ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / Sai Arham

Completed No litigation declared Others project

Sai Arham

By Sai Anand Builders & Developers

RG-MH-44947 · RERA P52100052337 · Last updated on MahaRERA portal: 18 May 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedregistration recorded completed
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
15 of 30Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 86 documents Report an error

Sai Arham is a Others project by Sai Anand Builders & Developers in Pune, Maharashtra, registered with MahaRERA as P52100052337 on 14 Aug 2023. The registration is recorded completed; possession was promised by 31 Dec 2026. 15 of the 30 units on this registration are recorded sold or booked, and 10 of 11 construction stages are filed complete.

At a glance

Project

  • NameSai Arham
  • TypeOthers
  • Location
    • Survey No- 65
    • Hissa No- B/2/20
    • Kondhwa-Budruk
    • kondhwa BK
    • Haveli
    • Pune
    • 411048
  • Pincode411048
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100052337
  • ReraGenie IDRG-MH-44947

Builder

  • NameSai Anand Builders & Developers
  • Entity typePartnership
  • PartnersDeepak Kesharchand Dhoka, Trinkle Piyush Dugad, Shashikala Deepak Dhoka, Pinky Amit Bhansali

Key dates

this monthRegisteredAug 2023PromisedDec 2026Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on14 Aug 2023
  • Promised completion31 Dec 2026
  • Revised completionNone
  • Buildings1 building record
  • Documents filed86 files

Current status

50%15 of 30 units booked
100.0%Work done, per cost certificate

Figures as on 18 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Sai ArhamNA8828230

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 18 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

Sai Arham: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 18 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed56

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots56
Closed/Covered24
Open Space32

Land and ownership2

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,200 sq m
Land owned byNot the promoter
Named landowners2
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on4 Jul 2025
LandownerVillageDistrict
Indumati Zumbarlal LalwaniPune (M Corp.)Pune
Pratibha Pradeep LalwaniPune (M Corp.)Pune

Approvals and building plan

Sanctioning authorityPUNE MUNICIPAL CORPORATION
Permissible FSI2990.19
Proposed, not sanctioned2,988 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchHDFC Bank Ltd S No- 571/Crystal Roomnear Suryaprabha Gardenkenjale Nagar, Bibvewadi - Kondhwa
Estimated costRs 8.14 cr
Cost incurredRs 8.14 cr
Work done100.0%
BuildingWingEstimatedIncurred
Sai ArhamNARs 8.14 crRs 8.14 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectStudio SA Architect
EngineerSandip Rangdal & Associates
EngineerRanjit Pankhe
EngineerLokesh Nahar
Chartered AccountantPGMJ & Associates
Chartered AccountantNITISH VAIDYA & ASSOCIATES
PartnerRole in project
Sai Anand Builders & Developers-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 24 Jul 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 18 May 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 18 May 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 12 Apr 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed86

