ReraGenieLog inGet a buyer report

Home / Browse projects / Thane, Maharashtra / Sai Arcade

Registration lapsed No litigation declared Others project

Sai Arcade

By Sai Mangal Enterprises

RG-MH-26217 · RERA P51700003993 · Last updated on MahaRERA portal: 20 Jun 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 13 months past the filed date
  • 1 complaint at MahaRERA
  • Completion date moved by 45 months
  • 3 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Sep 2025Possession promised13 months past this date
13 of 33Construction stages doneacross 3 buildings; furthest along: Installation of Lifts, 95%
1Complaints at MahaRERAon this registration
Jump to the 80 documents Report an error

Sai Arcade is a Others project by Sai Mangal Enterprises in Thane, Maharashtra, registered with MahaRERA as P51700003993 on 7 Aug 2017. Possession was promised by 30 Sep 2025 and is now 13 months past that date. The completion date has moved by 45 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameSai Arcade
  • TypeOthers
  • Location
    • GANPATI MANDIR CROSS ROAD
    • PHADKE ROAD DOMBIVLI EAST
    • DOMBIVLI
    • Kalyan
    • Thane
    • 421201
  • Pincode421201
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700003993
  • ReraGenie IDRG-MH-26217

Builder

  • NameSai Mangal Enterprises
  • Entity typePartnership
  • PartnersSUBHASH GANGARAM PATIL, DEEPAK MAHADEV PAWAR

Key dates

13 months past promisethis monthRegisteredAug 2017First promiseDec 2021Revised toSep 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on7 Aug 2017
  • Promised completion30 Sep 2025
  • Revised completionRevised to 30 Sep 2025 (originally 30 Dec 2021)
  • Buildings3 building records
  • Documents filed80 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A WingNA110000
WING BNA150000
Proposed not sanctionedNA00000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 20 Jun 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

13 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Installation of Lifts, at 95%.

A Wing81%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
WING B79%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises75%
Sanitary Fittings within the flats / premises65%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.75%
Proposed not sanctioned0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 20 Jun 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed60

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots60
Closed/Covered60
BuildingClosed/CoveredTotal
A Wing3030
WING B3030

Land and ownership4

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,248 sq m
Land owned byThe promoter, with other names on the file
Named landowners4
LandownerVillageDistrict
ANANT BALKRUSHNA KHANDAGALEDOMBIVLIThane
KAMLAKAR SHANKAR JEJURKARDOMBIVLIThane
JITENDRA MADHUKAR JEJURKARDOMBIVLIThane
RAMAKANT MOTIRAM KHANDAGALEDOMBIVLIThane

Approvals and building plan

Permissible FSI4633.3
Proposed, not sanctioned4,633 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchDombivli East Branch 421201

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectUDAY MANSUKHLAL CHOPDA
EngineerE sturct Consultancy Pvt Ltd, MD Pankaj Kulkarni
Chartered AccountantJ L AGARWAL
PartnerRole in project
Sai Mangal Enterprises-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700011448Dec 2021 → Dec 2022

Reason as filed by the promoterTHERE IS A MATERAIL SHORTAGE SIMULTENEOUSLY LABOUR ALSO SHORTAGE DUE TO PANDEMIC CITUALTION OF COVID 19 PROKJECT WORK IS SLOW DUE TO MAIN REASON PROJECT IS NOT YET COMPLTED WE NEED EXTENTOIN PLEASE DO NEED FUL

EXT51700019813Dec 2021 → Sep 2025

Reason as filed by the promoterSHORTAGE OF MATERIAL AND LABOUR

EXT51700013841Dec 2021 → Mar 2024

Reason as filed by the promotera

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC006000000220828malhar darshan societySAI MANGAL ENTERPRISES15/04/2022

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 16 Feb 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 16 Feb 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 16 Feb 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed80

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration in FORM BFile: declaration form B Subhash Patil.pdf20 Jun 2024
Declaration about Commencement CertificateFile: Sai Mangal Enterprises Declaration about commencement certificate.pdf15 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Sai Mangal Enterprises Form 1 Architect Certificate.pdf15 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Sai Mangal Enterprises Form 2 Engineers Certificate.pdf15 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Sai Mangal Enterprises Form 2 A quality assurance certificate.pdf15 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Sai Mangal Enterprises Form 2 A quality assurance certificate.pdf15 May 2024
Disclosure of sold/ booked inventoryFile: Sai Mangal Enterprises Sold booked inventory (1).pdf15 May 2024
Certificates of CA (Form 3)File: Sai Mangal Enterprises Form 3 CA certificate - converted.pdf15 May 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Sai Mangal Enterprises Disclosure of other real estate Annexure A.pdf15 May 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: MAR 23.pdf15 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Saimangal Enterprises Form 2 Engineers Certificate.pdf4 Apr 2024
Certificates of CA (Form 3)File: Saimangal Enterprises Form 3 CA Certificate - converted.pdf4 Apr 2024
Proforma of Agreement for saleFile: FINAL DRAFT AGREEMENT - AS PER RERA 2024.pdf4 Apr 2024
Details of encumbrances concerned to FinanceFile: SAI MANGAL.pdf11 Mar 2023
Details of encumbrances concerned to LegalFile: SAI MANGAL.pdf11 Mar 2023
Declaration about Commencement CertificateFile: Sai Mangal Enterprise declaration about commencement certificate_0001.pdf11 Mar 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Sai Mangal Enterprise Architect Certificate form 1_0001.pdf11 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Sai Mangal Enterprises Engineers Certficate Form 2_0001 (1).pdf11 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Sai Mangal Enterprises Quality assurance certificate_0001.pdf11 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Sai Mangal Enterprises Quality assurance certificate_0001.pdf11 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Sai Mangal Enterprises Quality assurance certificate_0001.pdf11 Mar 2023
Disclosure of sold/ booked inventoryFile: Sai Mangal Enterprises Disclosure of sold-book inventory_0001 (1).pdf11 Mar 2023
Certificates of CA (Form 3)File: Sai Mangal Enterprises C A Certficate Form 3_0001 (1).pdf11 Mar 2023
Proforma of Allotment letterFile: Sai Mangal Enterprises Allotment letter_0001 (1).pdf11 Mar 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Sai Mangal Enterprise declaration Separate Bank account_0001.pdf11 Mar 2023
Deviation Report with respect to Allotment letterFile: Sai Mangal Enterprise Deviation Report _0001.pdf11 Mar 2023
Deviation Report with respect to model copy of AgreementFile: Sai Mangal Enterprise Deviation Report _0001.pdf11 Mar 2023
Layout approvalFile: PLAN 1.pdf16 Feb 2022
Layout approvalFile: PLAN 2.pdf16 Feb 2022
Layout approvalFile: PLAN 3.pdf16 Feb 2022
Layout approvalFile: PLAN 4.pdf16 Feb 2022
Building plan approvalFile: PLAN 1.pdf16 Feb 2022
Building plan approvalFile: PLAN 2.pdf16 Feb 2022
Building plan approvalFile: PLAN 3.pdf16 Feb 2022
Building plan approvalFile: PLAN 4.pdf16 Feb 2022
Copy of Layout Approval (in case of layout)File: PLAN 1.pdf16 Feb 2022
Copy of Layout Approval (in case of layout)File: PLAN 2.pdf16 Feb 2022
Copy of Layout Approval (in case of layout)File: PLAN 3.pdf16 Feb 2022
Copy of Layout Approval (in case of layout)File: PLAN 4.pdf16 Feb 2022
Building Plan Approval (IOD)File: PLAN 1.pdf16 Feb 2022
Building Plan Approval (IOD)File: PLAN 2.pdf16 Feb 2022
Building Plan Approval (IOD)File: PLAN 3.pdf16 Feb 2022
Building Plan Approval (IOD)File: PLAN 4.pdf16 Feb 2022
Commencement Certificates / NA Order for plotted developmentFile: AADESHPATRA.pdf16 Feb 2022
