Home / Browse projects / Thane, Maharashtra / RUDRAKSH TOWER

Registered No litigation declared Residential / Group Housing project

RUDRAKSH TOWER

By SHIVSHAKTI BUILDERS AND DEVELOPERS

RG-MH-28558 · RERA P51700026748 · Last updated on MahaRERA portal: 5 Aug 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 30 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 30 months from the original
3 of 11Construction stages donefurthest along: Stilt Floor, 95%
25 of 36Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 219 documents Report an error

RUDRAKSH TOWER is a Residential / Group Housing project by SHIVSHAKTI BUILDERS AND DEVELOPERS in Thane, Maharashtra, registered with MahaRERA as P51700026748 on 22 Oct 2020. Possession is promised by 31 Dec 2026. The completion date has moved by 30 months from the original filing. 11 of the 36 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete.

At a glance

Project

  • NameRUDRAKSH TOWER
  • TypeResidential / Group Housing
  • Location
    • DIN DAYAL ROAD
    • VILLAGE SHIVAJI NAGAR
    • DOMBIVLI
    • Kalyan
    • Thane
    • 421202
  • Pincode421202
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700026748
  • ReraGenie IDRG-MH-28558

Builder

  • NameSHIVSHAKTI BUILDERS AND DEVELOPERS
  • Entity typePartnership
  • PartnersLAXMAN BAMA MHATRE, YASHWANT APPA KAMBLE
  • Other registrations2 more →
  • Completed1 of 3
  • No longer live1 lapsed, de-registered or revoked

Key dates

this monthRegisteredOct 2020First promiseJun 2024Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on22 Oct 2020
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 30 Jun 2024)
  • Buildings1 building record
  • Documents filed219 files

Current status

31%11 of 36 units booked
95.4%Work done, per cost certificate

Figures as on 5 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
RUDRAKSH TOWERNA161436036

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 5 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Stilt Floor, at 95%.

RUDRAKSH TOWER: 77% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor95%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.85%

Progress on shared amenities15

As on 5 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsYes50%
Landscaping & Tree PlantingYes50%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes10%
Electrical meter room, sub-station, receiving stationYes90%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed11

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots11
Closed/Covered5
Open Space6

Land and ownership6

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,354 sq m
Land owned byThe promoter, with other names on the file
Named landowners6
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on3 Jul 2026
LandownerVillageDistrict
Bholanath Dattu MhatreDOMBIVLIThane
Manohar Dattu MhatreDOMBIVLIThane
Madhukar Dattu MhatreDOMBIVLIThane
Navnath Dattu MhatreDOMBIVLIThane
Janardhan Dattu MhatreDOMBIVLIThane
Harishchandra Dattu MhatreDOMBIVLIThane

Approvals and building plan

Sanctioning authorityKalyan-Dombivli Municipal Corporation
Permissible FSI1020.76
Proposed, not sanctioned1,021 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchDOMBIVLI WEST
Estimated costRs 6.35 cr
Cost incurredRs 6.06 cr
Work done95.37%
BuildingWingEstimatedIncurred
RUDRAKSH TOWERNARs 5.49 crRs 5.32 cr
-NARs 86.25 lakhRs 73.31 lakh

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSHIRISH GAJANAN NACHANE
EngineerRAJESH THAKARE & ASSOCIATES
Chartered AccountantABHIRUCHI V PARANJAPE & CO
Chartered AccountantDHANDEKAR METHWANI & CO
Chartered AccountantHARIYANI & ASSOCIATES
PartnerRole in project
SHIVSHAKTI BUILDERS AND DEVELOPERS-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700024805Jun 2024 → Mar 2026

Reason as filed by the promoterDear Sir/Madam, We are writing to update you on the status of our project, which commenced on January 1, 2020. The excavation work involves combined footings with a depth of 25 feet, consisting of two levels of tie beams, followed by a plinth slab. However, due to the COVID-19 pandemic, which hit on March 23, 2020, our progress was halted after completing the second-level tie beam. Our labor contractor returned to their native place and did not come back, settling there permanently. As you are aware, the incomplete plinth slab made it challenging to find a new contractor willing to take on the

