Home / Browse projects / Pune, Maharashtra / Rose Galaxy
Rose Galaxy
RG-MH-19899 · RERA P52100006411 · Last updated on MahaRERA portal: 24 Dec 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 7 months past the filed date
- 2 complaints at MahaRERA
- Completion date moved by 87 months
- 3 extensions taken
Clear
- No litigation declared
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Rose Galaxy is a Residential / Group Housing project by Rose Dream Developers in Pune, Maharashtra, registered with MahaRERA as P52100006411 on 14 Aug 2017. Possession was promised by 31 Mar 2026 and is now 7 months past that date. The completion date has moved by 87 months from the original filing. 32 of the 83 units on this registration are recorded sold or booked, and 8 of 22 construction stages are filed complete. 2 complaints are on record with the regulator.
At a glance
Project
- NameRose Galaxy
- TypeResidential / Group Housing
- Location
- Borhadewadi
- Moshi
- Pimpri Chinchawad (M Corp.)
- Haveli
- Pune
- 412105
- Pincode412105
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100006411
- ReraGenie IDRG-MH-19899
Builder
- NameRose Dream Developers
- Entity typePartnership
- PartnersKaran Gulab Ratnani, Sunil H Ramchandani, Vishal Rajkumar Dharmani, Jeetu Kishinchand Kukreja, Navin Rajkumar Dharmani
- Other registrations2 more →
- No longer live1 lapsed, de-registered or revoked
- Past their filed date2
- Declared earlier projects1 →
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on14 Aug 2017
- Promised completion31 Mar 2026
- Revised completionRevised to 31 Mar 2026 (originally 31 Dec 2018)
- Buildings2 building records
- Documents filed180 files
Current status
Figures as on 24 Dec 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A Building | NA | 3 | 3 | 47 | 0 | 47 |
| B Building | NA | 5 | 5 | 36 | 0 | 36 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 24 Dec 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
8 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Staircases, at 80%.
A Building49%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 30% |
| Sanitary Fittings within the flats / premises | 30% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 80% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
B Building58%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 50% |
| Sanitary Fittings within the flats / premises | 50% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 80% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 60% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 24 Dec 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed82
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| A Building | 28 | 19 | 47 |
| B Building | 21 | 14 | 35 |
Land and ownership1
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| Nirmiti Constructions | Bhosari | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Yijana Architect Arun joshi |
| Engineer | Structure Vizion |
| Engineer | nitin khobare |
| Chartered Accountant | priyesh jain |
| Chartered Accountant | nilesh raut |
| Partner | Role in project |
|---|---|
| Rose Dream Developers | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterAs there was Court Case and complaint filed by the tenements the same has got withdrawn in the favor the applicant hence project extension is required for completing construction activity and giving possession of flats to customers
Reason as filed by the promoterThe owners of the land adjacent to the project Mr. Ganesh Mokashe & Family have created nuisance due to various transaction entered by them with original land owners i.e. Borate Family, and they have filed various Civil & Criminal Cases against the firm and have also filed a Complaint before MAHARERA and various other forums. The Partners of the firm have appointed there Legal Representatives and submitted their replies before all the forums with whom the complaints have been filed & getting the cases to Legal Conclusion which has taken most of the time resulting in certain delay in Completion
Reason as filed by the promoterWe are applying for Extension (i.e. extension after receiving Completion Certificate) of our Project. The Completion Date with MahaRERA Authority, is 31-07-2023 which is required to be extended till 31-03-2026 considering receipt of completion certificate dated 12-01-2024
