ROSE CASTLE

By Rose Crystal Developers

RG-MH-92306 · RERA P52100016884 · Last updated on MahaRERA portal: 4 Apr 2025

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 40 months
  • 3 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Sep 2025Possession promisedregistration recorded completed
11 of 22Construction stages doneacross 2 buildings; furthest along: Basement (if any), 95%
1Complaints at MahaRERAon this registration
Jump to the 61 documents Report an error

ROSE CASTLE is a Residential / Group Housing project by Rose Crystal Developers in Pune, Maharashtra, registered with MahaRERA as P52100016884 on 20 Jun 2018. The registration is recorded completed; possession was promised by 30 Sep 2025. The completion date has moved by 40 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameROSE CASTLE
  • TypeResidential / Group Housing
  • Location
    • Borhadewadi
    • Near Panchsheel Club
    • Moshi
    • Pimpri Chinchawad (M Corp.)
    • Haveli
    • Pune
    • 412105
  • Pincode412105
  • RERA no.P52100016884
  • ReraGenie IDRG-MH-92306

Builder

  • NameRose Crystal Developers
  • Entity typePartnership
  • PartnersKaran Gulab Ratnani, Jagdishsingh Bhagatsingh Ramsinghani, Sunil Hassnand Ramchandani, Nirvairsingh Jagdishsingh Ramsinghani, Suresh Uttam Kakde
  • Other registrations1 more →
  • Completed2 of 2
  • Declared earlier projects3 →

Key dates

this monthRegisteredJun 2018First promiseMay 2022Revised toSep 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on20 Jun 2018
  • Promised completion30 Sep 2025
  • Revised completionRevised to 30 Sep 2025 (originally 30 May 2022)
  • Buildings2 building records
  • Documents filed61 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BNA120000
DNA90000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 4 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Basement (if any), at 95%.

B87%
ActivityProgress
Excavation100%
Basement (if any)95%
Podiums (if any)0%
Plinth95%
Stilt Floor95%
Slabs of Super Structure95%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
D91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 4 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes90%
Water SupplyYes90%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes90%
Landscaping & Tree PlantingYes90%
Street LightingYes90%
Community BuildingsYes95%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes90%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes90%
Electrical meter room, sub-station, receiving stationYes90%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed123

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots123
Closed/Covered74
Open Space49
BuildingClosed/CoveredOpen SpaceTotal
B402161
D342862

Land and ownership11

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,050 sq m
Land owned byThe promoter, with other names on the file
Named landowners11
LandownerVillageDistrict
ROSE CRYSTAL DEVELOPERSPimpri Chinchawad (M Corp.)Pune
Sopan Baban BoratePimpri Chinchawad (M Corp.)Pune
GANGUBAI SOPAN BORATEPimpri Chinchawad (M Corp.)Pune
NIVRUTTI SOPAN BORATEPimpri Chinchawad (M Corp.)Pune
SUNITA NIVRUTTI BORATEPimpri Chinchawad (M Corp.)Pune
ROHIT BORATEPimpri Chinchawad (M Corp.)Pune
ROHAN BORATEPimpri Chinchawad (M Corp.)Pune
SHANTARAM BORATEPimpri Chinchawad (M Corp.)Pune
MANISHA BORATEPimpri Chinchawad (M Corp.)Pune
VISHAL BORATEPimpri Chinchawad (M Corp.)Pune
VIRAJ BORATEPimpri Chinchawad (M Corp.)Pune

Approvals and building plan

Permissible FSI4496.81
Proposed, not sanctioned4,497 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchAJMERA COMPLEX PIMPRI PUNE 411018

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMr Narendra Joshi
PartnerRole in project
Rose Crystal Developers-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100015097May 2022 → Jul 2024

Reason as filed by the promoterWe are into the process of completion of our project “Rose Castle” for which the completion date as seen is 31st March, 2023. However due to certain conditions, enumerated below, the completion of the project is being pushed further. We thus are applying for extension of the completion of the project for which we request you to take cognizance and grant the extension. 1. Covid-19 has left a great impact on the commercial market and its impact is heavily seen in availability of raw materials, labour and also the movement of raw materials which are due for delivery. 2. The supply of labour is st

EXT52100012086May 2022 → Mar 2023

Reason as filed by the promoterReasons for delay has been listed in the letter attached. Thanks

EXT52100024816May 2022 → Sep 2025

Reason as filed by the promoterThe Rose Castle project comprises two buildings, Building B and Building D. We are pleased to inform you that Building D has already received its Occupation Certificate (OC) on 07/11/2023. Additionally, the construction of Building B is more than 90% complete, and we are committed to completing the remaining work within the next few months. The delay in completing the project has been due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we have been actively working to resolve these issues and ensure the timely compl

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12500537Shridarshan Gopichand BadgujarRose Crystal Developers16/02/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 8 Jun 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 8 Jun 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Jun 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 27 Jun 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 8 Feb 2025

Documents filed61

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of CA (Form 3)File: Form 3 Dec 2024 Numbere.pdf4 Apr 2025
Certificates of CA (Form 3)File: Form 3 Dec 2024 Numbere.pdf4 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 18-19.pdf13 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 19-20.pdf13 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 20-21.pdf13 Mar 2025
Other - TechnicalFile: P52100016884_FileName_3.pdf13 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 21-22.pdf13 Mar 2025
Declaration in FORM BFile: Form B.pdf8 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Dec 2024_11zon.pdf8 Feb 2025
Certificates of CA (Form 3)File: Form 3 Dec 2024_11zon.pdf8 Feb 2025
Certificates of CA (Form 3)File: 2 Certificates of CA (Form 3) (2).pdf8 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Dec 2024.pdf8 Feb 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: PART OC wing D.pdf8 Feb 2025
Disclosure of sold/ booked inventoryFile: Circular 29- RC_11zon.pdf8 Feb 2025
CERSAI detailsFile: Cersai declaration _ castle.pdf8 Feb 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: FORMAT A.pdf8 Feb 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A.pdf8 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 2022-23.pdf8 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 2023-24.pdf8 Feb 2025
Declaration in FORM BFile: Affidavit.pdf2 Dec 2024
Other - LegalFile: Affidavit for Extension.pdf2 Dec 2024
Declaration about Commencement CertificateFile: Declaration for commencement.pdf2 Dec 2024
CERSAI detailsFile: CERSAI Report.pdf2 Dec 2024
Other - TechnicalFile: Reason for extension.pdf2 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect_B and D_compressed.pdf16 Oct 2024
Disclosure of sold/ booked inventoryFile: Sold_Unsold B_compressed.pdf16 Oct 2024
Disclosure of sold/ booked inventoryFile: Sold_Unsold D_compressed.pdf16 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2A BD 2223.pdf16 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 2A BD 2324.pdf16 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Quality Certificate.pdf20 Mar 2023
Disclosure of sold/ booked inventoryFile: Sold unsold_B.pdf20 Mar 2023
Disclosure of sold/ booked inventoryFile: sold unsold_D.pdf20 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5_2021-22.pdf20 Mar 2023
Building plan approvalFile: Layout_sanctioned.pdf30 Jun 2022
Building Plan Approval (IOD)File: Layout_sanctioned.pdf30 Jun 2022
Commencement Certificates / NA Order for plotted developmentFile: New Commencement.pdf27 Jun 2022
Declaration about Commencement CertificateFile: Commencement Declaration.pdf27 Jun 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 2A_2019-20.pdf27 Jun 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 2A_2020-21.pdf27 Jun 2022
Disclosure of sold/ booked inventoryFile: Sold Unsold_B.pdf27 Jun 2022
Disclosure of sold/ booked inventoryFile: Sold Unsold_D.pdf27 Jun 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5_2018-19.pdf27 Jun 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5_2019-20.pdf27 Jun 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5_2020-21.pdf27 Jun 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate.pdf22 Jun 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf22 Jun 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Quality Certificate.pdf22 Jun 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Quality Certificate.pdf22 Jun 2022
CERSAI detailsFile: Cersai_Rose Castle.pdf22 Jun 2022
Layout approvalFile: WING_WISE_FSI_STATEMENT.pdf8 Jun 2018
Building plan approvalFile: WING_WISE_FSI_STATEMENT.pdf8 Jun 2018
PAN CardFile: rose crystal pancard.pdf8 Jun 2018
Copy of the legal title reportFile: TITLE SEARCH REPORT.pdf8 Jun 2018
Details of encumbrancesFile: Self Declaration.pdf8 Jun 2018
Copy of Layout Approval (in case of layout)File: WING_WISE_FSI_STATEMENT.pdf8 Jun 2018
Building Plan Approval (IOD)File: WING_WISE_FSI_STATEMENT.pdf8 Jun 2018
Commencement Certificates / NA Order for plotted developmentFile: COMMENNCEMENT.pdf8 Jun 2018
Declaration in FORM BFile: Form B compressed.pdf8 Jun 2018
Certificates of CA (Form 3)File: ca certificate-compressed.pdf8 Jun 2018
Proforma of Allotment letterFile: ALLOTMENT LETTER (1).pdf8 Jun 2018
Proforma of Allotment letterFile: Preforma of Agreement sales.pdf8 Jun 2018

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise2 not delivered by the promised date
ProjectLocationFlatsRegisteredStatusPromisedDelivered
Rose Gardenia Phase IIP52100035063Kiwale, Pune, Pune138May 2022OngoingSep 2026Not delivered
Rose GardeniaP52100019495Kiwale, Pune-Feb 2019OngoingSep 2026Registered original: Jan 2024Not delivered
Rose GalaxyP52100006411Moshi, Pune83Aug 2017CompletedJul 2023Registered original: Dec 2018Jul 2023

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 40 months
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ROSE CASTLE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Near Panchsheel Club, Moshi13,700+ in Pune

Builder: Rose Crystal Developers

Rose Crystal Developers has 2 registrations on MahaRERA, including ROSE CASTLE and Rose Castle. Its filings disclose 3 earlier MahaRERA projects: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if ROSE CASTLE is delayed beyond 30 Sep 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ROSE CASTLE?

The registered promoter entity is Rose Crystal Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ROSE CASTLE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against ROSE CASTLE?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for ROSE CASTLE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ROSE CASTLE?

The professionals named in the filing: Architect: Mr Narendra Joshi. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ROSE CASTLE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ROSE CASTLE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ROSE CASTLE to a free account