Declaration about Commencement CertificateFile: Sai Mangal enterprises format D_0001.pdf16 Feb 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf16 Feb 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf16 Feb 2022
CERSAI detailsFile: CERSAI.pdf16 Feb 2022
Certificates of CA (Form 3)File: FORM 3.pdf16 Feb 2022
Certificates of CA (Form 5)File: Form 5 Sai Mangal.pdf16 Oct 2018
Certificates of CA (Form 3)File: Form 3.pdf31 Jul 2017
Building plan approvalFile: scan0661-ilovepdf-compressed.pdf30 Jul 2017
Building plan approvalFile: scan0660-ilovepdf-compressed.pdf30 Jul 2017
Building plan approvalFile: Layout-ilovepdf-compressed.pdf30 Jul 2017
Building plan approvalFile: scan0659-ilovepdf-compressed (1).pdf30 Jul 2017
Layout approvalFile: scan0661-ilovepdf-compressed.pdf30 Jul 2017
Layout approvalFile: scan0660-ilovepdf-compressed.pdf30 Jul 2017
Layout approvalFile: scan0659-ilovepdf-compressed (1).pdf30 Jul 2017
Layout approvalFile: Layout-ilovepdf-compressed.pdf30 Jul 2017
PAN CardFile: sai mangal pan card.pdf30 Jul 2017
Copy of the legal title reportFile: Title 4997, 4998A.pdf30 Jul 2017
Copy of the legal title reportFile: Title 4998B, 4999, to 5011 and 5033-ilovepdf-compressed.pdf30 Jul 2017
Copy of the legal title reportFile: Title 5021 , 5024 to 5027.pdf30 Jul 2017
Copy of the legal title reportFile: Title 5021 to 5026.pdf30 Jul 2017
Copy of the legal title reportFile: Title 5028 to 5032.pdf30 Jul 2017
Details of encumbrancesFile: Encumbrances Certiicate.pdf30 Jul 2017
Copy of Layout Approval (in case of layout)File: Layout-ilovepdf-compressed.pdf30 Jul 2017
Copy of Layout Approval (in case of layout)File: scan0659-ilovepdf-compressed (1).pdf30 Jul 2017
Copy of Layout Approval (in case of layout)File: scan0660-ilovepdf-compressed.pdf30 Jul 2017
Copy of Layout Approval (in case of layout)File: scan0661-ilovepdf-compressed.pdf30 Jul 2017
Building Plan Approval (IOD)File: Layout-ilovepdf-compressed.pdf30 Jul 2017
Building Plan Approval (IOD)File: scan0659-ilovepdf-compressed (1).pdf30 Jul 2017
Building Plan Approval (IOD)File: scan0660-ilovepdf-compressed.pdf30 Jul 2017
Building Plan Approval (IOD)File: scan0661-ilovepdf-compressed.pdf30 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: IOD and CC Phadke.pdf30 Jul 2017
Declaration in FORM BFile: Form B-ilovepdf-compressed.pdf30 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch cert-ilovepdf-compressed.pdf30 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RCC engineer certificate-ilovepdf-compressed.pdf30 Jul 2017
Proforma of Allotment letterFile: Allotment letter.pdf30 Jul 2017
Proforma of Allotment letterFile: Agreement to sale _RERA_.pdf30 Jul 2017

How this compares with Thane

24%of Thane projects moved their completion datethis one moved by 45 months
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Sai Arcade on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near PHADKE ROAD DOMBIVLI EAST7,600+ in Thane

2 kmSai ArcadeCompleted 70Lapsed / revoked 56Other 112Dot size: filed unitsN

Filed coordinates, straight-line distance. 238 registered projects within 2 km.

Builder: Sai Mangal Enterprises

Sai Mangal Enterprises has 1 registration on MahaRERA, including Sai Arcade. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that Sai Arcade shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Sai Arcade is delayed beyond 30 Sep 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Sai Arcade?

The registered promoter entity is Sai Mangal Enterprises, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Sai Arcade?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Sai Arcade?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Sai Arcade?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Sai Arcade?

The professionals named in the filing: Architect: UDAY MANSUKHLAL CHOPDA; Engineer: E sturct Consultancy Pvt Ltd, MD Pankaj Kulkarni; Chartered Accountant: J L AGARWAL. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Sai Arcade?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Sai Arcade. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Sai Arcade to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.