Home / Browse projects / Pune, Maharashtra / Royal Exotica Phase 2
Royal Exotica Phase 2
RG-MH-44033 · RERA P52100047177 · Last updated on MahaRERA portal: 20 Apr 2024
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 19 months past the filed date
- 2 complaints at MahaRERA
Clear
- No litigation declared
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Royal Exotica Phase 2 is a Residential / Group Housing project by SVG Builders LLP in Pune, Maharashtra, registered with MahaRERA as P52100047177 on 10 Oct 2022. Possession was promised by 31 Mar 2025 and is now 19 months past that date. 2 complaints are on record with the regulator.
At a glance
Project
- NameRoyal Exotica Phase 2
- TypeResidential / Group Housing
- Location
- opp talab
- Kondhwa
- kondhwa BK
- Haveli
- Pune
- 411048
- Pincode411048
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100047177
- ReraGenie IDRG-MH-44033
Builder
- NameSVG Builders LLP
- Entity typePartnership
- PartnersPankaj Vohra, Rashmikant Jayantilal Gandhi, Suresh Indulal Shah
- Other registrations1 more →
- Completed1 of 2
- No longer live1 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on10 Oct 2022
- Promised completion31 Mar 2025
- Revised completionNone
- Buildings2 building records
- Documents filed64 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| WING 19 | NA | 18 | 0 | 0 | 0 | 0 |
| WING 20 | NA | 18 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 20 Apr 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
22 of 22 construction stages are filed complete across 2 buildings.
WING 19100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
WING 20100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 20 Apr 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 95% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 95% |
| Storm Water Drains | Yes | 95% |
| Landscaping & Tree Planting | Yes | 95% |
| Street Lighting | Yes | 95% |
| Community Buildings | Yes | 95% |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 95% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Parking filed2
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| WING 19 | 1 | 1 |
| WING 20 | 1 | 1 |
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| M/S Kunal Housing | Pune (M Corp.) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | CUBIX Architects Associates Imran Shaikh |
| Engineer | Planedge Consultants Pvt Ltd |
| Chartered Accountant | Muttha Lahoti and Associates |
| Partner | Role in project |
|---|---|
| SVG Builders LLP | - |
Litigation declared1
| Case | Court | Status |
|---|---|---|
| 1780/2021/2021 | Civil Court Senior Division Pune | Matter kept for plaintiff to take steps |
Complaints filed with MahaRERA2
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12504300 | SUHEL AHMED KHALEEL AHMED HAFIZ | SVG Builders LLP | 05/12/2025 |
| CC12504303 | SUHEL AHMED KHALEEL AHMED HAFIZ | SVG Builders LLP | 05/12/2025 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 30 Jun 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 24 Aug 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 5 Jul 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 30 Jun 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 20 Apr 2024
Documents filed64
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Complepion Certificate ROYAL EXOTICA 19 , 20 AND Club House.PDF | 20 Apr 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: PMC MAIL TO RERA.pdf | 20 Apr 2024 |
| Other - TechnicalFile: AltaScanner_10_27_2023.pdf | 29 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Phase 2 form 1 SVG.pdf | 20 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Royal Exotica Form 3 Phase 2_compressed.pdf | 20 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Royal Exotica_Form 2_Phase 2.pdf | 19 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Royal Exotica_Form 2A_Phase 2.pdf | 19 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Phase 2 SVG disclosure of sold booked inventory.pdf | 19 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ROYAL EXOTICA Form 1 PHASE 2.pdf | 20 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Royal Exotica_Form 2_Phase 2.pdf | 20 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Royal Exotica_Form 2A_Phase 2.pdf | 20 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: Phase 2 SVG disclosure of sold booked inventory_compressed.pdf | 20 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Royal Exotica Form 3 Phase 2_compressed.pdf | 20 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Svg Phase2 .pdf | 30 Sep 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Royal Exotica_Form 3_Phase 2_compressed.pdf | 22 Jul 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Royal Exotica_Form 2A_Phase 2.pdf | 21 Jul 2023 |
| Disclosure of sold/ booked inventoryFile: Phase 2 SVG disclosure of sold booked inventory_compressed.pdf | 21 Jul 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A SVG.PDF | 21 Jul 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Royal Exotica_Form 1_Phase 2.pdf | 20 Jul 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Royal Exotica_Form 2_Phase 2.pdf | 20 Jul 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Phase 2 Archtiect Exotica.pdf | 20 Apr 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Phase 2 Engineer Royal Extoica.pdf | 20 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A Phase 2 Engineer Royal Exotica.pdf | 20 Apr 2023 |