EA13072621737Jun 2024 → Dec 2026

Reason as filed by the promoterShortage of Funds due to low demand: The real estate project, situated in a remote area, has faced significant challenges due to limited customer bookings, resulting in a lower-than-anticipated response from prospective buyers. This lack of adequate buyer interest adversely impacted the financial inflow required for the timely completion of the project, as the anticipated funding from customer bookings could not be realized. Despite these challenges, the promoters have demonstrated unwavering commitment to the project's completion by arranging the necessary funds through the liquidation of per

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 6 Nov 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 6 Oct 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 8 Sep 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 8 Sep 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed219

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 219 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 1_ JUNE 26_ RUDRAKSH TOWER.pdf5 Aug 2026
Withdrawal Update Form 2File: FORM 2_ JUNE 26_ RUDRAKSH TOWER.pdf5 Aug 2026
Withdrawal Update Form 3File: FORM 3_ JUNE 26_ RUDRAKSH TOWER_compressed.pdf5 Aug 2026
Form 1File: FORM 1_ JUNE 25_ RUDRAKSH TOWER.pdf3 Jul 2026
Form 2File: FORM 2_ JUNE 25_ RUDRAKSH TOWER.pdf3 Jul 2026
Form 3File: FORM 3_ JUNE 25_ RUDRAKSH TOWER.pdf3 Jul 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD_ JUNE 25_ RUDRAKSH TOWER.pdf3 Jul 2026
Form 1File: FORM 1_ SEP 25_ RUDRARAKSH TOWER.pdf3 Jul 2026
Form 2File: FORM 2_ SEP 25_ RUDRAKSH TOWER.pdf3 Jul 2026
Form 3File: FORM 3_ SEP 25_ RUDRAKSH TOWER.pdf3 Jul 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD_ SEP 25_ RUDRAKSH TOWER.pdf3 Jul 2026
Form 1File: FORM 1_ DEC 25_ RUDRAKSH TOWER.pdf3 Jul 2026
Form 2File: FORM 2_ DEC 25_ RUDRAKSJH TOWER.pdf3 Jul 2026
Form 3File: FORM 3_ DEC 25_ RUDRAKSH TOWER.pdf3 Jul 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD_ DEC 25_ RUDRAKSH TOWER.pdf3 Jul 2026
Form 1File: FORM 1_ MARCH 26_ RUDRAKSH TOWER.pdf3 Jul 2026
Form 2File: FORM 2_ MARCH 26_ RUDRAKSH TOWER.pdf3 Jul 2026
Form 3File: FORM 3_ MARCH 26_ RUDRAKSH TOWER_compressed.pdf3 Jul 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD_ MARCH 26_ RUDRAKSH TOWER.pdf3 Jul 2026
Form 2A (FY 2024-2025)File: FORM 2A_ MARCH 25_ RUDRAKSH TOWER.pdf3 Jul 2026
Form 2A (FY 2025-2026)3 Jul 2026
Form 2A (FY 2025-2026)File: FORM 2A_ MARCH 26_ RUDRAKASH TOWER.pdf3 Jul 2026
Form 5 (FY 2024-2025)File: FORM 5_ MARCH 25_ RUDRAKSH TOWER.pdf3 Jul 2026
Form 5 (FY 2025-2026)File: FORM 5_ MARCH 26_ RUDRAKSH TOWER.pdf3 Jul 2026
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 dated 31-12-24 Rudraksh Tower_compressed.pdf11 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Dated 31-12-24 Rudraksh tower.pdf11 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Dated 31-12-2024 Rudraksh tower.pdf11 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 dated 31-12-24 Rudraksh Tower_compressed.pdf11 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Dated 31-12-24 Rudraksh tower.pdf11 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Dated 31-12-2024 Rudraksh tower.pdf11 Feb 2025
Other - FinanceFile: ligitimate reason for delay.pdf23 Dec 2024
Other - FinanceFile: ligitimate reason for delay.pdf23 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Dated 30 Sept 2024 Rudraksh Tower.pdf21 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Dated 30 Jun 2024 Rudraksh Tower.pdf21 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Dated 30 Sept 2024 Rudraksh Tower.pdf21 Dec 2024
OtherFile: Pert Schedule Dated 30 March 2026 Rudraksh Tower.pdf21 Dec 2024
OtherFile: Format C Consent letter of Customer.pdf21 Dec 2024
OtherFile: Shivshakti Allotment (1)_compressed.pdf21 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A Year Ending 2022-23 (1).pdf21 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Year Ending 2024 Rudraksh Tower.pdf21 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Dated 30 Sept 2024 Rudraksh Tower.pdf21 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Dated 30 Jun 2024 Rudraksh Tower.pdf21 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Dated 30 Sept 2024 Rudraksh Tower.pdf21 Dec 2024
OtherFile: Pert Schedule Dated 30 March 2026 Rudraksh Tower.pdf21 Dec 2024
OtherFile: Format C Consent letter of Customer.pdf21 Dec 2024
OtherFile: Shivshakti Allotment (1)_compressed.pdf21 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A Year Ending 2022-23 (1).pdf21 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Year Ending 2024 Rudraksh Tower.pdf21 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Dated 31 Dec 2023 Rudraksh Tower.pdf19 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Dated 30 Sept 2024 Rudraksh Tower (1).pdf19 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Dated 30 Jun 2024 Rudraksh Tower (1).pdf19 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Dated 31 Mar 2024 Rudraksh Tower.pdf19 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Dated 30 Sept 2023 Rudraksh Tower.pdf19 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Dated 31 Dec 2022 Rudraksh Tower.pdf19 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Dated 30 Jun 2023 Rudraksh Tower.pdf19 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Dated 31 Dec 2022 Rudraksh Tower.pdf19 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Dated 30 Sept 2022 Rudraksh tower.pdf19 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Dated 30 Jun 2022 Rudraksh Tower.pdf19 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Dated 30 Mar 2022 Rudraksh Tower.pdf19 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Dated 31 Mar 2023 Rudraksh Tower.pdf19 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Dated 31 Dec 2023 Rudraksh Tower.pdf19 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Dated 30 Sept 2024 Rudraksh Tower (1).pdf19 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Dated 30 Jun 2024 Rudraksh Tower (1).pdf19 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Dated 31 Mar 2024 Rudraksh Tower.pdf19 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Dated 30 Sept 2023 Rudraksh Tower.pdf19 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Dated 31 Dec 2022 Rudraksh Tower.pdf19 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Dated 30 Jun 2023 Rudraksh Tower.pdf19 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Dated 31 Dec 2022 Rudraksh Tower.pdf19 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Dated 30 Sept 2022 Rudraksh tower.pdf19 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Dated 30 Jun 2022 Rudraksh Tower.pdf19 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Dated 30 Mar 2022 Rudraksh Tower.pdf19 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Dated 31 Mar 2023 Rudraksh Tower.pdf19 Dec 2024
Declaration in FORM BFile: Form B Dated 31st March 2026.pdf17 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Dated 30 Sept 2023 Rudraksh Tower.pdf17 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Dated 30 Mar 2024 Rudraksh Tower.pdf17 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Dated 30 Dec 2023.pdf17 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Dated 30 Jun 2023 Rudraksh Tower.pdf17 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Dated 30 Mar 2023 Rudraksh Tower.pdf17 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Dated 30 Dec 2022.pdf17 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Dated 30 Sept 2022 Rudraksh Tower.pdf17 Dec 2024

