverside Projects LLP
See every Raigarh project, with the district possession charts
Builder: Triple 8 Realty Pvt Ltd
Triple 8 Realty Pvt Ltd has 2 registrations on MahaRERA, including Sai Darshan and SAI DHAM. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.
Frequently asked questions
What does it mean that SAI DHAM shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if SAI DHAM is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SAI DHAM?
The registered promoter entity is Triple 8 Realty Pvt Ltd, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SAI DHAM?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for SAI DHAM?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SAI DHAM?
The professionals named in the filing: Architect: MS THE DESIGN INDIA; Engineer: MS THE DESIGN INDIA; Chartered Accountant: Hitesh Mulchand shah. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SAI DHAM?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback