Home / Browse projects / Pune, Maharashtra / ROYAL SUBLIME
ROYAL SUBLIME
By ALIASAGAR ISMAIL ICECREAMWALA
RG-MH-75181 · RERA P52100019530 · Last updated on MahaRERA portal: 4 Dec 2024
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 33 months past the filed date
- 1 complaint at MahaRERA
Clear
- No litigation declared
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
ROYAL SUBLIME is a Residential / Group Housing project by ALIASAGAR ISMAIL ICECREAMWALA in Pune, Maharashtra, registered with MahaRERA as P52100019530 on 8 Feb 2019. Possession was promised by 30 Jan 2024 and is now 33 months past that date. 1 complaint is on record with the regulator.
At a glance
Project
- NameROYAL SUBLIME
- TypeResidential / Group Housing
- Location
- DP ROAD
- KONDHWA KHURD
- Haveli
- Pune
- 411048
- Pincode411048
- RERA no.P52100019530
- ReraGenie IDRG-MH-75181
Builder
- NameALIASAGAR ISMAIL ICECREAMWALA
- Entity typeIndividual
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on8 Feb 2019
- Promised completion30 Jan 2024
- Revised completionNone
- Buildings2 building records
- Documents filed51 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Building C - A WING - Tulip | NA | 15 | 0 | 0 | 0 | 0 |
| Building C -B WING - Lilly | NA | 15 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 4 Dec 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
16 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Stilt Floor, at 13%.
Building C - A WING - Tulip91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building C -B WING - Lilly57%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 13% |
| Slabs of Super Structure | 13% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 4 Dec 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed48
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| Building C - A WING - Tulip | 24 | 24 |
| Building C -B WING - Lilly | 24 | 24 |
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| M/S. LIVING CONCEPT ENTERPRISES | Mumbai City | Mumbai City |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | AFROZ JAFER SAYYED |
| Engineer | SAMEER YUNUS KHAN |
| Chartered Accountant | YOGESH N SHAH |
| Partner | Role in project |
|---|---|
| ALIASAGAR ISMAIL ICECREAMWALA | - |
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000340898 | Muddsar Nizamphasha Jahangir | Aliasgar ismail icecreamwala | 09/05/2024 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 29 Jan 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 29 Jan 2019 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 29 Jan 2019 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 31 Jan 2019Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 25 Jul 2024
Documents filed51
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect’s Certificate on Completion of Project (Form 4)File: f-4.pdf | 4 Dec 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: f-4.pdf | 4 Dec 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: oc -B.pdf | 25 Jul 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: oc -B.pdf | 25 Jul 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC- A.pdf | 25 Jul 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: ocak (1).pdf | 10 Apr 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: form 5 fy 19-20.pdf | 24 Feb 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Final.pdf | 7 Oct 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf | 7 Oct 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 arc.pdf | 7 Oct 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 7 Oct 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 7 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A.pdf | 7 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2.pdf | 7 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A.pdf | 7 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A.pdf | 7 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: form 2A 31 aug 21.pdf | 7 Oct 2021 |
| Certificates of CA (Form 3)File: Form 3 Final.pdf | 7 Oct 2021 |
| Certificates of CA (Form 3)File: FOrm 3 Final.pdf | 7 Oct 2021 |
| Certificates of CA (Form 3)File: Form 3 Final.pdf | 7 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A.pdf | 20 Mar 2020 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 2.pdf | 20 Mar 2020 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 3.pdf | 20 Mar 2020 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 November 3 2019.pdf | 22 Jan 2020 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Novmber 3 2019.pdf | 22 Jan 2020 |
| Certificates of CA (Form 3)File: Form 3 November 3 2019.pdf | 22 Jan 2020 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf | 30 Oct 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Royal.pdf | 30 Oct 2019 |
| Certificates of CA (Form 3)File: Form 3 Royal.pdf | 30 Oct 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Final.pdf | 11 Jul 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2_1st Quarter.pdf | 11 Jul 2019 |
| Certificates of CA (Form 3)File: Form 3_Final_1st Quarter.pdf | 11 Jul 2019 |
| Details of encumbrancesFile: Search Report.pdf | 31 Jan 2019 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf | 31 Jan 2019 |
| Declaration in FORM BFile: Form B_Living Concept Enterprises.pdf | 31 Jan 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1_Architect Certificate.pdf | 31 Jan 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_Engineers Certificate.pdf | 31 Jan 2019 |
| OtherFile: Development Agreement_Final.pdf | 31 Jan 2019 |
| Building plan approvalFile: Sanctioned Plan_1.pdf | 29 Jan 2019 |
| Layout approvalFile: Layout Plan_1_1.pdf | 29 Jan 2019 |
| Layout approvalFile: Floor Plan_2_1.pdf | 29 Jan 2019 |
| Layout approvalFile: Floor Plan_3_1.pdf | 29 Jan 2019 |
| PAN CardFile: pan card Scan.pdf | 29 Jan 2019 |
| Copy of the legal title reportFile: Search Report.pdf | 29 Jan 2019 |
| Copy of Layout Approval (in case of layout)File: Layout Plan_1_1.pdf | 29 Jan 2019 |
| Copy of Layout Approval (in case of layout)File: Floor Plan_2_1.pdf | 29 Jan 2019 |
| Copy of Layout Approval (in case of layout)File: Floor Plan_3_1.pdf | 29 Jan 2019 |
| Building Plan Approval (IOD)File: Sanctioned Plan_1.pdf | 29 Jan 2019 |
| Declaration in FORM BFile: FORM B - Affidavit - Declaration.pdf | 29 Jan 2019 |
| Certificates of CA (Form 3)File: Form 3_CA Certificate-ilovepdf-compressed.pdf | 29 Jan 2019 |
| Proforma of Allotment letterFile: Agreement for sale final (1) (1) (3).pdf | 29 Jan 2019 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- All 51 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep ROYAL SUBLIME on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near KONDHWA KHURD13,700+ in Pune
Dwarikadham
Yashodhan Affordable Landmark LLP
UNITAS FASHION CENTER
UNITATIS DEVELOPMENTS PVT. LTD
Millennium Park
Xrbia Epoch Creations LLP
BABAR CLASSIC VISTA WING E, F, G
Classic Properties
JITO NAGAR
JAIN ASHAPURI DEVELOPER UNIT II
Wellwisher West Views
Bhansali Infrastructure LLP
Builder: ALIASAGAR ISMAIL ICECREAMWALA
ALIASAGAR ISMAIL ICECREAMWALA has 1 registration on MahaRERA, including ROYAL SUBLIME. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that ROYAL SUBLIME shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if ROYAL SUBLIME is delayed beyond 30 Jan 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of ROYAL SUBLIME?
The registered promoter entity is ALIASAGAR ISMAIL ICECREAMWALA, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in ROYAL SUBLIME?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against ROYAL SUBLIME?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for ROYAL SUBLIME?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at ROYAL SUBLIME?
The professionals named in the filing: Architect: AFROZ JAFER SAYYED; Engineer: SAMEER YUNUS KHAN; Chartered Accountant: YOGESH N SHAH. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in ROYAL SUBLIME?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback