Home / Browse projects / Mumbai Suburban, Maharashtra / ROYALE

Registered No litigation declared Others project

ROYALE

By KHOKER SYNERGY DEVELOPERS

RG-MH-24656 · RERA P51800006143 · Last updated on MahaRERA portal: 3 Jun 2026

Source: official MahaRERA filing

Red flags

  • Possession 1 months past the filed date
  • 2 complaints at MahaRERA
  • Completion date moved by 38 months
  • 4 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Sep 2026Possession promised1 month past this date
5 of 11Construction stages donefurthest along: Staircases, 95%
36 of 70Units unsoldnot recorded sold or booked
2Complaints at MahaRERAon this registration
Jump to the 114 documents Report an error

ROYALE is a Others project by KHOKER SYNERGY DEVELOPERS in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800006143 on 14 Aug 2017. Possession was promised by 30 Sep 2026 and is now 1 months past that date. The completion date has moved by 38 months from the original filing. 34 of the 70 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete. 2 complaints are on record with the regulator.

At a glance

Project

  • NameROYALE
  • TypeOthers
  • Location
    • RTo lane
    • FourBungalows
    • Andheri
    • Mumbai Suburban
    • 400053
  • Pincode400053
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800006143
  • ReraGenie IDRG-MH-24656

Builder

  • NameKHOKER SYNERGY DEVELOPERS
  • Entity typePartnership
  • PartnerSarfraz Abdulaziz

Key dates

1 months past promisethis monthRegisteredAug 2017First promiseJul 2023Revised toSep 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on14 Aug 2017
  • Promised completion30 Sep 2026
  • Revised completionRevised to 30 Sep 2026 (originally 31 Jul 2023)
  • Buildings1 building record
  • Documents filed114 files

Current status

49%34 of 70 units booked
77.2%Work done, per cost certificate

Figures as on 3 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ROYALENA232069170

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 3 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 95%.

ROYALE: 82% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)75%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises85%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.65%

Progress on shared amenities15

As on 3 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes80%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed59

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots59
Closed/Covered33
Open Space26

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,260 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on5 Jan 2026

Approvals and building plan

Sanctioning authorityBMC
Permissible FSI4052.79
Proposed, not sanctioned3,265 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPALI NAKA, BANDRA WEST
Estimated costRs 29.20 cr
Cost incurredRs 22.53 cr
Work done77.15%
BuildingWingEstimatedIncurred
ROYALENARs 14.60 crRs 11.26 cr
-NARs 14.60 crRs 11.26 cr

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectS.P. KARMARKAR & ASSOCIATE
EngineerFRAMES STRUCTURAL ENGINEERS
Chartered AccountantNEHALI & CO
PartnerRole in project
KHOKER SYNERGY DEVELOPERS-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800013993Jul 2023 → Jul 2024

Reason as filed by the promoterdue to covid 19 and after effects of nationwide lockdown, increases in prices of raw material, labour etc, the project was unable to get completed in time therefore we would request you to please grant us an extension for 12 months of upto 30/7/2024

EXT51800023000Jul 2023 → Mar 2025

Reason as filed by the promoterDue to shortage of laboour and material not able to complete project please grant us extension till 31/03/2025

EXT51800028001Jul 2023 → Dec 2025

Reason as filed by the promoterThe structural work is complete amd the finishing works are going on Due to some technical difficulties in btaining TREE NOC for tree cutting and the excavation works and other factors the work could not be completed on time and hence an extension of the sam is required for another 09 (nine) months Request you to kindly consider the above and approve

EA24022619977Jul 2023 → Sep 2026

Reason as filed by the promoterThis is to inform you that our project name ROYALE located at CTS No. 825/1/20 of Village Ambivali, Four Bungalows, Andheri (W), Mumbai - 400054 Bearing Rera No P51800006143 is due to lapse by 31/12/2025.We request you to kindly give extension till 30/09/2026.The structural work is complete and the finishing works are going on. There has been a technical and construction difficulty in installation of passenger lifts and Car lifts, since the balance Podium is not yet casted at the site due to which the work could not be completed on time and hence an extension of the same is required for anothe

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC006000000161348Mr. Tanveer Iqbal ZamaneKhoker Synergy Developers25/10/2019
CC006000000161350Javed Alimiya ZamaneKhoker Synergy Developers25/10/2019

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 4 May 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed114