| Disclosure of sold/ booked inventoryFile: Phase 2 Disclosure of sold booked inventory SVG Builders.PDF | 20 Apr 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Phase 2 CA Certificate.PDF | 20 Apr 2023 |
| Details of encumbrances concerned to FinanceFile: 1 Details of encumbrances (1).pdf | 10 Mar 2023 |
| Details of encumbrances concerned to LegalFile: 1 Details of encumbrances (1).pdf | 10 Mar 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_PHASE 2_Royal Exotica.pdf | 7 Feb 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Phase 2 Royal Extoica.pdf | 7 Feb 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A_Phase 2 Royal Exotica.pdf | 7 Feb 2023 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold inventory_Phase 2 Royal Exotica_compressed.pdf | 7 Feb 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_Phase 2 Royal Exotica_CA Certificate_compressed.pdf | 7 Feb 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Cert.pdf | 20 Jan 2023 |
| Proforma of Allotment letterFile: Agreement to Sale_SVG_26092022.pdf | 26 Sep 2022 |
| Deviation Report with respect to model copy of AgreementFile: DocScanner 23 Sept 2022 5-17 pm.pdf | 24 Sep 2022 |
| CERSAI detailsFile: CERSAI_Search_Report_200247354529_For_Asset_Based_Search_16_09_2022_18_31_08_870.pdf | 16 Sep 2022 |
| Details of encumbrances concerned to LegalFile: 818-2011 Gaikwad -Plaint copy showing defendent numbers _organized_compressed.pdf | 6 Sep 2022 |
| Details of encumbrances concerned to LegalFile: 818-2011 Order of compromise .pdf | 6 Sep 2022 |
| Details of encumbrances concerned to LegalFile: 1901-2017 case Ex 41 order showing withdrawal of suit .pdf | 6 Sep 2022 |
| Details of encumbrances concerned to LegalFile: Plaint 1091 showing Defendent no 6 and 7.pdf | 6 Sep 2022 |
| Details of encumbrances concerned to LegalFile: encumbrance certificate legal .pdf | 30 Aug 2022 |
| Layout approvalFile: Layout .pdf | 24 Aug 2022 |
| Details of encumbrances concerned to FinanceFile: encumbrance certificate finance .pdf | 24 Aug 2022 |
| Copy of Layout Approval (in case of layout)File: Layout .pdf | 24 Aug 2022 |
| Proforma of Allotment letterFile: Allottment Letter .pdf | 23 Aug 2022 |
| Declaration in FORM BFile: SVG Buildars kondhwa maharera Affidavit cum Declaration Form B 05 07 2022_compressed.pdf | 8 Aug 2022 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Separate Bnk Account .pdf | 8 Aug 2022 |
| Deviation Report with respect to Allotment letterFile: copy.PDF | 11 Jul 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA certificate.pdf | 9 Jul 2022 |
| Building plan approvalFile: bldg 19.pdf | 5 Jul 2022 |
| Building plan approvalFile: bldg 19 -2 .pdf | 5 Jul 2022 |
| Building plan approvalFile: bldg 19 - 3.pdf | 5 Jul 2022 |
| Building plan approvalFile: bldg 20 .pdf | 5 Jul 2022 |
| Building plan approvalFile: bldg 20 -2.pdf | 5 Jul 2022 |
| Details of encumbrances concerned to LegalFile: IMG-20220705-WA0017 (1).pdf | 5 Jul 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: bldg 19.pdf | 5 Jul 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: bldg 19 -2 .pdf | 5 Jul 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: bldg 19 - 3.pdf | 5 Jul 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: bldg 20 .pdf | 5 Jul 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: bldg 20 -2.pdf | 5 Jul 2022 |
| Declaration about Commencement CertificateFile: commencement.pdf | 4 Jul 2022 |
| PAN CardFile: 1 PAN Card.pdf | 30 Jun 2022 |
| Copy of the legal title reportFile: 1 Copy of the legal title report.pdf | 30 Jun 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE CC0576 14 06 2019.pdf | 30 Jun 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 64 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Royal Exotica Phase 2 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Kondhwa13,700+ in Pune
Filed coordinates, straight-line distance. 194 registered projects within 2 km.
Dwarikadham
Yashodhan Affordable Landmark LLP
UNITAS FASHION CENTER
UNITATIS DEVELOPMENTS PVT. LTD
Millennium Park
Xrbia Epoch Creations LLP
BABAR CLASSIC VISTA WING E, F, G
Classic Properties
JITO NAGAR
JAIN ASHAPURI DEVELOPER UNIT II
Wellwisher West Views
Bhansali Infrastructure LLP
Builder: SVG Builders LLP
SVG Builders LLP has 2 registrations on MahaRERA, including ROYAL EXOTICA PHASE I and Royal Exotica Phase 2. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that Royal Exotica Phase 2 shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Royal Exotica Phase 2 is delayed beyond 31 Mar 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Royal Exotica Phase 2?
The registered promoter entity is SVG Builders LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Royal Exotica Phase 2?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Royal Exotica Phase 2?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Royal Exotica Phase 2?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Royal Exotica Phase 2?
The professionals named in the filing: Architect: CUBIX Architects Associates Imran Shaikh; Engineer: Planedge Consultants Pvt Ltd; Chartered Accountant: Muttha Lahoti and Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Royal Exotica Phase 2?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback