Home / Browse projects / Mumbai Suburban, Maharashtra / Saffron Heights

Completed No litigation declared Residential / Group Housing project

Saffron Heights

By Pratham Varadvinayak Developers LLP

RG-MH-25696 · RERA P51800003304 · Last updated on MahaRERA portal: 10 Jan 2024

Source: official MahaRERA filing

Red flags

  • Completion date moved by 25 months
  • 4 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Oct 2023Possession promisedregistration recorded completed
11 of 11Construction stages doneevery applicable stage filed complete
0Complaints at MahaRERAon this registration
Jump to the 60 documents Report an error

Saffron Heights is a Residential / Group Housing project by Pratham Varadvinayak Developers LLP in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800003304 on 5 Aug 2017. The registration is recorded completed; possession was promised by 4 Oct 2023. The completion date has moved by 25 months from the original filing.

At a glance

Project

  • NameSaffron Heights
  • TypeResidential / Group Housing
  • Location
    • Veera Desai Road
    • Azad Nagar 2
    • Andheri
    • Mumbai Suburban
    • 400053
  • Pincode400053
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800003304
  • ReraGenie IDRG-MH-25696

Builder

  • NamePratham Varadvinayak Developers LLP
  • Entity typeOthers
  • Named personsMinawala Developers LLP, Dharmesh Minawala, Ashok Ramesh Rane

Key dates

this monthRegisteredAug 2017First promiseSep 2021Revised toOct 2023Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on5 Aug 2017
  • Promised completion4 Oct 2023
  • Revised completionRevised to 4 Oct 2023 (originally 30 Sep 2021)
  • Buildings1 building record
  • Documents filed60 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Saffron HeightsNA270000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 10 Jan 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 11 construction stages are filed complete.

Saffron Heights: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities16

As on 10 Jan 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes90%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes90%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes85%
Electrical meter room, sub-station, receiving stationYes90%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable
GymYes0%

Parking filed68

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots68
Closed/Covered68

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area890 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI7067.0
Proposed, not sanctioned7,067 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSwagatam opp Khar police station sv road khar west mumbai-400052

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAshok Rane
PartnerRole in project
Pratham Varadvinayak Developers LLP-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800016711Sep 2021 → Aug 2023

Reason as filed by the promoterDUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION TILL 31/08/2023

EXT51800013948Sep 2021 → May 2023

Reason as filed by the promoterThe company had placed ordered with M/s. Fujitec India Private Limited And M/s. Fujitec India Private Limited had instructed in its China office for arrangement of lift, however, due to unexpected lockdown in China, the material couldn’t be processed / shipped. Further, labor force was also not easily available during the interim period so installation was delayed. Therefore, we need an extension.

EXT51800017878Sep 2021 → Oct 2023

Reason as filed by the promoterwe have received the full OC for the project and accordingly we want to complete the project under RERA

EXT51800006173Sep 2021 → Sep 2022

Reason as filed by the promoterChange in law , being the planning authority was changed from MCGM to MHADA and all the permissions were noq required to be applied to and obtained from MHADA. force majeure conditions due to heavy rains pf the years 2017,2018,2019 . further change in Development Control (Promotion and Regulation) Act, 2034 came to be enforced which resulted in change of plans of the building.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 20 Oct 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 20 Oct 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 10 Oct 2023

Documents filed60

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: form 4.pdf10 Jan 2024
CERSAI detailsFile: CERSAI_Acknowledgemnt_Report_200285114108_For_Registration_Of_Security_Interest_30_10_202330 Oct 2023
CERSAI detailsFile: CERSAI_Acknowledgemnt_Report_200285148285_For_Registration_Of_Security_Interest_30_10_202330 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A FY 22-23.pdf27 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 22 to 23.pdf27 Oct 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC Plan Dated_1-3.pdf10 Oct 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC Plan Dated_4-end.pdf10 Oct 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: Society Regi Cert.pdf10 Oct 2023
Status of ConveyanceFile: Deed of Lease 37.pdf10 Oct 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 37-Full OC dated.pdf4 Oct 2023
Declaration in FORM BFile: Form B.pdf6 Jun 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate form 1.pdf6 Jun 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer certificate form 2.pdf6 Jun 2023
Disclosure of sold/ booked inventoryFile: Disclosure Of Sold Booked Inventory Details.pdf1 Jun 2023
Declaration about Commencement CertificateFile: Declaration about CC For RERA Format D.pdf19 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 19-20.pdf19 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 20-21.pdf19 May 2023
Certificates of CA (Form 3)File: Form 3 CA Certificate dated 04-02-2023.pdf3 Apr 2023
Certificates of CA (Form 3)File: CA Certificate Form 3_PVDLLP_31072022.pdf24 Mar 2023
Certificates of CA (Form 3)File: Chartered Accountants Certicate Form 3.pdf24 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 Scanned SOA FY 2018-19.pdf24 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 Annual Report April 19 to March 20.pdf24 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 FY 2020-21.pdf20 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 FY 2021-22.pdf20 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Quality Assurance certificate.pdf2 Mar 2023
Disclosure of sold/ booked inventoryFile: Declaration of Sold Unsold.pdf1 Mar 2023
Building plan approvalFile: IOD till 23f.pdf20 Oct 2021
Building Plan Approval (IOD)File: IOD till 23f.pdf20 Oct 2021
Commencement Certificates / NA Order for plotted developmentFile: CC tilll 23c.pdf20 Oct 2021
Details of encumbrancesFile: Declaration on Encrumbance.pdf7 Jul 2021
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf2 Jul 2021
Proforma of Allotment letterFile: AFS.pdf2 Jul 2021
Building plan approvalFile: IOD UPTO 15 FLOOR.pdf19 Mar 2021
Building Plan Approval (IOD)File: IOD UPTO 15 FLOOR.pdf19 Mar 2021
Building plan approvalFile: IOD dated 26-10-2020.pdf29 Oct 2020
Building Plan Approval (IOD)File: IOD dated 26-10-2020.pdf29 Oct 2020
Proforma of Allotment letterFile: AFS Minawala Saffron Heights UnadkatCo Final-RERA.pdf29 Oct 2020
Proforma of Allotment letterFile: AFS Minawala Saffron Heights UnadkatCo Final-RERA.pdf29 Oct 2020
Proforma of Allotment letterFile: Allotment Letter Minawala Saffron Heights UnadkatCo Final RERA.pdf29 Oct 2020
Proforma of Allotment letterFile: Allotment Letter Minawala Saffron Heights UnadkatCo Final-RERA.pdf29 Oct 2020
Annual Audit Report of Statutory CA (Form 5)File: Form 5 Annual Report April 19 to March 20-compressed.pdf25 Aug 2020
Proforma of Allotment letterFile: Allotment Letter_compressed.pdf25 Aug 2020
Proforma of Allotment letterFile: Agreement for Sale-compressed.pdf25 Aug 2020
Annual Audit Report of Statutory CA (Form 5)File: Form 5.pdf16 Sep 2019
Commencement Certificates / NA Order for plotted developmentFile: CC upto 6th floor.pdf28 May 2019
Commencement Certificates / NA Order for plotted developmentFile: 37 CC Copy.pdf25 Sep 2017
Proforma of Allotment letterFile: Combined AOS and allotment new12.pdf29 Jul 2017
Layout approvalFile: IOD Plan.pdf28 Jul 2017
Building plan approvalFile: IOD PART 1-.pdf28 Jul 2017
Building plan approvalFile: PART 2 IOD.pdf28 Jul 2017
PAN CardFile: Pratham PAN Attested.pdf28 Jul 2017
Copy of the legal title reportFile: Title Certificate-(SH).pdf28 Jul 2017
Details of encumbrancesFile: Encumbrance Certificate.pdf28 Jul 2017
Copy of Layout Approval (in case of layout)File: IOD Plan.pdf28 Jul 2017
Building Plan Approval (IOD)File: IOD PART 1-.pdf28 Jul 2017
Building Plan Approval (IOD)File: PART 2 IOD.pdf28 Jul 2017
Declaration in FORM BFile: FORM B Notarized_Compressed.pdf28 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect's certificate_Compressed.pdf28 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate.pdf28 Jul 2017
Certificates of CA (Form 3)File: CA Certificate final.pdf28 Jul 2017

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 25 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Saffron Heights on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Azad Nagar 26,700+ in Mumbai Suburban

2 kmSaffron HeightsCompleted 122Lapsed / revoked 91Abeyance 1Other 164Dot size: filed unitsN

Filed coordinates, straight-line distance. 378 registered projects within 2 km.

Builder: Pratham Varadvinayak Developers LLP

Pratham Varadvinayak Developers LLP has 1 registration on MahaRERA, including Saffron Heights. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Saffron Heights is delayed beyond 4 Oct 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Saffron Heights?

The registered promoter entity is Pratham Varadvinayak Developers LLP, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Saffron Heights?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Saffron Heights?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Saffron Heights?

The professionals named in the filing: Architect: Ashok Rane. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Saffron Heights?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Saffron Heights. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Saffron Heights to a free account