Litigation declared3
| Case | Court | Status |
|---|---|---|
| 1079/2018 | Civil Court Senior Division Pune | Notice is Served |
| 250/2018 | Session Court Shivajinagar Pune | Final Bail Granted |
| 1079/2018/2018 | Civil Court Division Pune | Suit is withdrawn court order received |
Complaints filed with MahaRERA2
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000011275 | GANESH MOKASHE | NIRMITI CONSTRUCTIONS AND ROSE DREAM DEVELOPERS | 07/04/2018 |
| CC005000000011925 | GANESH MOKASHE | M/S ROSE DREAM DEVELOPERS (PARTNERSHIP FIRM) & M/S NIRMITI CONSTRUCTION (PARTNERSHIP FIRM) | 14/08/2018 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 9 Aug 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 29 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 19 May 2018 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 19 May 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed180
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 180 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: Form-1 Architect Certificate 30062023.pdf | 24 Dec 2025 |
| Form 2File: Form-2 Engineer Certificate 30062023.pdf | 24 Dec 2025 |
| Form 3File: Form-3 CA Certificate 30062023.pdf | 24 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Booked Inventory 30062023.pdf | 24 Dec 2025 |
| Form 1File: Form-1 Architect Certificate 30092017.pdf | 11 Dec 2025 |
| Form 2File: Form-2 Engineer Certificate 30092017.pdf | 11 Dec 2025 |
| Form 3File: Form-3 CA Certificate 30092017.pdf | 11 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Booked Inventory 30092017.pdf | 11 Dec 2025 |
| Form 1File: Form-1 Architect Certificate 31122017.pdf | 11 Dec 2025 |
| Form 2File: Form-2 Engineer Certificate 31122017.pdf | 11 Dec 2025 |
| Form 3File: Form-3 CA Certificate 31122017.pdf | 11 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Booked Inventory 31122017.pdf | 11 Dec 2025 |
| Form 1File: Form-1 Architect Certificate 31032018.pdf | 11 Dec 2025 |
| Form 2File: Form-2 Engineer Certificate 31032018.pdf | 11 Dec 2025 |
| Form 3File: Form-3 CA Certificate 31032018.pdf | 11 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Booked Inventory 31032018.pdf | 11 Dec 2025 |
| Form 1File: Form-1 Architect Certificate 30062018.pdf | 11 Dec 2025 |
| Form 2File: Form-2 Engineer Certificate 30062018.pdf | 11 Dec 2025 |
| Form 3File: Form-3 CA Certificate 30062018.pdf | 11 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Booked Inventory 30062018.pdf | 11 Dec 2025 |
| Form 1File: Form-1 Architect Certificate 30092018.pdf | 11 Dec 2025 |
| Form 2File: Form-2 Engineer Certificate 30092018.pdf | 11 Dec 2025 |
| Form 3File: Form-3 CA Certificate 30092018.pdf | 11 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Booked Inventory 30092018.pdf | 11 Dec 2025 |
| Form 1File: Form-1 Architect Certificate 31122018.pdf | 11 Dec 2025 |
| Form 2File: Form-2 Engineer Certificate 31122018.pdf | 11 Dec 2025 |
| Form 3File: Form-3 CA Certificate 31122018.pdf | 11 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Booked Inventory 31122018.pdf | 11 Dec 2025 |
| Form 1File: Form-1 Architect Certificate 30062019.pdf | 11 Dec 2025 |
| Form 2File: Form-2 Engineer Certificate 30062019.pdf | 11 Dec 2025 |
| Form 3File: Form-3 CA Certificate 30062019.pdf | 11 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Booked Inventory 30062019.pdf | 11 Dec 2025 |
| Form 1File: Form-1 Architect Certificate 30092019.pdf | 11 Dec 2025 |
| Form 2File: Form-2 Engineer Certificate 30092019.pdf | 11 Dec 2025 |
| Form 3File: Form-3 CA Certificate 30092019.pdf | 11 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Booked Inventory 30092019.pdf | 11 Dec 2025 |
| Form 1File: Form-1 Architect Certificate 31122019.pdf | 11 Dec 2025 |
| Form 2File: Form-2 Engineer Certificate 31122019.pdf | 11 Dec 2025 |
| Form 3File: Form-3 CA Certificate 31122019.pdf | 11 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Booked Inventory 31122019.pdf | 11 Dec 2025 |
| Form 1File: Form-1 Architect Certificate 30062020.pdf | 11 Dec 2025 |
| Form 2File: Form-2 Engineer Certificate 30062020.pdf | 11 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Booked Inventory 30062020.pdf | 11 Dec 2025 |
| Form 3File: Form-3 CA Certificate 30062020.pdf | 11 Dec 2025 |
