Home / Browse projects / Mumbai Suburban, Maharashtra / Runwal Pinnacle

Registered No litigation declared Residential / Group Housing project

Runwal Pinnacle

By Runwal Enterprises Limited

RG-MH-03292 · RERA P51800021322 · Last updated on MahaRERA portal: 10 Jul 2026

Source: official MahaRERA filing

Red flags

  • 8 complaints at MahaRERA
  • Completion date moved by 30 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2028Possession promisedmoved 30 months from the original
10 of 55Construction stages doneacross 5 buildings; furthest along: Slabs of Super Structure, 86%
8Complaints at MahaRERAon this registration
Jump to the 412 documents Report an error

Runwal Pinnacle is a Residential / Group Housing project by Runwal Enterprises Limited in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800021322 on 21 Jun 2019. Possession is promised by 30 Dec 2028. The completion date has moved by 30 months from the original filing. 8 complaints are on record with the regulator.

At a glance

Project

  • NameRunwal Pinnacle
  • TypeResidential / Group Housing
  • Location
    • Goregaon Mulund Link Road
    • Mulund(West)
    • Kurla
    • Mumbai Suburban
    • 400080
  • Pincode400080
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800021322
  • ReraGenie IDRG-MH-03292

Builder

  • NameRunwal Enterprises Limited
  • Entity typeCompany
  • CINU70109MH2016PLC273223
  • GSTIN27AAICP4839P1ZL

Key dates

this monthRegisteredJun 2019First promiseJun 2026Revised toDec 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on21 Jun 2019
  • Promised completion30 Dec 2028
  • Revised completionRevised to 30 Dec 2028 (originally 30 Jun 2026)
  • Buildings5 building records
  • Documents filed412 files

Current status

41.1%Work done, per cost certificate

Figures as on 10 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower 1NA570000
Tower 2NA570000
Tower 3NA570000
Tower 4NA570000
Tower 5NA570000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building5

As on 10 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Slabs of Super Structure, at 86%.

Tower 146%
ActivityProgress
Excavation100%
Basement (if any)80%
Podiums (if any)85%
Plinth100%
Stilt Floor80%
Slabs of Super Structure52%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises9%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Tower 246%
ActivityProgress
Excavation100%
Basement (if any)80%
Podiums (if any)85%
Plinth100%
Stilt Floor80%
Slabs of Super Structure50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises9%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Tower 352%
ActivityProgress
Excavation100%
Basement (if any)80%
Podiums (if any)85%
Plinth100%
Stilt Floor80%
Slabs of Super Structure86%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises28%
Sanitary Fittings within the flats / premises7%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.2%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.7%
Tower 452%
ActivityProgress
Excavation100%
Basement (if any)80%
Podiums (if any)85%
Plinth100%
Stilt Floor80%
Slabs of Super Structure86%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises28%
Sanitary Fittings within the flats / premises6%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.1%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.6%
Tower 546%
ActivityProgress
Excavation100%
Basement (if any)80%
Podiums (if any)85%
Plinth100%
Stilt Floor80%
Slabs of Super Structure51%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises8%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 10 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed662

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots662
Closed/Covered662
BuildingClosed/CoveredTotal
Tower 1130130
Tower 2161161
Tower 3121121
Tower 4140140
Tower 5110110

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area4,926 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on2 Jul 2025

Approvals and building plan

Permissible FSI78152.28
Proposed, not sanctioned38,465 sq m
Buildings approved5
Buildings sanctioned5

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMatunga East Mumbai
Estimated costRs 717.72 cr
Cost incurredRs 295.07 cr
Work done41.11%
BuildingWingEstimatedIncurred
Tower 2NARs 129.15 crRs 53.04 cr
Tower 1NARs 126.17 crRs 43.26 cr
-NARs 125.75 crRs 37.34 cr
Tower 5NARs 120.15 crRs 43.61 cr
Tower 4NARs 115.08 crRs 63.27 cr
Tower 3NARs 101.41 crRs 54.55 cr

Certifying professionals and partners8

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAmit A Wasrani & Associates
EngineerSantosh Rawale
EngineerSuresh Sable
EngineerShashikant Ahire
EngineerUttam Kawathankar
Chartered AccountantKshirsagar & Associates
Chartered AccountantM B Agarwal and Co
Chartered AccountantSinghi & Co
PartnerRole in project
Runwal Enterprises Limited-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800018059Jun 2026 → Jun 2027

Reason as filed by the promoterProject completion has been delayed due to certain mitigating circumstances beyond the control of the Promoter

EA22042620690Jun 2026 → Dec 2028

Reason as filed by the promoterThe delay in completion of the Project has occurred due to post-pandemic disruptions, unanticipated site conditions such as hard rock strata requiring controlled blasting, and delays in the supply of key materials including aluminium shuttering. Further, the execution of the Project was adversely affected by contractor underperformance, irregular availability of essential construction materials, changes in the contract structure, delays in vendor finalisation, and seasonal manpower shortages, which collectively impacted the overall construction schedule and progress. In view of these circumsta

Litigation declared1

CaseCourtStatus
LC Suit No 100552/2013/2013CITY CIVIL COURT BOMBAYDisposed Off

Complaints filed with MahaRERA8

Case no.ComplainantRespondentFiled
CC006000000374829Umesh Baban KoradeRunwal Pinnacle17/03/2023
CC006000000429552SAGAR PHAPALERUNWAL APARTMENT PRIVATE LIMITED08/03/2024
CC12500528Cajetan PereiraRunwal Apartments Private Limited15/02/2025
CC12501762Sandeep Anil KudvaRunwal Apartments Private Limited29/05/2025
CC12503756Runwal Enterprises LimitedNanda Pravin Magdum27/10/2025
CC12503899Runwal Enterprises LimitedAruna Madhukar Dahiwal07/11/2025
CC12504526Runwal Enterprises LimitedMohd Saleem18/12/2025
CC12604270HEMANT UTTAM BANSODERunwal Enterprises Limited07/07/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 10 Jun 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 18 Sep 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 5 Aug 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 25 Jun 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Dec 2028

