Home / Browse projects / Mumbai City, Maharashtra / RUSI MEHTA TOWERS

Completed No litigation declared Residential / Group Housing project

RUSI MEHTA TOWERS

By ANAHITA RUSI MEHTA

RG-MH-89065 · RERA P51900007228 · Last updated on MahaRERA portal: 28 Nov 2023

Source: official MahaRERA filing

Red flags

  • Completion date moved by 41 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai City registration emailed to you, free during the pilot beta.
Dec 2021Possession promisedregistration recorded completed
9 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 42 documents Report an error

RUSI MEHTA TOWERS is a Residential / Group Housing project by ANAHITA RUSI MEHTA in Mumbai City, Maharashtra, registered with MahaRERA as P51900007228 on 17 Aug 2017. The registration is recorded completed; possession was promised by 30 Dec 2021. The completion date has moved by 41 months from the original filing.

At a glance

Project

  • NameRUSI MEHTA TOWERS
  • TypeResidential / Group Housing
  • Location
    • Mumbai City
    • 400008
  • Pincode400008
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900007228
  • ReraGenie IDRG-MH-89065

Builder

  • NameANAHITA RUSI MEHTA
  • Entity typeIndividual

Key dates

this monthRegisteredAug 2017First promiseJul 2018Revised toDec 2021Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on17 Aug 2017
  • Promised completion30 Dec 2021
  • Revised completionRevised to 30 Dec 2021 (originally 31 Jul 2018)
  • Buildings1 building record
  • Documents filed42 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
RUSI MEHTA TOWERNA180000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 28 Nov 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

RUSI MEHTA TOWER: 82% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 28 Nov 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes40%
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area285 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI1326.93
Proposed, not sanctioned1,327 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGRANT ROAD EAST MUMBAI 400007

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPRAKASH DHARIA
EngineerV J JOSHI
Chartered AccountantVIRAL SHAH & CO
PartnerRole in project
ANAHITA RUSI MEHTA-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51900006108Jul 2018 → Jun 2021

Reason as filed by the promoterTHE PROJECT HAS GOT DELAYED DUE TO UNFORSEEN CIRCUMSTANCES ARISING IN PROCURING FURTHER C C FROM MCGM AND DUE TO THE DELAY IN COMPLETING INTERIOR FINISHING WORK

EXT51900000767Jul 2018 → Jul 2019

Reason as filed by the promoterDelay in issuance of Further CC by MCGM and due to delay in internal finishing work by labor contractor.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 4 Nov 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 4 Nov 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 14 Jul 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 9 Jul 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 16 Feb 2021

Documents filed42

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: Rera completin cert new format.pdf28 Nov 2023
CERSAI detailsFile: SRO NAREDCO Membership Form Sd-.pdf1 Mar 2022
CERSAI detailsFile: NWF1920SROTI529 RPM-M-NR519000030- Anitha.pdf1 Mar 2022
CERSAI detailsFile: SRO NAREDCO Membership Form Sd-.pdf1 Mar 2022
CERSAI detailsFile: NAREDCO.pdf1 Mar 2022
Declaration about Commencement CertificateFile: Declaration about Commencement Certificate as per Circular 32 .pdf24 Nov 2021
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Inventory Circular No 29 of 2021.pdf24 Nov 2021
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Unsold Inventory Circular No 29 2021.pdf31 Jul 2021
Declaration about Commencement CertificateFile: Declaration about Commencement Certificate C-32 2021.pdf30 Jul 2021
Building plan approvalFile: IOD DA EB 4980 11082014 .pdf14 Jul 2021
Building Plan Approval (IOD)File: IOD DA EB 4980 11082014 .pdf14 Jul 2021
Commencement Certificates / NA Order for plotted developmentFile: FurtherCC_signed 19-06-2018.pdf9 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Annual Audit Report of Statutory CA (Form 5) (FY 2020 - 21).pdf1 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Annual Audit Report of Statutory CA (Form 5) Y 2018 - 19).pdf1 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Annual Audit Report of Statutory CA (Form 5) (FYPeriod 2019 - 20).pdf1 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Annual Audit Report of Statutory CA (Form 5) (FY 2020 - 21).pdf1 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Annual Audit Report of Statutory CA (Form 5) (FY 2018-19).pdf30 Jun 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Annual Audit Report of Statutory CA (Form 5) (FYPeriod 2019-20).pdf30 Jun 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Annual Audit Report of Statutory CA (Form 5) (FY 2020-21).pdf30 Jun 2021
PAN CardFile: ARM PAN CARD.pdf26 Jun 2021
Declaration about Commencement CertificateFile: Declaration about Commencement Certificate.pdf26 Jun 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 2251789_OC_signed.pdf16 Feb 2021
Proforma of Allotment letterFile: Proforma of Allotment Letter and Agreement for Sale - Correct Document.pdf28 Jul 2020
Proforma of Allotment letterFile: Proforma of Allotment Letter and Agreement for Sale - Correct Document.pdf28 Jul 2020
Certificates of CA (Form 5)File: CA Certificate Form 5 for RERA.pdf19 Mar 2019
OtherFile: CA Certificate Form 5 for RERA.pdf19 Mar 2019
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf27 Mar 2018
Layout approvalFile: 2 IOD plan - Bapty Road.pdf4 Nov 2017
Copy of the legal title reportFile: 3 Title Report.pdf4 Nov 2017
Copy of Layout Approval (in case of layout)File: 2 IOD plan - Bapty Road.pdf4 Nov 2017
Proforma of Allotment letterFile: 1 Final RMT Allotment Letter and Sale Agreement-RERA-MOFA Format.pdf4 Nov 2017
Building plan approvalFile: BMC-IOD.pdf31 Jul 2017
Layout approvalFile: 291Bapty Road.pdf31 Jul 2017
Copy of the legal title reportFile: Affidavit.pdf31 Jul 2017
Details of encumbrancesFile: No Encumbrances (Signed).pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: 291Bapty Road.pdf31 Jul 2017
Building Plan Approval (IOD)File: BMC-IOD.pdf31 Jul 2017
Declaration in FORM BFile: Affidavit.pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect's - Certificate 001.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate.pdf31 Jul 2017
Certificates of CA (Form 3)File: CA-Certificate.pdf31 Jul 2017
Proforma of Allotment letterFile: ARM_IT_2017-07-29.pdf31 Jul 2017

How this compares with Mumbai City

33%of Mumbai City projects moved their completion datethis one moved by 41 months
25%of Mumbai City registrations have lapsed or been cancelledthis one is completed

Computed across the 780+ Mumbai City projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep RUSI MEHTA TOWERS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Mumbai City780+ in Mumbai City

2 kmRUSI MEHTA TOWERSCompleted 18Lapsed / revoked 41Other 101Dot size: filed unitsN

Filed coordinates, straight-line distance. 160 registered projects within 2 km.

Builder: ANAHITA RUSI MEHTA

ANAHITA RUSI MEHTA has 1 registration on MahaRERA, including RUSI MEHTA TOWERS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai City district page.

Frequently asked questions

What are my rights if RUSI MEHTA TOWERS is delayed beyond 30 Dec 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of RUSI MEHTA TOWERS?

The registered promoter entity is ANAHITA RUSI MEHTA, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in RUSI MEHTA TOWERS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for RUSI MEHTA TOWERS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at RUSI MEHTA TOWERS?

The professionals named in the filing: Architect: PRAKASH DHARIA; Engineer: V J JOSHI; Chartered Accountant: VIRAL SHAH & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in RUSI MEHTA TOWERS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About RUSI MEHTA TOWERS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save RUSI MEHTA TOWERS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.