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 114 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM_1_SIGNED.pdf3 Jun 2026
Withdrawal Update Form 2File: Form_2.pdf3 Jun 2026
Withdrawal Update Form 3File: FORM 3.pdf3 Jun 2026
Withdrawal Update Form 1File: FORM 1 signed 31 12 25.pdf23 Feb 2026
Withdrawal Update Form 2File: form 2 SIGNED 31 12 25.pdf23 Feb 2026
Withdrawal Update Form 3File: CA CERTIFICATE DEC 25.pdf23 Feb 2026
Withdrawal Update Form 1File: form 1.pdf5 Feb 2026
Withdrawal Update Form 2File: Form 2 30 09 25 2 (1)_11zon.pdf5 Feb 2026
Withdrawal Update Form 3File: CA Certificate Sept 25.pdf5 Feb 2026
Withdrawal Update Form 1File: form 1.pdf13 Jan 2026
Withdrawal Update Form 2File: form2 final.pdf13 Jan 2026
Withdrawal Update Form 3File: CA_Certificate_june_25.pdf13 Jan 2026
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM_2A-FY_22-23.pdf26 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM_2A-FY_23-24 (2).pdf26 Mar 2025
Certificates of CA (Form 3)File: Resigned_CA_Certificate_-_Khoker_Synergy_dec_24.pdf24 Mar 2025
Declaration in FORM BFile: Form B.pdf22 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf22 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf22 Mar 2025
Disclosure of sold/ booked inventoryFile: inventory_disclosure revised.pdf22 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: CA form 5 23-24.pdf12 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect_form_1.pdf7 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect_form_1 (2).pdf7 Feb 2025
Certificates of CA (Form 3)File: Signed_CA_Certificate_-_Khoker_Synergy_sep_24__1_.pdf7 Feb 2025
Certificates of CA (Form 3)File: Signed_CA_Certificate_-_Khoker_Synergy_sep_24__1_.pdf7 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: form 5 22-23.pdf7 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: form 2A 23-24.pdf7 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1.pdf31 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf31 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: form 2A.pdf31 Jul 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank_account_delcaration.pdf29 Jun 2024
Disclosure of sold/ booked inventoryFile: inventory_disclosure.pdf28 Jun 2024
Certificates of CA (Form 3)File: Signed_CA_Certificate_-_mar_24_revised.pdf28 Jun 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure_A__revised.pdf28 Jun 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1.pdf27 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf24 May 2024
Declaration in FORM BFile: FROM_B.pdf17 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer form 2.pdf17 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A 23-24.pdf17 May 2024
Disclosure of sold/ booked inventoryFile: Diclosure_of_inventory.pdf17 May 2024
Certificates of CA (Form 3)File: CA Form 3.pdf17 May 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: CA form 5 22-23.pdf17 May 2024
Proforma of Agreement for saleFile: DRAFT AGREEMENT FOR SALE.pdf5 Oct 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer form 2.pdf22 May 2023
Certificates of CA (Form 3)File: FORM_3_CA.pdf22 May 2023
Commencement Certificates / NA Order for plotted developmentFile: 14 FLOORS.pdf4 May 2023
Declaration about Commencement CertificateFile: cc covering letter.pdf2 Mar 2023
Disclosure of sold/ booked inventoryFile: disclosure of inventory.pdf2 Mar 2023
CERSAI detailsFile: cersai.pdf2 Mar 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf8 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf8 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A.pdf8 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: form_5_SIGNED.pdf8 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer form 2.pdf27 Jul 2022
Certificates of CA (Form 3)File: CA FORM 3.pdf25 Jul 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect_form_1.pdf20 Jul 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect_form_1.pdf19 Jul 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT FORM 1.pdf25 Apr 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER FORM 2.pdf25 Apr 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: ENGINEER FORM 2A.pdf25 Apr 2022
Certificates of CA (Form 3)File: CA FORM 3.pdf25 Apr 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: CA FORM 5 20-21.pdf11 Feb 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf24 Jan 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1_compressed.pdf18 Oct 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2_compressed.pdf18 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: form 2a.pdf18 Oct 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect form 1.pdf11 Aug 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 MARCH.pdf11 Aug 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 JUNE.pdf11 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A MARCH.pdf11 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A JUNE.pdf11 Aug 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Certificate 30 form 2.pdf16 Jun 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Certificate 31 form 2.pdf16 Jun 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Certificate form 2.pdf16 Jun 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Certificate 30 form 2A.pdf16 Jun 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Certificate 31 form 2A.pdf16 Jun 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Certificate form 2A.pdf16 Jun 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5.pdf8 Mar 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 2A KHOKERS.pdf13 Aug 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT.pdf10 Aug 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG.pdf10 Aug 2020

How this compares with Mumbai Suburban

49%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 38 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ROYALE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near FourBungalows6,700+ in Mumbai Suburban

2 kmROYALECompleted 102Lapsed / revoked 62Other 74Dot size: filed unitsN

Filed coordinates, straight-line distance. 238 registered projects within 2 km.

Builder: KHOKER SYNERGY DEVELOPERS

KHOKER SYNERGY DEVELOPERS has 1 registration on MahaRERA, including ROYALE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if ROYALE is delayed beyond 30 Sep 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ROYALE?

The registered promoter entity is KHOKER SYNERGY DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ROYALE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against ROYALE?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for ROYALE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ROYALE?

The professionals named in the filing: Architect: S.P. KARMARKAR & ASSOCIATE; Engineer: FRAMES STRUCTURAL ENGINEERS; Chartered Accountant: NEHALI & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ROYALE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ROYALE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ROYALE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.