Documents filed412

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 412 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: Form 2A - Runwal Pinnacle (FY 2025 - 2026).pdf10 Jul 2026
Form 2A (FY 2019-2020)File: Form 2 A 19_20.pdf21 Apr 2026
Form 2A (FY 2020-2021)File: Form 2A (FY 2020-21).pdf21 Apr 2026
Form 2A (FY 2021-2022)File: Form 2A (FY 2021-22).pdf21 Apr 2026
Form 2A (FY 2022-2023)File: Form 2A (FY 2022-23).pdf21 Apr 2026
Form 2A (FY 2023-2024)File: Form 2A (FY 2023-24).pdf21 Apr 2026
Withdrawal Update Form 1File: Form 1 - Runwal Pinnacle - 31 March 2026.pdf20 Apr 2026
Withdrawal Update Form 1File: Form 1 - Runwal Pinnacle - 31 March 2026.pdf20 Apr 2026
Withdrawal Update Form 2File: Form 2 - Runwal Pinnacle - 31 March 2026.pdf20 Apr 2026
Withdrawal Update Form 2File: Form 2 - Runwal Pinnacle - 31 March 2026.pdf20 Apr 2026
Withdrawal Update Form 3File: Pinnacle - Form 3 - 31 March 2026.pdf20 Apr 2026
Withdrawal Update Form 3File: Pinnacle - Form 3 - 31 March 2026.pdf20 Apr 2026
Withdrawal Update Form 1File: Runwal Pinnacle - Form 1 - 31 December 2025.pdf17 Jan 2026
Withdrawal Update Form 2File: Form 2 - Engineering Certificate 31 December 2025 Pinnacle.pdf17 Jan 2026
Withdrawal Update Form 3File: Pinnacle Form 3 - 17 Jan 2026.pdf17 Jan 2026
Withdrawal Update Form 1File: Runwal Pinnacle - Form 1 - 31 December 2025.pdf16 Jan 2026
Withdrawal Update Form 2File: Form 2 - Engineering Certificate 31 December 2025 Pinnacle.pdf16 Jan 2026
Withdrawal Update Form 3File: Pinnacle Form 3 - 31 December 2025.pdf16 Jan 2026
Withdrawal Update Form 1File: Runwal Pinnacle - Form 1 - 30 Septemeber 2025.pdf15 Oct 2025
Withdrawal Update Form 1File: Runwal Pinnacle - Form 1 - 30 Septemeber 2025.pdf15 Oct 2025
Withdrawal Update Form 1File: Runwal Pinnacle - Form 1 - 30 Septemeber 2025.pdf15 Oct 2025
Withdrawal Update Form 1File: Runwal Pinnacle - Form 1 - 30 Septemeber 2025.pdf15 Oct 2025
Withdrawal Update Form 2File: Runwal Pinnacle - Form 2 - 30 September 2025.pdf15 Oct 2025
Withdrawal Update Form 2File: Runwal Pinnacle - Form 2 - 30 September 2025.pdf15 Oct 2025
Withdrawal Update Form 2File: Runwal Pinnacle - Form 2 - 30 September 2025.pdf15 Oct 2025
Withdrawal Update Form 2File: Runwal Pinnacle - Form 2 - 30 September 2025.pdf15 Oct 2025
Withdrawal Update Form 3File: Pinnacle Form 3 - 30 September 2025.pdf15 Oct 2025
Withdrawal Update Form 3File: Pinnacle Form 3 - 30 September 2025.pdf15 Oct 2025
Withdrawal Update Form 3File: Pinnacle Form 3 - 30 September 2025.pdf15 Oct 2025
Withdrawal Update Form 3File: Pinnacle Form 3 - 30 September 2025.pdf15 Oct 2025
Form 5 (FY 2024-2025)File: REL - Pinnacle - Form5 - April 2024 to March 2025 - 30 Septemeber 2025.pdf15 Oct 2025
Form 2A (FY 2024-2025)File: Runwal Pinnacle - Form 2A - Quality Assurance Certificate - 30 September 2025.pdf14 Oct 2025
Building plan approval or NA orderFile: Amend letter - 21 July 2025.pdf5 Aug 2025
Building plan approval or NA orderFile: Amended IOD Plans - 21 July 2025 - 1.pdf5 Aug 2025
Building plan approval or NA orderFile: Amended IOD Plans - 21 July 2025 - 2.pdf5 Aug 2025
Building plan approval or NA orderFile: Amended IOD Plans - 21 July 2025 - 3.pdf5 Aug 2025
Building plan approval or NA orderFile: Amended IOD Plans - 21 July 2025 - 4.pdf5 Aug 2025
Building plan approval or NA orderFile: Amended IOD Plans - 21 July 2025 - 5.pdf5 Aug 2025
Withdrawal Update Form 1File: Runwal Pinnacle - Form 1 - 1 April 2025 to June 2025.pdf21 Jul 2025
Withdrawal Update Form 2File: Runwal Pinnacle - Form 2 - 30 June 2025.pdf21 Jul 2025
Withdrawal Update Form 3File: Pinnacle Form 3 - 30 June 2025.pdf21 Jul 2025
Withdrawal Update Form 1File: Runwal Pinnacle - Form 1 - 1 April 2025 to June 2025.pdf18 Jul 2025
Withdrawal Update Form 1File: Runwal Pinnacle - Form 1 - 1 April 2025 to June 2025.pdf18 Jul 2025
Withdrawal Update Form 1File: Runwal Pinnacle - Form 1 - 1 April 2025 to June 2025.pdf18 Jul 2025
Withdrawal Update Form 2File: Runwal Pinnacle - Form 2 - 30 June 2025.pdf18 Jul 2025
Withdrawal Update Form 2File: Runwal Pinnacle - Form 2 - 30 June 2025.pdf18 Jul 2025
Withdrawal Update Form 2File: Runwal Pinnacle - Form 2 - 30 June 2025.pdf18 Jul 2025
Withdrawal Update Form 3File: Pinnacle Form 3 - 30 June 2025.pdf18 Jul 2025
