Home / Browse projects / Pune, Maharashtra / RUDRA DESIRE
RUDRA DESIRE
By RADHAKRUSHANA MADHUKAR KALE
RG-MH-14695 · RERA P52100023077 · Last updated on MahaRERA portal: 11 May 2023
Source: official MahaRERA filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
RUDRA DESIRE is a Residential / Group Housing project by RADHAKRUSHANA MADHUKAR KALE in Pune, Maharashtra, registered with MahaRERA as P52100023077 on 29 Nov 2019. The registration is recorded completed; possession was promised by 30 Mar 2023.
At a glance
Project
- NameRUDRA DESIRE
- TypeResidential / Group Housing
- Location
- JABHALI ROAD
- AMBEKAR MALA BABURAO NAGAR
- Shirur Gramin
- Shirur
- Pune
- 412210
- Pincode412210
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100023077
- ReraGenie IDRG-MH-14695
Builder
- NameRADHAKRUSHANA MADHUKAR KALE
- Entity typeIndividual
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on29 Nov 2019
- Promised completion30 Mar 2023
- Revised completionNone
- Buildings1 building record
- Documents filed43 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| RUDRA DESIRE | NA | 7 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 11 May 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
7 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 0%.
RUDRA DESIRE: 64% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 11 May 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed3
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership4
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| VIKAS BAPURAO AMBEKAR | Shirur Gramin | Pune |
| DEEPAK BAPURAO AMBEKAR | Shirur Gramin | Pune |
| VILAS BAPURAO AMBEKAR | Shirur Gramin | Pune |
| KIRAN BAPURAO AMBEKAR | Shirur Gramin | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | RAHUL LONDHE |
| Engineer | AJIT DEVRAM BORHADE |
| Chartered Accountant | SUNIL YELLOL |
| Partner | Role in project |
|---|---|
| RADHAKRUSHANA MADHUKAR KALE | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 3 Nov 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 3 Nov 2019 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 3 Nov 2019 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 3 Nov 2019Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 27 Aug 2022
Documents filed43
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: form 5 ca annual report.pdf | 11 May 2023 |
| Architect’s Certificate on Completion of Project (Form 4)File: rudra desire form 4_compressed.pdf | 8 Apr 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineer form 2 rera up to jun 2022_compressed.pdf | 27 Aug 2022 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: pmrda COMPLETION (1)_compressed.pdf | 27 Aug 2022 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: rudra desire sociaty_rejisration (1)_compressed.pdf | 27 Aug 2022 |
| Status of ConveyanceFile: CONVANCE DEED-1-20 (1).pdf | 27 Aug 2022 |
| Status of ConveyanceFile: CONVANCE DEED-21-40 (1).pdf | 27 Aug 2022 |
| Status of ConveyanceFile: CONVANCE DEED-41-60 (1).pdf | 27 Aug 2022 |
| Status of ConveyanceFile: CONVANCE DEED-61-74 (1).pdf | 27 Aug 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: ENGINEER FORM 2 rera up to jun 2022 (2)_compressed.pdf | 26 Aug 2022 |
| Disclosure of sold/ booked inventoryFile: discolsure sold booked up to jun 2022.pdf | 26 Aug 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ca form 3 up to jun 2022_compressed.pdf | 26 Aug 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: rudra desire rera engineer form 2 up to Dec 2021.pdf | 8 Mar 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: rudra desire rera engineer 2a up to Dec 2021.pdf | 8 Mar 2022 |
| Disclosure of sold/ booked inventoryFile: rudra desire rera sold un soldup to Dec 2021.pdf | 8 Mar 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: rudra desire rera CA up to Dec 2021.pdf | 8 Mar 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERTIFICATE FORM 2_compressed.pdf | 11 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A (2)_compressed.pdf | 11 Oct 2021 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf | 8 Oct 2021 |
| Disclosure of sold/ booked inventoryFile: Inventory sold unsold.pdf | 8 Oct 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate.pdf | 8 Oct 2021 |
| Declaration about Commencement CertificateFile: rudra desire decleration certificate.pdf | 17 Aug 2021 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: rudra desire architect certificate.pdf | 10 Aug 2021 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: rudra desire engineer form 2_compressed.pdf | 10 Aug 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: rudra desire engineer form 2A_compressed.pdf | 10 Aug 2021 |
| Disclosure of sold/ booked inventoryFile: rudra desire sold unsold inventry (1).pdf | 10 Aug 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: rudra desire ca form 3.pdf | 10 Aug 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: rudra desire form 5.pdf | 10 Aug 2021 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Form 1.pdf | 9 Dec 2020 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Form 2.pdf | 9 Dec 2020 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A.pdf | 9 Dec 2020 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Form 3.pdf | 9 Dec 2020 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: CA Form 5.pdf | 9 Dec 2020 |
| Layout approvalFile: LAY OUT.pdf | 3 Nov 2019 |
| Building plan approvalFile: PLAN.pdf | 3 Nov 2019 |
| Copy of the legal title reportFile: title report.pdf | 3 Nov 2019 |
| Details of encumbrancesFile: ENCUMBRANCES.pdf | 3 Nov 2019 |
| Copy of Layout Approval (in case of layout)File: LAY OUT.pdf | 3 Nov 2019 |
| Building Plan Approval / NA Order for plotted developmentFile: PLAN.pdf | 3 Nov 2019 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificates.pdf | 3 Nov 2019 |
| Declaration in FORM BFile: FROM NO B.pdf | 3 Nov 2019 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate.pdf | 3 Nov 2019 |
| Proforma of Allotment letterFile: DRAFT.pdf | 3 Nov 2019 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 43 filed documents as one ZIP, foldered, with a manifest
Keep RUDRA DESIRE on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near AMBEKAR MALA BABURAO NAGAR13,700+ in Pune
Filed coordinates, straight-line distance. 39 registered projects within 2 km.
SUNDAR SHRUSHTI
RAMLING LAND DEVELOPERS LLP
Rayat Residency
SOHAM CONSTRUCTIONS AND DEVELOPERS
NAKSHATRA AROMA
NITU ASSOCIATES
NAKSHATRA SAFFRON
NAMRATA DEVELOPERS
Rayat Regency
SOHAM CONSTRUCTIONS AND DEVELOPERS
KEWAL KUNJ
BORA EXCELLENCY DEVELOPERS UNIT 1
Builder: RADHAKRUSHANA MADHUKAR KALE
RADHAKRUSHANA MADHUKAR KALE has 1 registration on MahaRERA, including RUDRA DESIRE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if RUDRA DESIRE is delayed beyond 30 Mar 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of RUDRA DESIRE?
The registered promoter entity is RADHAKRUSHANA MADHUKAR KALE, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in RUDRA DESIRE?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for RUDRA DESIRE?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at RUDRA DESIRE?
The professionals named in the filing: Architect: RAHUL LONDHE; Engineer: AJIT DEVRAM BORHADE; Chartered Accountant: SUNIL YELLOL. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in RUDRA DESIRE?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback