ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / ROHAN YUVA - BUILD A

Registered No litigation declared Commercial project

ROHAN YUVA - BUILD A

By ANUMIT BUILDCON PRIVATE LIMITED

RG-MH-14642 · RERA P52100023080 · Last updated on MahaRERA portal: 16 Aug 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 40 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Apr 2027Possession promisedmoved 40 months from the original
4 of 11Construction stages donefurthest along: Staircases, 72%
102 of 127Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 175 documents Report an error

ROHAN YUVA - BUILD A is a Commercial project by ANUMIT BUILDCON PRIVATE LIMITED in Pune, Maharashtra, registered with MahaRERA as P52100023080 on 29 Nov 2019. Possession is promised by 30 Apr 2027. The completion date has moved by 40 months from the original filing. 25 of the 127 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.

At a glance

Project

  • NameROHAN YUVA - BUILD A
  • TypeCommercial
  • Location
    • PUNE NAGAR HIGHWAY
    • PUNE NAGAR ROAD
    • WAGHOLI
    • Haveli
    • Pune
    • 412207
  • Pincode412207
  • RERA no.P52100023080
  • ReraGenie IDRG-MH-14642

Builder

  • NameANUMIT BUILDCON PRIVATE LIMITED
  • Entity typeCompany
  • CINU41001PN2025PTC248816
  • PartnersARUN RAGHU THIGALE, JALINDAR VITTHAL SASWADE
  • Other registrations2 more →

Key dates

this monthRegisteredNov 2019First promiseDec 2023Revised toApr 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on29 Nov 2019
  • Promised completion30 Apr 2027
  • Revised completionRevised to 30 Apr 2027 (originally 30 Dec 2023)
  • Buildings1 building record
  • Documents filed175 files

Current status

20%25 of 127 units booked
97.5%Work done, per cost certificate

Figures as on 16 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ROHAN YUVA - BUILD ANA660127127

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 16 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 72%.

ROHAN YUVA - BUILD A: 61% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises5%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks72%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.55%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%

Progress on shared amenities15

As on 16 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes25%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed113

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots113
Closed/Covered104
Open Space9

Land and ownership3

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area2,637 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on8 Nov 2025
LandownerVillageDistrict
VISHNU PANDURANG SATAV & FAMILYWAGHOLIPune
DATTATRAY PANDURANG SATAV & FAMILYWAGHOLIPune
Vishnu Pandurang SatavWAGHOLIPune

Approvals and building plan

Sanctioning authorityPMRDA
Permissible FSI5545.0
Proposed, not sanctioned5,545 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchOffice no 101 and 102 First floor Bahiratwadi Dist Pune
Estimated costRs 17.34 cr
Cost incurredRs 16.90 cr
Work done97.45%
BuildingWingEstimatedIncurred
ROHAN YUVA - BUILD ANARs 13.62 crRs 13.46 cr
-NARs 3.73 crRs 3.45 cr

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectATIT SHRIKANT ADMULWAR
EngineerLAXMIKANT MORE
Chartered AccountantRSMS AND ASSOCIATES
Chartered AccountantK D Gargorte & Associates
Chartered AccountantIndrajit Tambade
Chartered AccountantPrasad Nandkumar Malkar
Chartered AccountantDBT AND ASSOCIATES
PartnerRole in project
ANUMIT BUILDCON PRIVATE LIMITED-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100018588Dec 2023 → Dec 2024

Reason as filed by the promoterWe have declared our date of completion is 30/12/2023 however due to some hindrances which are more specifically mentioned below we are requesting you for granting of extension for the project completion date till 29/12/2024. Reason for Delay Project:- Due to lockdown 1.0 we are facing lots of issue to complete the project on time. There are various issues standing in front of us in this pandemic. • There is lack of supply of construction Material as well as transportation of material on site. • Also facing problem of labours as they are migrated to their native place in this covid situation.

EXT52100027572Dec 2023 → Apr 2027

Reason as filed by the promoterWe have attached declaration form explanation the reason for delay in other tab, also attached the explanation for extension period.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 6 Nov 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 13 Nov 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 6 Nov 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 6 Nov 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Apr 2027

Documents filed175

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 175 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 - Building A - Jun 26.pdf16 Aug 2026
Withdrawal Update Form 2File: Form 2-A Bldg Jun 26.pdf16 Aug 2026
Withdrawal Update Form 3File: Form3.pdf16 Aug 2026
Form 2A (FY 2020-2021)File: Form 2A - A Bldg - 2021.pdf16 Aug 2026
Form 2A (FY 2021-2022)File: Form 2A - A Bldg - 2022.pdf16 Aug 2026
Form 2A (FY 2022-2023)File: Form 2A - A Bldg - 2023.pdf16 Aug 2026
Form 2A (FY 2023-2024)File: Form 2A - A Bldg - 2024.pdf16 Aug 2026
Form 2A (FY 2024-2025)File: Form 2A - A Bldg - 2025.pdf16 Aug 2026
Form 2A (FY 2025-2026)File: Form 2A - A Bldg - 2026.pdf16 Aug 2026
Form 2A (FY 2026-2027)File: Form 2A - A Bldg - 2027.pdf16 Aug 2026
Form 2A (FY 2019-2020)File: Form 2A - A Bldg - 2020.pdf14 Aug 2026
Withdrawal Update Form 1File: Form 1 - Building A - Jun 26.pdf24 Jul 2026
Withdrawal Update Form 2File: Form 2-A Bldg Jun 26.pdf24 Jul 2026
Withdrawal Update Form 3File: Form3.pdf24 Jul 2026
Withdrawal Update Form 1File: Form 1 - A Bldg.pdf6 May 2026
Withdrawal Update Form 2File: Form 2- Build A.pdf6 May 2026
Withdrawal Update Form 3File: Form 3 - A Bldg.pdf6 May 2026
Withdrawal Update Form 1File: A Bldg - Form 1 Dec 25.pdf31 Jan 2026
Withdrawal Update Form 2File: Form 2 - A Bldg - Dec 25.pdf31 Jan 2026
Withdrawal Update Form 3File: Form 3 - A Bldg - Dec 25.pdf31 Jan 2026
Form 1File: A Bldg - Form 1 - Mar 25.pdf13 Nov 2025
Form 2File: A Bldg - Form 2 - Mar 25.pdf13 Nov 2025
Form 3File: Form 3 Q-4 F.pdf13 Nov 2025
Disclosure of Sold and Booked InventoryFile: 24-25 Q-4.pdf13 Nov 2025
Withdrawal Update Form 1File: A Bldg - Form 1 - Mar 25.pdf13 Nov 2025
Withdrawal Update Form 1File: A Bldg - Form 1 - Jun 25.pdf13 Nov 2025
Withdrawal Update Form 1File: A Bldg - Form 1 - Sep 25.pdf13 Nov 2025
Withdrawal Update Form 2File: A Bldg - Form 2 - Mar 25.pdf13 Nov 2025
Withdrawal Update Form 2File: A Bldg - Form 2 - Jun 25.pdf13 Nov 2025
Withdrawal Update Form 2File: A Bldg - Form 2 - Sep 25.pdf13 Nov 2025
Withdrawal Update Form 3File: Form 3 Q-4 F.pdf13 Nov 2025
Withdrawal Update Form 3File: Form 3 Q-1 25-26.pdf13 Nov 2025
Withdrawal Update Form 3File: Form 3 Q-2 25-26.pdf13 Nov 2025
Declaration in FORM BFile: Form - B - A Bldg.pdf5 Mar 2025
Declaration about Commencement CertificateFile: Format D - Building A.pdf5 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 12 A Bldg - Form 3 - 30-09-22.pdf18 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 13 A Bldg - Form 3 - 31-12-22.pdf18 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 14 A Bldg - Form 3 - 31-03-23.pdf18 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 15 A Bldg - Form 3 - 30-06-23.pdf18 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 16 A Bldg - Form 3 - 30-09-23.pdf18 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 17 A Bldg - Form 3 - 31-12-23.pdf18 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 18 A Bldg - Form 3 - 31-03-24.pdf18 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 19 A Bldg - Form 3 - 30-06-24.pdf18 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 20 A Bldg - Form 3 - 30-09-24.pdf18 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 21 A Bldg - Form 3 - 31-12-24.pdf18 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 7 A Bldg - Form 3 - 30-06-21.pdf18 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 10 A Bldg - Form 3 - 31-03-22.pdf18 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 9 A Bldg - Form 3 - 31-12-21.pdf18 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 8 A Bldg - Form 3 - 30-09-21.pdf18 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 