Home / Browse projects / Aurangabad, Maharashtra / ROYALS DHRUVIKA APARTMENT

Registration lapsed No litigation declared Residential / Group Housing project

ROYALS DHRUVIKA APARTMENT

By MOHAMMED ALTAF AHMED

RG-MH-14743 · RERA P51500048743 · Last updated on MahaRERA portal: 28 Jul 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 4 earlier projects delivered on promise

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Aurangabad registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
9 of 11Construction stages donefurthest along: Podiums (if any), 0%
10 of 10Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 52 documents Report an error

ROYALS DHRUVIKA APARTMENT is a Residential / Group Housing project by MOHAMMED ALTAF AHMED in Aurangabad, Maharashtra, registered with MahaRERA as P51500048743 on 17 Jan 2023. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 12 months from the original filing. 0 of the 10 units on this registration are recorded sold or booked, and 9 of 11 construction stages are filed complete.

At a glance

Project

  • NameROYALS DHRUVIKA APARTMENT
  • TypeResidential / Group Housing
  • Location
    • PLOT NO 04
    • CTS NO 20741/44
    • NANDANVAN COLONY
    • Aurangabad (M Corp.)
    • Aurangabad
    • 431001
  • Pincode431001
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51500048743
  • ReraGenie IDRG-MH-14743

Builder

  • NameMOHAMMED ALTAF AHMED
  • Entity typeIndividual
  • Declared earlier projects5 →

Key dates

10 months past promisethis monthRegisteredJan 2023First promiseDec 2024Revised toDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on17 Jan 2023
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 31 Dec 2024)
  • Buildings1 building record
  • Documents filed52 files

Current status

0%0 of 10 units booked

Figures as on 28 Jul 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ROYALS DHRUVIKA APARTMENTNA5510010

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 28 Jul 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

ROYALS DHRUVIKA APARTMENT: 82% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 28 Jul 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyNoNot applicable
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed6

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots6
Open Space6

Land and ownership3

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area282 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on9 Jun 2026
LandownerVillageDistrict
MOHAMMED ALTAF AHMEDAurangabad (M Corp.)Aurangabad
SURAJ BABASAHEB TRUBHUWANAurangabad (M Corp.)Aurangabad
SHUBHANGI SURAJ TRIBHUWANAurangabad (M Corp.)Aurangabad

Approvals and building plan

Sanctioning authorityAURANGABAD MUNICIPAL CORPORATION AURANGABAD
Permissible FSI783.4
Proposed, not sanctioned783 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchAURANGABAD MAIN BRANCH JUNA BAZAAR AURANGABAD

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectTADEEB SIDDIQUI
ArchitectTADEEBUDDIN TAUFIQUDDIN SIDDIQUE
EngineerMUJHAED HASHMI
Chartered AccountantWASIM AMIN BAIG AND ASSOCIATES
Chartered AccountantANWAR HUSSAIN
PartnerRole in project
MOHAMMED ALTAF AHMED-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51500027877Dec 2024 → Dec 2025

Reason as filed by the promoterEXTENSION TO UPLOAD COMPLETION

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Nov 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 23 Nov 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 23 Nov 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 23 Nov 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 7 Nov 2024

Documents filed52

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: QPR4 ENG CERT PLOT NO 4.pdf28 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: QPR 4 pLOT nO 4.pdf26 Jul 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: QPR 2 ENG CERT FOR PLOT NO 4.pdf26 Jul 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: QPR3 ENG CERT FOR PLOT NO 4.pdf26 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: QPR 1 4.pdf19 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: QPR 2 4.pdf19 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: QPR 3 4.pdf19 Jul 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2023 QPR 1 ENG CERTIFICATE.pdf19 Jul 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer 17-06-25.pdf7 Jul 2025
Disclosure of sold/ booked inventoryFile: DIS 17-07-23.pdf28 Jun 2025
Disclosure of sold/ booked inventoryFile: DIS 17-01-24.pdf28 Jun 2025
Disclosure of sold/ booked inventoryFile: DIS 17-06-24.pdf28 Jun 2025
Disclosure of sold/ booked inventoryFile: DISCLOSURE 17-07-2023.pdf26 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form1 pl 4.pdf12 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 .pdf12 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 plot 4.pdf12 May 2025
Disclosure of sold/ booked inventoryFile: sold plot no 4.pdf12 May 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: form 2a plot 4.pdf12 May 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2024-25)File: form5.pdf12 May 2025
Architect’s Certificate on Completion of Project (Form 4)File: form 4 plot no 4.pdf9 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: quality assurance plot no 4.pdf9 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate.pdf7 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf7 Nov 2024
Status of Formation of Legal Entity (Society/Co Op etc.)File: society p no 4.pdf7 Nov 2024
Status of ConveyanceFile: conveyance p no 4.pdf7 Nov 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: plot no 4 oc.pdf7 Nov 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: scan 2mb.pdf7 Nov 2024
Foreclosure of the ProjectFile: foreclosure p no 4.pdf7 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: form 5 22-23.pdf7 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form 5 23-24.pdf7 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form 5 24-25.pdf7 Nov 2024
Declaration in FORM BFile: FORM B NEW.pdf4 Jan 2023
CERSAI detailsFile: CERSAI_Search_Report_200256772771_For_Asset_Based_Search_04_01_2023_19_58_22_151.pdf4 Jan 2023
CERSAI detailsFile: declaration cersai.pdf4 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ca new plot no 4.pdf4 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: disclosure.pdf4 Jan 2023
Copy of the legal title reportFile: SEARCH REPORT PLOT NO 4.pdf27 Nov 2022
Proforma of Allotment letterFile: plot no 04 allotment letter.pdf24 Nov 2022
Proforma of Agreement for saleFile: PLOT NO 04 AGREEMENT TO SALE DRAFT.pdf24 Nov 2022
Layout approvalFile: TOCH.pdf23 Nov 2022
Building plan approvalFile: building plan.pdf23 Nov 2022
PAN CardFile: PAN.pdf23 Nov 2022
Details of encumbrances concerned to FinanceFile: ENCUMBRANCES TO LEGAL.pdf23 Nov 2022
Details of encumbrances concerned to LegalFile: ENCUMBRANCES TO LEGAL.pdf23 Nov 2022
Copy of Layout Approval (in case of layout)File: TOCH.pdf23 Nov 2022
Building Plan Approval / NA Order for plotted developmentFile: building plan.pdf23 Nov 2022
Commencement Certificates / NA Order for plotted developmentFile: CC CERTIFICATE.pdf23 Nov 2022
Declaration about Commencement CertificateFile: CC DECLARATION.pdf23 Nov 2022
CERSAI detailsFile: LOAN STATEMENT.pdf23 Nov 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: BANK DECLARATION.pdf23 Nov 2022
Deviation Report with respect to Allotment letterFile: to allotment letter devaition.pdf23 Nov 2022
Deviation Report with respect to model copy of AgreementFile: AFS DEVAITION.pdf23 Nov 2022

Promoter's earlier projects4

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

4 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
ROYAL ANMOL APARTMENTNANDANVAN COLONY AURANGABAD8CompletedFeb 2023Mar 2022
ROYAL ENCLAVENANDANVAN COLONY AURANGABAD10CompletedJun 2022Jan 2022
ASHWIN RESIDENCYNANDANVAN COLONY18CompletedMay 2022Jan 2022
ROYAL AVENUECTS NO 237 NANDANVAN COLONY AURANGABAD12CompletedMar 2020Dec 2019

How this compares with Aurangabad

0%of this project is bookeddistrict median 6%
14%of Aurangabad projects moved their completion datethis one moved by 12 months
32%of Aurangabad registrations have lapsed or been cancelledthis one is among them

Computed across the 1,400+ Aurangabad projects on ReraGenie, from their own filings.

Keep ROYALS DHRUVIKA APARTMENT on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NANDANVAN COLONY1,400+ in Aurangabad

2 kmROYALS DHRUVIKA APARTMENCompleted 2Lapsed / revoked 5Other 8Dot size: filed unitsN

Filed coordinates, straight-line distance. 15 registered projects within 2 km.

Builder: MOHAMMED ALTAF AHMED

MOHAMMED ALTAF AHMED has 1 registration on MahaRERA, including ROYALS DHRUVIKA APARTMENT. Its filings disclose 5 earlier MahaRERA projects: declares 5 of 5 past projects completed on time. Read the full track record. See more projects on the Aurangabad district page.

Frequently asked questions

What does it mean that ROYALS DHRUVIKA APARTMENT shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if ROYALS DHRUVIKA APARTMENT is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ROYALS DHRUVIKA APARTMENT?

The registered promoter entity is MOHAMMED ALTAF AHMED, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ROYALS DHRUVIKA APARTMENT?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ROYALS DHRUVIKA APARTMENT?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ROYALS DHRUVIKA APARTMENT?

The professionals named in the filing: Architect: TADEEB SIDDIQUI; Architect: TADEEBUDDIN TAUFIQUDDIN SIDDIQUE; Engineer: MUJHAED HASHMI; Chartered Accountant: WASIM AMIN BAIG AND ASSOCIATES; Chartered Accountant: ANWAR HUSSAIN. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ROYALS DHRUVIKA APARTMENT?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ROYALS DHRUVIKA APARTMENT. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ROYALS DHRUVIKA APARTMENT to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.