ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai City, Maharashtra / SAI ARADHYA

Registered No litigation declared Residential / Group Housing project

SAI ARADHYA

By MANGALMURTI DEVELOPERS

RG-MH-04460 · RERA P51900023477 · Last updated on MahaRERA portal: 14 Aug 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 36 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai City registration emailed to you, free during the pilot beta.
Mar 2027Possession promisedmoved 36 months from the original
9 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 214 documents Report an error

SAI ARADHYA is a Residential / Group Housing project by MANGALMURTI DEVELOPERS in Mumbai City, Maharashtra, registered with MahaRERA as P51900023477 on 16 Dec 2019. Possession is promised by 31 Mar 2027. The completion date has moved by 36 months from the original filing.

At a glance

Project

  • NameSAI ARADHYA
  • TypeResidential / Group Housing
  • Location
    • D. L. VAIDYA ROAD
    • DADAR WEST
    • GNorth-400028
    • Ward GNorth
    • Mumbai City
    • 400028
  • Pincode400028
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900023477
  • ReraGenie IDRG-MH-04460

Builder

  • NameMANGALMURTI DEVELOPERS
  • Entity typePartnership
  • GSTIN27AAOFM2521J1Z5
  • PartnersSHIVAJI KONDIBA MANE, CHANDRASHEKHAR NARSINH SHENOY, AMIT RAMKRISHNA ACHAREKAR
  • Other registrations2 more →
  • Completed1 of 3
  • No longer live1 lapsed, de-registered or revoked

Key dates

this monthRegisteredDec 2019First promiseMar 2024Revised toMar 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on16 Dec 2019
  • Promised completion31 Mar 2027
  • Revised completionRevised to 31 Mar 2027 (originally 30 Mar 2024)
  • Buildings1 building record
  • Documents filed214 files

Current status

100.7%Work done, per cost certificate

Figures as on 14 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SAI ARADHYANA230000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 14 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

SAI ARADHYA: 82% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 14 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed54

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots54
Closed/Covered54

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area590 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on14 Aug 2026

Approvals and building plan

Sanctioning authorityMuncipal Corporation of Greater Mumbai
Permissible FSI4012.51
Proposed, not sanctioned4,013 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchHOTEL ROA BUILDING, LBS MARG, GHATKOPAR WEST, MUMBAI- 400 086
Estimated costRs 127.02 cr
Cost incurredRs 127.86 cr
Work done100.66%
BuildingWingEstimatedIncurred
SAI ARADHYANARs 63.51 crRs 63.93 cr
-NARs 63.51 crRs 63.93 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectGANESH P SHENOY
EngineerNISHANT SHIVAJI MANE
EngineerMAHENDRA T KASBE
EngineerGanesh Sugandhrao Mhamunkar
Chartered AccountantAGRAWAL IYER AND ASSOCIATES
Chartered AccountantAnkit Deepak Bajaj
PartnerRole in project
MANGALMURTI DEVELOPERS-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51900017329Mar 2024 → Mar 2025

Reason as filed by the promoterDue to delay in obtaining full CC from Municipal Corporation of Greater Mumbai

EXT51900027799Mar 2024 → Mar 2026

Reason as filed by the promoterDelay due to delay in getting necessary approvals and general slow down

EA24042620717Mar 2024 → Mar 2027

Reason as filed by the promoterWe respectfully submit that the project has been completed in all respects, and we have already obtained the Part Occupation Certificate (Part OC) in the year 2024. Further, we have applied for the Full Occupation Certificate (Full OC), which is presently pending approval with the MCGM. We would also like to inform you that all requisite No Objection Certificates (NOCs), including those from MHADA, Fire Department, and other concerned authorities, have been duly obtained for completion of the project. However, as the project approval has lapsed prior to the receipt of the Full OC-despite the a

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 21 Aug 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 23 Sep 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 23 Sep 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 18 May 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 21 Nov 2024

Documents filed214

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 214 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: June-26.pdf14 Aug 2026
Withdrawal Update Form 2File: Form2 Engineers Certificate 300626.pdf14 Aug 2026
Withdrawal Update Form 3File: Form 3-300626.pdf14 Aug 2026
Form 2A (FY 2025-2026)File: Form2a - Engineers Certificate for Quallity Assurance.pdf24 Apr 2026
Form 1File: Form-1 March-26.pdf17 Apr 2026
Form 2File: Form-2 Engineers Certificate 310326.pdf17 Apr 2026
Form 3File: Form 3-310326.pdf17 Apr 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold or Booked Inventory.pdf17 Apr 2026
Form 1File: Form-1 Mar-25.pdf12 Mar 2026
Form 2File: Form 2-Mar-25.PDF12 Mar 2026
Form 3File: Form 3-31032025.pdf12 Mar 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold or Booked Inventory.pdf12 Mar 2026
Form 1File: Form-1.pdf12 Mar 2026
Form 2File: Form-2.pdf12 Mar 2026
Form 3File: Form 3 - Final.PDF12 Mar 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold and booked inventory 311224.pdf12 Mar 2026
Form 1File: Form1.pdf12 Mar 2026
Form 2File: Form2.pdf12 Mar 2026
Form 3File: Form 3 - Final.pdf12 Mar 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold or Booked Inventory.pdf12 Mar 2026
Form 1File: Form-1.pdf12 Mar 2026
Form 2File: Form-2-Engineer Certiifcate.pdf12 Mar 2026
Form 3File: Form 3-300624 (final).pdf12 Mar 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold or Booked Inventory.pdf12 Mar 2026
Form 1File: Form-3 March-24.pdf12 Mar 2026
Form 2File: Form2 March-24.pdf12 Mar 2026
Form 3File: Form-3 March-24.pdf12 Mar 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold or Booked Inventory.pdf12 Mar 2026
Form 1File: Form-1 Architect Certificate.pdf12 Mar 2026
Form 2File: Engineer certificate Form 2.pdf12 Mar 2026
Form 3File: Form 3.pdf12 Mar 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Booked Inventory.pdf12 Mar 2026
Form 1File: Architect Certificate Q2.pdf12 Mar 2026
Form 2File: Form-2 Engineer Certificate.pdf12 Mar 2026
Form 3File: Form-3 Q2_.pdf12 Mar 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold or Booked Inventory 300923.pdf12 Mar 2026
Form 1File: Form-1-Architect Certificate.pdf12 Mar 2026
Form 2File: Form-2 Engineer Certiificate.pdf12 Mar 2026
Form 3File: Form 3- CA Certificate.PDF12 Mar 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold or Booked Inventory 3006623.pdf12 Mar 2026
Form 1File: Form-1 Architect Certificate.pdf12 Mar 2026
Form 2File: Form 2-Engineer Certificate.pdf12 Mar 2026
Form 3File: Form 3-310323.PDF12 Mar 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold or Booked Inventory 300423.pdf12 Mar 2026
Form 1File: Form 1 Architect Certificate Dec22.pdf12 Mar 2026
Form 2File: FORM 2.pdf12 Mar 2026
Form 3File: Form 3 Q3.pdf12 Mar 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of sold or booked Inventory_signed.pdf12 Mar 2026
Form 1File: Form1-Dec-25.pdf27 Jan 2026
Form 2File: Form-2 Engineers Certificate 311225.pdf27 Jan 2026
Form 3File: Form 3-311225.pdf27 Jan 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold or Booked Inventory.pdf27 Jan 2026
Form 1File: Form-1 300925.pdf1 Dec 2025
Form 2File: Form-2 300925.pdf1 Dec 2025
Form 3File: Form 3-300925.pdf1 Dec 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold or Booked Inventory.pdf1 Dec 2025
Form 5 (FY 2024-2025)File: Form 5.pdf1 Dec 2025
Form 1File: Form-1 June-25.pdf6 Nov 2025
Form 2File: Form-2 June-25.pdf6 Nov 2025
Form 3File: Form 3-300625.pdf6 Nov 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold or Booked Inventory.pdf6 Nov 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate april 2025.pdf15 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3-31032025.pdf15 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.PDF15 May 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold or Booked Inventory.pdf15 May 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form2A.PDF15 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 Mar-25.pdf8 May 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Annex-A RERA Bank Declaration.pdf8 May 2025
Declaration in FORM BFile: Form-B-Affidavit Cum Declaration.pdf20 Mar 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold or Booked Inventory.pdf20 Mar 2025
Disclosure for secured/unsecured finance availed for the projectFile: Disclosure of Sold or Booked Inventory.pdf20 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Final.PDF7 Mar 2025
CERSAI detailsFile: CERSAI_Search_Report.pdf7 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2.pdf27 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form2a.pdf27 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1.pdf9 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1.pdf9 Jan 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Part OC 020724.pdf21 Nov 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Part OC 020724.pdf21 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1.pdf25 Oct 2024

How this compares with Mumbai City

33%of Mumbai City projects moved their completion datethis one moved by 36 months
25%of Mumbai City registrations have lapsed or been cancelledthis one is on the register

Computed across the 780+ Mumbai City projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SAI ARADHYA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near DADAR WEST780+ in Mumbai City

2 kmSAI ARADHYACompleted 89Lapsed / revoked 71Other 103Dot size: filed unitsN

Filed coordinates, straight-line distance. 263 registered projects within 2 km.

Builder: MANGALMURTI DEVELOPERS

MANGALMURTI DEVELOPERS has 3 registrations on MahaRERA, including YASHWANT HEIGHTS and SAI ARADHYA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai City district page.

Frequently asked questions

What are my rights if SAI ARADHYA is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SAI ARADHYA?

The registered promoter entity is MANGALMURTI DEVELOPERS, a partnership as per the filing. Its GSTIN 27AAOFM2521J1Z5 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SAI ARADHYA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SAI ARADHYA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SAI ARADHYA?

The professionals named in the filing: Architect: GANESH P SHENOY; Engineer: NISHANT SHIVAJI MANE; Engineer: MAHENDRA T KASBE; Engineer: Ganesh Sugandhrao Mhamunkar; Chartered Accountant: AGRAWAL IYER AND ASSOCIATES; Chartered Accountant: Ankit Deepak Bajaj. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SAI ARADHYA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SAI ARADHYA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SAI ARADHYA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.