11 A Bldg - Form 3 - 30-06-22.pdf18 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 6 A Bldg - Form 3 - 31-03-21.pdf18 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 5 A Bldg - Form 3 - 31-12-20.pdf18 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 4 A Bldg - Form 3 - 30-09-20.pdf18 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3 A Bldg - Form 3 - 30-06-20.pdf18 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 2 A Bldg - Form 3 - 31-03-20.pdf18 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 1 A Bldg - Form 3 - 31-12-19.pdf18 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: A Bldg - Form 5 2023-24.pdf18 Feb 2025
Details of encumbrances concerned to FinanceFile: A Bldg - Legal Encumbrance.pdf17 Feb 2025
Details of encumbrances concerned to FinanceFile: A Bldg - Financial Encumbrances.pdf17 Feb 2025
Details of encumbrances concerned to FinanceFile: A Bldg - Financial Encumbrances.pdf17 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 13 A Bldg Form 1 - Dec 23.pdf17 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 17 A Bldg Form 1 - Dec 24.pdf17 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 16 A Bldg Form 1 - Sep 24.pdf17 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 15 A Bldg Form 1 - Jun 24.pdf17 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 14 A Bldg Form 1 - Mar 24.pdf17 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 12 A Bldg Form 1 - Sep 23.pdf17 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 11 A Bldg Form 1 - Jun 23.pdf17 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 10 A Bldg Form 1 - Dec 22.pdf17 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 8 A Bldg Form 1 - Dec 21.pdf17 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 7 A Bldg Form 1 - Sep 21.pdf17 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 6 A Bldg Form 1 - Jun 21.pdf17 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 9 A Bldg Form 1 - Sep 22.pdf17 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 5 A Bldg Form 1 - Dec 20.pdf17 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 4 A Bldg Form 1 - Sep 20.pdf17 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 3 A Bldg Form 1 - Jun 20.pdf17 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 2 A Bldg Form 1 - Mar 20.pdf17 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 A Bldg Form 1 - Dec 19.pdf17 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 9 Form 2 Jun 22.pdf17 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 10 Form 2 Sep 22.pdf17 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 11 Form 2 Dec 22.pdf17 Feb 2025

How this compares with Pune

20%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 40 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ROHAN YUVA - BUILD A on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near PUNE NAGAR ROAD13,700+ in Pune

Builder: ANUMIT BUILDCON PRIVATE LIMITED

ANUMIT BUILDCON PRIVATE LIMITED has 3 registrations on MahaRERA, including ROHAN YUVA - BUILD A and ROHAN YUVA - BLDG E. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if ROHAN YUVA - BUILD A is delayed beyond 30 Apr 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ROHAN YUVA - BUILD A?

The registered promoter entity is ANUMIT BUILDCON PRIVATE LIMITED, a company as per the filing. Its CIN U41001PN2025PTC248816 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ROHAN YUVA - BUILD A?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ROHAN YUVA - BUILD A?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ROHAN YUVA - BUILD A?

The professionals named in the filing: Architect: ATIT SHRIKANT ADMULWAR; Engineer: LAXMIKANT MORE; Chartered Accountant: RSMS AND ASSOCIATES; Chartered Accountant: K D Gargorte & Associates; Chartered Accountant: Indrajit Tambade; Chartered Accountant: Prasad Nandkumar Malkar. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ROHAN YUVA - BUILD A?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ROHAN YUVA - BUILD A. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ROHAN YUVA - BUILD A to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.