| Form 1File: Form-1 Architect Certificate 30092020.pdf | 11 Dec 2025 |
| Form 2File: Form-2 Engineer Certificate 30092020.pdf | 11 Dec 2025 |
| Form 3File: Form-3 CA Certificate 30092020.pdf | 11 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Booked Inventory 30092020.pdf | 11 Dec 2025 |
| Form 1File: Form-1 Architect Certificate 31122020.pdf | 11 Dec 2025 |
| Form 2File: Form-2 Engineer Certificate 31122020.pdf | 11 Dec 2025 |
| Form 3File: Form-3 CA Certificate 31122020.pdf | 11 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Booked Inventory 31122020.pdf | 11 Dec 2025 |
| Form 1File: Form-1 Architect Certificate 31032021.pdf | 11 Dec 2025 |
| Form 2File: Form-2 Engineer Certificate 31032021.pdf | 11 Dec 2025 |
| Form 3File: Form-3 CA Certificate 31032021.pdf | 11 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Booked Inventory 31032021.pdf | 11 Dec 2025 |
| Form 1File: Form-1 Architect Certificate 30062021.pdf | 11 Dec 2025 |
| Form 2File: Form-2 Engineer Certificate 30062021.pdf | 11 Dec 2025 |
| Form 3File: Form-3 CA Certificate 30062021.pdf | 11 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Booked Inventory 30062021.pdf | 11 Dec 2025 |
| Form 1File: Form-1 Architect Certificate 30092021.pdf | 11 Dec 2025 |
| Form 2File: Form-2 Engineer Certificate 30092021.pdf | 11 Dec 2025 |
| Form 3File: Form-3 CA Certificate 30092021.pdf | 11 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Booked Inventory 30092021.pdf | 11 Dec 2025 |
| Form 1File: Form-1 Architect Certificate 31122021.pdf | 11 Dec 2025 |
| Form 2File: Form-2 Engineer Certificate 31122021.pdf | 11 Dec 2025 |
| Form 3File: Form-3 CA Certificate 31122021.pdf | 11 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Booked Inventory 31122021.pdf | 11 Dec 2025 |
| Form 1File: Form-1 Architect Certificate 31032022.pdf | 11 Dec 2025 |
| Form 2File: Form-2 Engineer Certificate 31032022.pdf | 11 Dec 2025 |
| Form 3File: Form-3 CA Certificate 31032022.pdf | 11 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Booked Inventory 31032022.pdf | 11 Dec 2025 |
| Form 1File: Form-1 Architect Certificate 30062022.pdf | 11 Dec 2025 |
| Form 2File: Form-2 Engineer Certificate 30062022.pdf | 11 Dec 2025 |
| Form 3File: Form-3 CA Certificate 30062022.pdf | 11 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Booked Inventory 30062022.pdf | 11 Dec 2025 |
| Form 1File: Form-1 Architect Certificate 30092022.pdf | 11 Dec 2025 |
| Form 2File: Form-2 Engineer Certificate 30092022.pdf | 11 Dec 2025 |
| Form 3File: Form-3 CA Certificate 30062022.pdf | 11 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Booked Inventory 30092022.pdf | 11 Dec 2025 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Rose Gardenia | S no 9 B P Kiwale Pune | 182 | Completed | Jan 2024 | Jan 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 180 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Rose Galaxy on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Moshi13,700+ in Pune
Filed coordinates, straight-line distance. 218 registered projects within 2 km.
TANISH PARK
TANISH DEVELOPERS
Ajinkya Towers
APAK Bussiness Innovation Pvt Ltd
SILVER GARDENIA
SILVER PROMOTERS AND DEVELOPERS
Mangalam Life Park
Mangalam Buildcorp
SingaPune Ph 3
Xrbia Mirth Properties LLP
SingaPune Ph 2
Xrbia Mirth Properties LLP
Builder: Rose Dream Developers
Rose Dream Developers has 3 registrations on MahaRERA, including Rose Galaxy and Rose Gardenia. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that Rose Galaxy shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Rose Galaxy is delayed beyond 31 Mar 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Rose Galaxy?
The registered promoter entity is Rose Dream Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Rose Galaxy?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Rose Galaxy?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Rose Galaxy?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Rose Galaxy?
The professionals named in the filing: Architect: Yijana Architect Arun joshi; Engineer: Structure Vizion; Engineer: nitin khobare; Chartered Accountant: priyesh jain; Chartered Accountant: nilesh raut. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Rose Galaxy?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback