ReraGenieLog inGet a buyer report

Home / Browse projects / Nashik, Maharashtra / SAI COURT

Registered No litigation declared Others project

SAI COURT

By JAY WIN DEVELOPERS

RG-MH-13922 · RERA P51600029904 · Last updated on MahaRERA portal: 11 Aug 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 12 months from the original
7 of 11Construction stages donefurthest along: Internal walls, 85%
74 of 94Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 63 documents Report an error

SAI COURT is a Others project by JAY WIN DEVELOPERS in Nashik, Maharashtra, registered with MahaRERA as P51600029904 on 15 Jul 2021. Possession is promised by 26 Dec 2026. The completion date has moved by 12 months from the original filing. 20 of the 94 units on this registration are recorded sold or booked, and 7 of 11 construction stages are filed complete.

At a glance

Project

  • NameSAI COURT
  • TypeOthers
  • Location
    • NASHIK
    • 422005
  • Pincode422005
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51600029904
  • ReraGenie IDRG-MH-13922

Builder

  • NameJAY WIN DEVELOPERS
  • Entity typePartnership
  • PartnersVIJAY VASUDEO LALWANI, HITESH RATILAL KARIA
  • Declared earlier projects1 →

Key dates

this monthRegisteredJul 2021First promiseDec 2025Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on15 Jul 2021
  • Promised completion26 Dec 2026
  • Revised completionRevised to 26 Dec 2026 (originally 25 Dec 2025)
  • Buildings1 building record
  • Documents filed63 files

Current status

21%20 of 94 units booked
34.4%Work done, per cost certificate

Figures as on 11 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SAI COURTNA121288694

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 11 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 85%.

SAI COURT: 89% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises85%
Sanitary Fittings within the flats / premises70%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.85%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.40%

Progress on shared amenities15

As on 11 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes10%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes10%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes10%
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes10%

Parking filed51

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots51
Closed/Covered1
Open Space50

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area2,454 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on12 Dec 2025

Approvals and building plan

Sanctioning authorityEXECUTIVE ENGINEER NASHIK MUNCIPLE CORPORATION
Permissible FSI12655.85
Proposed, not sanctioned9,209 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKULKARNI BAUG, NASHIK
Estimated costRs 18.00 cr
Cost incurredRs 6.20 cr
Work done34.44%
BuildingWingEstimatedIncurred
SAI COURTNARs 17.00 crRs 6.20 cr
-NARs 1.00 cr-

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectHEMANT DUGAD
EngineerSHAILESH DHUMNE
EngineerBHUSHAN SHINTRE
Chartered AccountantSUNIL KUNDNANI KUNDNANI
Chartered AccountantS BRAMHECHA & CO
PartnerRole in project
JAY WIN DEVELOPERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA03012619261Dec 2025 → Dec 2026

Reason as filed by the promoterdue to labour shortage & some technical difficulaties

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jun 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 May 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 14 Oct 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 30 May 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 26 Dec 2026

Documents filed63

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 sai court.pdf11 Aug 2026
Withdrawal Update Form 2File: form 2 sai court.pdf11 Aug 2026
Withdrawal Update Form 3File: Scan 12 Dec 2025 (1).pdf11 Aug 2026
Withdrawal Update Form 1File: Form 1 sai court.pdf3 Jan 2026
Withdrawal Update Form 1File: Form 1 sai court.pdf3 Jan 2026
Withdrawal Update Form 2File: form 2 sai court.pdf3 Jan 2026
Withdrawal Update Form 2File: form 2 sai court.pdf3 Jan 2026
Withdrawal Update Form 3File: Scan 12 Dec 2025 (1).pdf3 Jan 2026
Withdrawal Update Form 3File: Scan 12 Dec 2025 (1).pdf3 Jan 2026
Form 2A (FY 2024-2025)File: Form 2 A of Sai Court.pdf3 Jan 2026
Form 5 (FY 2024-2025)File: Form 5 of Sai Court.pdf3 Jan 2026
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate - Sai Court (1).pdf24 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate - SAI COURT (1)_11zon.pdf24 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate - Sai Court (1).pdf24 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: DocScanner 23 Oct 2024 3-08 pm.pdf24 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Quality Assurance certificate - Sai Court (1).pdf24 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: DocScanner 23 Oct 2024 3-06 pm.pdf24 Oct 2024
Building plan approvalFile: HPSCANNER3936__1__11zon.pdf14 Oct 2024
Building plan approvalFile: HPSCANNER3935_11zon.pdf14 Oct 2024
Building Plan Approval / NA Order for plotted developmentFile: HPSCANNER3936__1__11zon.pdf14 Oct 2024
Building Plan Approval / NA Order for plotted developmentFile: HPSCANNER3935_11zon.pdf14 Oct 2024
Declaration about Commencement CertificateFile: commencement sai court 2024_11zon.pdf14 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: DocScanner 13 May 2024 1-54 pm.pdf13 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: DocScanner 13 May 2024 1-51 pm.pdf13 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: DocScanner 3 May 2024 1-23 pm_compressed.pdf3 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architecture Certificate_001_compressed.pdf10 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Sai Court Form-2_001_compressed.pdf8 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 388 -3.pdf8 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 30-3-22 388.pdf2 May 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 30-3-22 388.pdf2 May 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 30-9-22 388.pdf2 May 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 30-6-22 388.pdf2 May 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 31-12-22 388.pdf2 May 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: DOC-1.pdf27 Mar 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: DOC-2.pdf27 Mar 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: DOC-3.pdf27 Mar 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: DOC-4.pdf27 Mar 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 SAI COURT_001_11zon.pdf27 Mar 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 SAI COURT(2)_001_11zon.pdf27 Mar 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 SAI COURT(3)_001_11zon.pdf27 Mar 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 SAI COURT.pdf27 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: SAI COURT FORM 5.pdf27 Mar 2023
Declaration about Commencement CertificateFile: jay win circular 32 compressed.pdf30 Jun 2021
Copy of the legal title reportFile: legal tital repot-compressed-compressed.pdf29 Jun 2021
Copy of the legal title reportFile: New sai court title report ompressed.pdf14 Jun 2021
Layout approvalFile: Layout S No 388.pdf30 May 2021
Building plan approvalFile: 1.pdf30 May 2021
Building plan approvalFile: 2.pdf30 May 2021
Building plan approvalFile: 3.pdf30 May 2021
Building plan approvalFile: 4.pdf30 May 2021
Building plan approvalFile: 5.pdf30 May 2021
PAN CardFile: JAy win Pan Card.pdf30 May 2021
Details of encumbrancesFile: non encumbrance 388.pdf30 May 2021
Copy of Layout Approval (in case of layout)File: Layout S No 388.pdf30 May 2021
Building Plan Approval / NA Order for plotted developmentFile: 1.pdf30 May 2021
Building Plan Approval / NA Order for plotted developmentFile: 2.pdf30 May 2021
Building Plan Approval / NA Order for plotted developmentFile: 3.pdf30 May 2021
Building Plan Approval / NA Order for plotted developmentFile: 4.pdf30 May 2021
Building Plan Approval / NA Order for plotted developmentFile: 5.pdf30 May 2021
Commencement Certificates / NA Order for plotted developmentFile: Commencement Sai court.pdf30 May 2021
Declaration in FORM BFile: Form B jay win dev.pdf30 May 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Jaywin Sai form 3 compressed.pdf30 May 2021
Proforma of Allotment letterFile: Sai Court compressed.pdf30 May 2021

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
VIJAY SHRUSHTI BNASHIK1CompletedSep 2020Late, Oct 2020

How this compares with Nashik

21%of this project is bookeddistrict median 17%
10%of Nashik projects moved their completion datethis one moved by 12 months
19%of Nashik registrations have lapsed or been cancelledthis one is on the register

Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.

Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SAI COURT on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NASHIK4,100+ in Nashik

2 kmSAI COURTCompleted 44Lapsed / revoked 9Other 49Dot size: filed unitsN

Filed coordinates, straight-line distance. 102 registered projects within 2 km.

Builder: JAY WIN DEVELOPERS

JAY WIN DEVELOPERS has 1 registration on MahaRERA, including SAI COURT. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Nashik district page.

Frequently asked questions

What are my rights if SAI COURT is delayed beyond 26 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SAI COURT?

The registered promoter entity is JAY WIN DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SAI COURT?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SAI COURT?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SAI COURT?

The professionals named in the filing: Architect: HEMANT DUGAD; Engineer: SHAILESH DHUMNE; Engineer: BHUSHAN SHINTRE; Chartered Accountant: SUNIL KUNDNANI KUNDNANI; Chartered Accountant: S BRAMHECHA & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SAI COURT?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SAI COURT. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SAI COURT to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.