Withdrawal Update Form 3File: Pinnacle Form 3 - 30 June 2025.pdf18 Jul 2025
Withdrawal Update Form 3File: Pinnacle Form 3 - 30 June 2025.pdf18 Jul 2025
Form 1File: Runwal Pinnacle_31 March 2025.pdf6 Jun 2025
Form 2File: R Pinnacle - Form 2 - 31 March 2025.pdf6 Jun 2025
Form 3File: Form 3 Pinnacle 31 March 2025.pdf6 Jun 2025
Disclosure of Sold and Booked InventoryFile: Pinnacle 31 March 2025_11zon (1).pdf6 Jun 2025
Self-declaration of Quarterly ProgressFile: Pinnacle 31 March 2025_11zon (1).pdf6 Jun 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: R Pinnacle - Form 2 - 31 March 2025.pdf19 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Runwal Pinnacle_31 March 2025.pdf18 Apr 2025
Disclosure of sold/ booked inventoryFile: Inventory.pdf18 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: R Pinnacle - Form 2 - 31 March 2025.pdf17 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Pinnacle 31 March 2025_11zon.pdf16 Apr 2025
Certificates of CA (Form 3)File: Form 3 Pinnacle 31 March 2025.pdf15 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: R Pinnacle RERA Form 2.pdf20 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: R Pinnacle RERA Form 2.pdf20 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: R Pinnacle RERA Form 2.pdf20 Jan 2025
Certificates of CA (Form 3)File: Pinnacle Form 3.pdf18 Jan 2025
Disclosure of sold/ booked inventoryFile: Runwal Pinnacle_11zon.pdf18 Jan 2025
Certificates of CA (Form 3)File: Pinnacle Form 3.pdf18 Jan 2025
Disclosure of sold/ booked inventoryFile: Runwal Pinnacle_11zon.pdf18 Jan 2025
Certificates of CA (Form 3)File: Pinnacle Form 3.pdf18 Jan 2025
Disclosure of sold/ booked inventoryFile: Runwal Pinnacle_11zon.pdf18 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Runwal Pinnacle - Form 1 - 31 Dec 2024.pdf10 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Runwal Pinnacle - Form 1 - 31 Dec 2024.pdf10 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Runwal Pinnacle - Form 1 - 31 Dec 2024.pdf10 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: R Pinnacle- RERA - Form 2 signed copy.pdf21 Oct 2024
Disclosure of sold/ booked inventoryFile: Pinnacle Inventory Dosclosure 30092024_11zon.pdf21 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: R Pinnacle- RERA - Form 2 signed copy.pdf21 Oct 2024
Disclosure of sold/ booked inventoryFile: Pinnacle Inventory Dosclosure 30092024_11zon.pdf21 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: R Pinnacle- RERA - Form 2 signed copy.pdf21 Oct 2024
Disclosure of sold/ booked inventoryFile: Pinnacle Inventory Dosclosure 30092024_11zon.pdf21 Oct 2024
Certificates of CA (Form 3)File: Pinnacle Form 3.pdf15 Oct 2024

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 30 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Runwal Pinnacle on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Mulund(West)6,700+ in Mumbai Suburban

2 kmRunwal PinnacleCompleted 102Lapsed / revoked 70Other 141Dot size: filed unitsN

Filed coordinates, straight-line distance. 313 registered projects within 2 km.

Builder: Runwal Enterprises Limited

Runwal Enterprises Limited has 1 registration on MahaRERA, including Runwal Pinnacle. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Runwal Pinnacle is delayed beyond 30 Dec 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Runwal Pinnacle?

The registered promoter entity is Runwal Enterprises Limited, a company as per the filing. Its CIN U70109MH2016PLC273223 and GSTIN 27AAICP4839P1ZL can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Runwal Pinnacle?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Runwal Pinnacle?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Runwal Pinnacle?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Runwal Pinnacle?

The professionals named in the filing: Architect: Amit A Wasrani & Associates; Engineer: Santosh Rawale; Engineer: Suresh Sable; Engineer: Shashikant Ahire; Engineer: Uttam Kawathankar; Chartered Accountant: Kshirsagar & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Runwal Pinnacle?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Runwal Pinnacle. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Runwal Pinnacle to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.