Home / Browse projects / Aurangabad, Maharashtra / Sahavas Apartments

Completed No litigation declared Residential / Group Housing project

Sahavas Apartments

By Yojak Developers

RG-MH-08420 · RERA P51500019967 · Last updated on MahaRERA portal: 29 Jan 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 43 months
  • 4 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Aurangabad registration emailed to you, free during the pilot beta.
Feb 2025Possession promisedregistration recorded completed
9 of 11Construction stages donefurthest along: Installation of Lifts, 98%
4 of 22Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 73 documents Report an error

Sahavas Apartments is a Residential / Group Housing project by Yojak Developers in Aurangabad, Maharashtra, registered with MahaRERA as P51500019967 on 15 Mar 2019. The registration is recorded completed; possession was promised by 13 Feb 2025. The completion date has moved by 43 months from the original filing. 18 of the 22 units on this registration are recorded sold or booked, and 9 of 11 construction stages are filed complete.

At a glance

Project

  • NameSahavas Apartments
  • TypeResidential / Group Housing
  • Location
    • Osmanpura
    • Aurangabad (M Corp.)
    • Aurangabad
    • 431001
  • Pincode431001
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51500019967
  • ReraGenie IDRG-MH-08420

Builder

  • NameYojak Developers
  • Entity typePartnership
  • PartnersSwati Shodhan Joshi, Neha Sameer Patil, Surekha Ashok Patil

Key dates

this monthRegisteredMar 2019First promiseJul 2021Revised toFeb 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on15 Mar 2019
  • Promised completion13 Feb 2025
  • Revised completionRevised to 13 Feb 2025 (originally 21 Jul 2021)
  • Buildings1 building record
  • Documents filed73 files

Current status

82%18 of 22 units booked
74.0%Work done, per cost certificate

Figures as on 29 Jan 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Sahavas ApartmentsNA7022022

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 29 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 98%.

Sahavas Apartments: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.98%

Progress on shared amenities15

As on 29 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes80%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes100%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes100%

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area936 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on31 Oct 2025

Approvals and building plan

Sanctioning authorityAurangabad Municipal Corporation, Aurangabad
Permissible FSI1157.72
Proposed, not sanctioned1,158 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKranti Chowk, Aurangabad
Estimated costRs 3.25 cr
Cost incurredRs 2.40 cr
Work done74.0%
BuildingWingEstimatedIncurred
Sahavas ApartmentsNARs 3.25 crRs 2.40 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectR S Jadhav
EngineerN G Karkhane
Chartered AccountantCA Santosh Garud
Chartered AccountantCA Sunil Salunke
PartnerRole in project
Yojak Developers-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51500019115Jul 2021 → Dec 2024

Reason as filed by the promoterDespite our earnest efforts, we are facing unforeseen challenges that have resulted in delays in the site development work for our project. These challenges have contributed to delays in multiple aspects of the project, including the development of the project site area, completion of finishing work, parking area, and plantation. The pending site development work is a critical aspect of the project, and we are committed to completing it to the highest standards. We seek your understanding and kind consideration in granting an extension to our project.

EXT51500010265Jul 2021 → Jun 2022

Reason as filed by the promoterDue to the severe adverse effect of the pandemic of COVID-19 and resulting lockdown restrictions effected by the competent authorities from time to time at local or state or national level, it was difficult to accomplish the said project within the said date of completion of 21/07/2021 as construction activities were suspended.

EXT51500013611Jul 2021 → Dec 2023

Reason as filed by the promoterThe Project “Sahavas Apartments” (P51500019967) of “Yojak Developers” is fully completed, Also the lift is installed and working. The application has been submitted for occupancy certificate of project at Aurangabad Municipal Corporation. But the Occupancy Certificate is in the process. Hence we require the project extension.

EA07112518270Jul 2021 → Feb 2025

Reason as filed by the promoterThe construction and development activities for the mentioned project were completed as per the planned schedule. However, the Occupancy Certificate (OC) from the competent authority was received on 13/02/2025, after the original completion date of 31/12/2024. To ensure full compliance with MahaRERA guidelines and to reflect the actual project status, we kindly seek your approval for an extension of the project timeline up to 13/02/2025. This extension will allow us to regularize the updated completion date in accordance with the RERA framework.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 18 Feb 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 18 Feb 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 18 Feb 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 18 Feb 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed73

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Final Form 1.pdf29 Jan 2026
Withdrawal Update Form 2File: Yojak Form 2 Q1.pdf29 Jan 2026
Withdrawal Update Form 3File: Yojak Form 3 - Q2 25-26.pdf29 Jan 2026
Form 1File: Final Form 1.pdf17 Dec 2025
Form 2File: Yojak Form 2 Q4 of 24-25.pdf17 Dec 2025
Form 3File: QPR Q4 2024-25.pdf17 Dec 2025
Disclosure of Sold and Booked InventoryFile: Sold Booked Inventory.pdf17 Dec 2025
Occupational CertificateFile: OC.pdf16 Dec 2025
Occupational CertificateFile: Completion Drawing_compressed.pdf16 Dec 2025
Occupational CertificateFile: Form 4.pdf16 Dec 2025
Occupational CertificateFile: Verification Mail..pdf16 Dec 2025
Occupational CertificateFile: Completion note.pdf16 Dec 2025
Withdrawal Update Form 1File: Final Form 1.pdf10 Dec 2025
Withdrawal Update Form 2File: Yojak Form 2 Q1.pdf10 Dec 2025
Withdrawal Update Form 3File: Yojak Form 3 - Q2 25-26.pdf10 Dec 2025
Form 1File: Final Form 1.pdf30 Oct 2025
Form 2File: Final Form 2.pdf30 Oct 2025
Form 3File: Form 3 Yojak Q3.pdf30 Oct 2025
Disclosure of Sold and Booked InventoryFile: Yojak sold unsold - Q3.pdf30 Oct 2025
Form 5 (FY 2024-2025)File: Form 5 - Yojak Developers.pdf30 Oct 2025
Certificates of CA (Form 3)File: Form 3.pdf30 Oct 2024
Certificates of CA (Form 3)File: Form 3.pdf30 Oct 2024
Certificates of CA (Form 3)File: Form 3.pdf28 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5.pdf28 Oct 2024
Declaration in FORM BFile: Form B.pdf19 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf19 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf19 Mar 2024
Form 2AFile: Form 2A.pdf19 Mar 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold .pdf19 Mar 2024
Certificates of CA (Form 3)File: Form 3.pdf19 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5.pdf15 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Architect's Certificate .pdf20 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q1 23-24.pdf20 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Q2 23-24.pdf20 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Engineer's Certificate.pdf20 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Q1 23-24.pdf20 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Q2 2023-24.pdf20 Nov 2023
Certificates of CA (Form 3)File: Form 3.pdf20 Nov 2023
Certificates of CA (Form 3)File: Form 3.pdf20 Nov 2023
Certificates of CA (Form 3)File: Form 3.pdf20 Nov 2023
Disclosure of sold/ booked inventoryFile: Sold Unsold Yojak.pdf19 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1.pdf16 Mar 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2.pdf16 Mar 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 3.pdf16 Mar 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 4.pdf16 Mar 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 5.pdf16 Mar 2023
Certificates of CA (Form 3)File: Form 3 18-19 Yojak _compressed.pdf10 Mar 2023
Certificates of CA (Form 3)File: Form 3 19-20 Yojak _compressed.pdf10 Mar 2023
Certificates of CA (Form 3)File: Form 3 20-21 Yojak _compressed.pdf10 Mar 2023
Certificates of CA (Form 3)File: Form 3 21-22 Yojak.pdf10 Mar 2023
Certificates of CA (Form 3)File: Form 3 Q1 22-23 Yojak.pdf10 Mar 2023
Certificates of CA (Form 3)File: Form 3 Q2 22-23 Yojak.pdf10 Mar 2023
Certificates of CA (Form 3)File: Form 3 Q3 22-23 Yojak.pdf10 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 21-22 .pdf10 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Yojak Developers From 5 18-19.pdf3 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Yojak Developers From 5 19-20.pdf3 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A_Signed.pdf22 Jul 2021
Declaration about Commencement CertificateFile: Declaration for Commencement Certificate_Signed.pdf20 Jul 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certficate-compressed.pdf20 Jul 2021
Form 2AFile: Form 2A_Signed.pdf20 Jul 2021
Disclosure of sold/ booked inventoryFile: Signed_Declaration for sold unsold units_compressed.pdf20 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 Signed.pdf20 Jul 2021
Form 2AFile: Form-2A.pdf6 Aug 2019
Declaration in FORM BFile: Affidavit-min.pdf22 Feb 2019
Certificates of CA (Form 3)File: FORM3.pdf22 Feb 2019
Proforma of Allotment letterFile: Proforma.pdf22 Feb 2019
Building plan approvalFile: Rera-1-.pdf18 Feb 2019
Layout approvalFile: Rera-1-.pdf18 Feb 2019
Copy of the legal title reportFile: Title Search Report.pdf18 Feb 2019
Details of encumbrancesFile: Title Search Report.pdf18 Feb 2019
Copy of Layout Approval (in case of layout)File: Rera-1-.pdf18 Feb 2019
Building Plan Approval (IOD)File: Rera-1-.pdf18 Feb 2019
Commencement Certificates / NA Order for plotted developmentFile: 20180626121202_00001min.pdf18 Feb 2019

How this compares with Aurangabad

82%of this project is bookeddistrict median 6%
14%of Aurangabad projects moved their completion datethis one moved by 43 months
32%of Aurangabad registrations have lapsed or been cancelledthis one is completed

Computed across the 1,400+ Aurangabad projects on ReraGenie, from their own filings.

Keep Sahavas Apartments on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Osmanpura1,400+ in Aurangabad

2 kmSahavas ApartmentsCompleted 29Lapsed / revoked 18Other 38Dot size: filed unitsN

Filed coordinates, straight-line distance. 85 registered projects within 2 km.

Builder: Yojak Developers

Yojak Developers has 1 registration on MahaRERA, including Sahavas Apartments. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Aurangabad district page.

Frequently asked questions

What are my rights if Sahavas Apartments is delayed beyond 13 Feb 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Sahavas Apartments?

The registered promoter entity is Yojak Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Sahavas Apartments?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Sahavas Apartments?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Sahavas Apartments?

The professionals named in the filing: Architect: R S Jadhav; Engineer: N G Karkhane; Chartered Accountant: CA Santosh Garud; Chartered Accountant: CA Sunil Salunke. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Sahavas Apartments?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Sahavas Apartments. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Sahavas Apartments to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.