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 86 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Layout approvalFile: Sanction Plan..pdf18 May 2026
Building plan approvalFile: Building Plan..pdf18 May 2026
Form 2A (FY 2025-2026)File: Form 2A.pdf18 May 2026
Withdrawal Update Form 1File: Form 1.pdf21 Apr 2026
Withdrawal Update Form 2File: Form 2.pdf21 Apr 2026
Withdrawal Update Form 3File: Form.pdf21 Apr 2026
Form 2A (FY 2024-2025)File: Form 2A.pdf9 Mar 2026
Withdrawal Update Form 1File: Form 1.pdf2 Mar 2026
Withdrawal Update Form 2File: Form 2.pdf2 Mar 2026
Withdrawal Update Form 3File: Form.pdf2 Mar 2026
Form 5 (FY 2024-2025)File: Form 5 Final.pdf17 Feb 2026
Withdrawal Update Form 1File: Form 1.pdf14 Jan 2026
Withdrawal Update Form 2File: Form 2.pdf14 Jan 2026
Withdrawal Update Form 3File: Form 3.pdf14 Jan 2026
Withdrawal Update Form 1File: form 1.pdf19 Oct 2025
Withdrawal Update Form 2File: form 2 (1).pdf19 Oct 2025
Withdrawal Update Form 3File: Form 3.pdf19 Oct 2025
Withdrawal Update Form 1File: Form 1.pdf17 Oct 2025
Withdrawal Update Form 2File: Form 2.pdf17 Oct 2025
Withdrawal Update Form 3File: Form 3.pdf17 Oct 2025
Form 1File: Form 1 final.PDF18 Jul 2025
Form 2File: FORM 2 FINAL.pdf18 Jul 2025
Form 3File: Form 3 Final.pdf18 Jul 2025
Disclosure of Sold and Booked InventoryFile: sold circular final.pdf18 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 final.PDF19 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Final.pdf19 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 FINAL.pdf19 Apr 2025
Disclosure of sold/ booked inventoryFile: sold circular final.pdf19 Apr 2025
Layout approvalFile: Layout Plan.pdf12 Apr 2025
Building plan approvalFile: Building Plan.pdf12 Apr 2025
Copy of Layout Approval (in case of layout)File: Layout Plan.pdf12 Apr 2025
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf12 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: Building Plan.pdf12 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q3 FY 2024-2025.pdf18 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf18 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf17 Jan 2025
Disclosure of sold/ booked inventoryFile: Sold Circular.pdf17 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Final.pdf31 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q2 FY 2024-25.pdf23 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf20 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Final.pdf20 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf20 Oct 2024
Disclosure of sold/ booked inventoryFile: Sold Circular.pdf20 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Letter.PDF18 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.PDF18 Jul 2024
Disclosure of sold/ booked inventoryFile: Sold -Unsold Inventory.PDF18 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA- CERTIFICATE.PDF18 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SAI ARHAM ARCHITECT LETTER Q3 Upload.pdf17 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate Upload.pdf17 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: sai arham - engg letter Upload.pdf17 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 (1).pdf17 Apr 2024
Disclosure of sold/ booked inventoryFile: Sold Circular 29 Final.pdf17 Apr 2024
Disclosure of sold/ booked inventoryFile: Sold Circular.pdf17 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Upload.pdf17 Apr 2024
Layout approvalFile: PLAN 1_compressed.pdf14 Mar 2024
Building plan approvalFile: Plan 2.pdf14 Mar 2024
Copy of Layout Approval (in case of layout)File: PLAN 1_compressed.pdf14 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: Plan 2.pdf14 Mar 2024
Commencement Certificates / NA Order for plotted developmentFile: 20240313051638.pdf14 Mar 2024
Declaration about Commencement CertificateFile: 20240313051638.pdf14 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 (CA and Promoter Signed).pdf20 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: STUDIO SA ARCHITECT CERTIFICATE Final.pdf23 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE Final.pdf23 Nov 2023
Disclosure of sold/ booked inventoryFile: Sold Circular 29 Final.pdf23 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Final Signed.pdf23 Nov 2023
Details of encumbrances concerned to FinanceFile: Encumbrance Letter- Finance.pdf25 Jul 2023
Details of encumbrances concerned to FinanceFile: Encumbrance Letter- Legal.pdf25 Jul 2023
Details of encumbrances concerned to LegalFile: Encumbrance Letter- Finance.pdf25 Jul 2023
Details of encumbrances concerned to LegalFile: Encumbrance Letter- Legal.pdf25 Jul 2023
Declaration about Commencement CertificateFile: Format D.pdf25 Jul 2023
CERSAI detailsFile: Cersai of Declaration (3).pdf25 Jul 2023
Proforma of Allotment letterFile: Allotment Letter - Format 02052023.pdf25 Jul 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A.pdf25 Jul 2023
Copy of the legal title reportFile: Revised Title Report- Sai Arham (1)_11zon (2).pdf24 Jul 2023
Deviation Report with respect to model copy of AgreementFile: Deviation Allotment letter.pdf24 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate - Sai Anand Builders.pdf19 Jul 2023
Proforma of Agreement for saleFile: AFS.pdf19 Jul 2023
Deviation Report with respect to Allotment letterFile: Deviation Letter - Sai Aanand Builders (1).pdf19 Jul 2023
Declaration in FORM BFile: Form B- Promoter.pdf18 Jul 2023
Layout approvalFile: SACTION PLAN -1.pdf11 Jul 2023

How this compares with Pune

50%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Sai Arham on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kondhwa-Budruk13,700+ in Pune

2 kmSai ArhamCompleted 55Lapsed / revoked 35Other 84Dot size: filed unitsN

Filed coordinates, straight-line distance. 174 registered projects within 2 km.

Builder: Sai Anand Builders & Developers

Sai Anand Builders & Developers has 1 registration on MahaRERA, including Sai Arham. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Sai Arham is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Sai Arham?

The registered promoter entity is Sai Anand Builders & Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Sai Arham?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Sai Arham?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Sai Arham?

The professionals named in the filing: Architect: Studio SA Architect; Engineer: Sandip Rangdal & Associates; Engineer: Ranjit Pankhe; Engineer: Lokesh Nahar; Chartered Accountant: PGMJ & Associates; Chartered Accountant: NITISH VAIDYA & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Sai Arham?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Sai Arham. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Sai Arham to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.