How this compares with Thane

31%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 30 months
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep RUDRAKSH TOWER on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near VILLAGE SHIVAJI NAGAR7,600+ in Thane

2 kmRUDRAKSH TOWERCompleted 50Lapsed / revoked 38Other 64Dot size: filed unitsN

Filed coordinates, straight-line distance. 152 registered projects within 2 km.

Builder: SHIVSHAKTI BUILDERS AND DEVELOPERS

SHIVSHAKTI BUILDERS AND DEVELOPERS has 3 registrations on MahaRERA, including PAWAR PARADISE and RUDRAKSH TOWER. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if RUDRAKSH TOWER is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of RUDRAKSH TOWER?

The registered promoter entity is SHIVSHAKTI BUILDERS AND DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in RUDRAKSH TOWER?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for RUDRAKSH TOWER?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at RUDRAKSH TOWER?

The professionals named in the filing: Architect: SHIRISH GAJANAN NACHANE; Engineer: RAJESH THAKARE & ASSOCIATES; Chartered Accountant: ABHIRUCHI V PARANJAPE & CO; Chartered Accountant: DHANDEKAR METHWANI & CO; Chartered Accountant: HARIYANI & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in RUDRAKSH TOWER?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About RUDRAKSH TOWER. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save RUDRAKSH TOWER to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.