Home / Browse projects / Aurangabad, Maharashtra / RENUKAPURAM PHASE-2

Registration lapsed No litigation declared Residential / Group Housing project

RENUKAPURAM PHASE-2

By PADMANABH BUILDCON

RG-MH-13404 · RERA P51500047597 · Last updated on MahaRERA portal: 29 Jun 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 4 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Aurangabad registration emailed to you, free during the pilot beta.
Jun 2026Possession promised4 months past this date
0 of 11Construction stages donefurthest along: Excavation, 0%
10 of 25Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 77 documents Report an error

RENUKAPURAM PHASE-2 is a Residential / Group Housing project by PADMANABH BUILDCON in Aurangabad, Maharashtra, registered with MahaRERA as P51500047597 on 14 Nov 2022. Possession was promised by 30 Jun 2026 and is now 4 months past that date. 15 of the 25 units on this registration are recorded sold or booked, and 0 of 11 construction stages are filed complete.

At a glance

Project

  • NameRENUKAPURAM PHASE-2
  • TypeResidential / Group Housing
  • Location
    • NASHIK HIGHWAY
    • PADEGAON
    • Aurangabad (M Corp.)
    • Aurangabad
    • 431001
  • Pincode431001
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51500047597
  • ReraGenie IDRG-MH-13404

Builder

  • NamePADMANABH BUILDCON
  • Entity typePartnership
  • PartnersKISHOR HARICHANDRA TALREJA, ANUJA TUSHAR KADAM
  • Other registrations1 more →
  • No longer live2 lapsed, de-registered or revoked

Key dates

4 months past promisethis monthRegisteredNov 2022PromisedJun 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on14 Nov 2022
  • Promised completion30 Jun 2026
  • Revised completionNone
  • Buildings1 building record
  • Documents filed77 files

Current status

60%15 of 25 units booked

Figures as on 29 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ROW HOUSENA2225025

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 29 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 0%.

ROW HOUSE: 0% average across the applicable activities

ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 29 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed48

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots48
Closed/Covered24
Open Space24

Land and ownership5

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,184 sq m
Land owned byThe promoter, with other names on the file
Named landowners5
LandownerVillageDistrict
DHANSING RAMSING WANIAurangabad (M Corp.)Aurangabad
THAKUJI RAMSING WANIAurangabad (M Corp.)Aurangabad
RAMLAL RAMSING WANIAurangabad (M Corp.)Aurangabad
HIRALAL RAMSING WANIAurangabad (M Corp.)Aurangabad
JITENDRA GHANSHYAM WANIAurangabad (M Corp.)Aurangabad

Approvals and building plan

Sanctioning authorityAURANGABAD MUNICIPAL CORPORATION
Permissible FSI6272.64
Proposed, not sanctioned2,773 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSARANG CO OP HO SOC GARKHEDA

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPRAMOD VITHOBA NARALE
EngineerSACHIN HANDE
EngineerER VITTHAL GOLANDE
Chartered AccountantBangad Parjane and Co
Chartered AccountantCA PUNJARAM KALE
PartnerRole in project
PADMANABH BUILDCON-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Aug 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Aug 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Aug 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 Aug 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed77

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2022-2023)File: Form-2A 22-23.pdf29 Jun 2026
Form 2A (FY 2023-2024)File: Form-2A 23-24.pdf29 Jun 2026
Form 2A (FY 2024-2025)File: Form-2A 24-25.pdf29 Jun 2026
Form 2A (FY 2025-2026)File: Form-2A 25-26.pdf29 Jun 2026
Form 1File: Form-1 Sep 25.pdf26 Jun 2026
Form 2File: Form-2 Sep 25.pdf26 Jun 2026
Form 3File: Form-3 Declaration Sep 25.pdf26 Jun 2026
Disclosure of Sold and Booked InventoryFile: Sold Sep 25.pdf26 Jun 2026
Form 1File: Form-1 Dec 25.pdf26 Jun 2026
Form 2File: Form-2 Dec 25.pdf26 Jun 2026
Form 3File: Form-3 Declaration Dec 25.pdf26 Jun 2026
Disclosure of Sold and Booked InventoryFile: Sold Dec 25.pdf26 Jun 2026
Form 1File: Form-1 March 26.pdf26 Jun 2026
Form 2File: Form-2 March 26.pdf26 Jun 2026
Form 3File: Form-3 Declaration March 26.pdf26 Jun 2026
Disclosure of Sold and Booked InventoryFile: Sold March 26.pdf26 Jun 2026
Form 1File: 1 Form-1 March 25.pdf23 Aug 2025
Form 2File: 2 Form-2 March 25.pdf23 Aug 2025
Form 3File: 3 Form-3 March 25.pdf23 Aug 2025
Disclosure of Sold and Booked InventoryFile: 4 Sold March 25.pdf23 Aug 2025
Form 1File: 1 Form-1 June 25.pdf23 Aug 2025
Form 2File: 2 Form-2 June 25.pdf23 Aug 2025
Form 3File: 3 Form-3 June 25.pdf23 Aug 2025
Disclosure of Sold and Booked InventoryFile: 4 Sold June 25.pdf23 Aug 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 March 23.pdf28 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 June 23.pdf28 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 Sep 23.pdf28 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 Dec 23.pdf28 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 March 24.pdf28 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 June 24.pdf28 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 Sep 24.pdf28 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 Dec 24.pdf28 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form- 1 Dec 22.pdf28 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 March 24.pdf28 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 Dec24.pdf28 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FOrm-3 Sep 24.pdf28 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 June 24.pdf28 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 Dec 23.pdf28 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 Sep 23.pdf28 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 June 23.pdf28 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 March 23.pdf28 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 Dec 22.pdf28 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 Dec 22.pdf28 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 March 23.pdf28 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 June 23.pdf28 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 Sep 23.pdf28 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 Dec 23.pdf28 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 March 24.pdf28 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 June 24.pdf28 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 Sep 24.pdf28 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 Dec 24.pdf28 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form-2A 22-23.pdf28 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form-2A 23-24.pdf28 Apr 2025
Details of encumbrances concerned to FinanceFile: Renukapuram Phase 2 No enc fin.pdf31 Oct 2022
Details of encumbrances concerned to LegalFile: Renukapuram Phase 2 No enc fin.pdf31 Oct 2022
Declaration about Commencement CertificateFile: Renukapuram Phase 2 Format D.pdf31 Oct 2022
Proforma of Allotment letterFile: Renukapuram Phase 2 Allotment Letter_compressed.pdf31 Oct 2022
Proforma of Agreement for saleFile: RERA ATS DRAFT.pdf31 Oct 2022
Deviation Report with respect to Allotment letterFile: Renukapuram Phase 2 Deviation Report.pdf31 Oct 2022
Deviation Report with respect to model copy of AgreementFile: Renukapuram Phase 2 Deviation Report.pdf31 Oct 2022
Layout approvalFile: Epson20.pdf28 Aug 2022
Layout approvalFile: Epson21.pdf28 Aug 2022
Layout approvalFile: Epson22.pdf28 Aug 2022
Building plan approvalFile: Epson20.pdf28 Aug 2022
PAN CardFile: PAN PADMANABH BUILDCON.pdf28 Aug 2022
Copy of the legal title reportFile: SEARCH REPORT-PHASE-2.pdf28 Aug 2022
Details of encumbrances concerned to FinanceFile: ENCUBRANCE FINANCE.pdf28 Aug 2022
Details of encumbrances concerned to LegalFile: encumbrance.pdf28 Aug 2022
Copy of Layout Approval (in case of layout)File: Epson20.pdf28 Aug 2022
Copy of Layout Approval (in case of layout)File: Epson21.pdf28 Aug 2022
Copy of Layout Approval (in case of layout)File: Epson22.pdf28 Aug 2022
Building Plan Approval / NA Order for plotted developmentFile: Epson20.pdf28 Aug 2022
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE.pdf28 Aug 2022
Declaration in FORM BFile: FORM B PADMANABH.pdf28 Aug 2022
CERSAI detailsFile: CERSAI.pdf28 Aug 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Padmanabh Buildcon Form 3_compressed.pdf28 Aug 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: SEPRATE BANK-PHASE-2.pdf28 Aug 2022

How this compares with Aurangabad

60%of this project is bookeddistrict median 6%
14%of Aurangabad projects moved their completion datethis one has not
32%of Aurangabad registrations have lapsed or been cancelledthis one is among them

Computed across the 1,400+ Aurangabad projects on ReraGenie, from their own filings.

Keep RENUKAPURAM PHASE-2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near PADEGAON1,400+ in Aurangabad

2 kmRENUKAPURAM PHASE-2Completed 5Lapsed / revoked 6Other 8Dot size: filed unitsN

Filed coordinates, straight-line distance. 19 registered projects within 2 km.

Builder: PADMANABH BUILDCON

PADMANABH BUILDCON has 2 registrations on MahaRERA, including RENUKAPURAM PHASE-1 and RENUKAPURAM PHASE-2. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Aurangabad district page.

Frequently asked questions

What does it mean that RENUKAPURAM PHASE-2 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if RENUKAPURAM PHASE-2 is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of RENUKAPURAM PHASE-2?

The registered promoter entity is PADMANABH BUILDCON, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in RENUKAPURAM PHASE-2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for RENUKAPURAM PHASE-2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at RENUKAPURAM PHASE-2?

The professionals named in the filing: Architect: PRAMOD VITHOBA NARALE; Engineer: SACHIN HANDE; Engineer: ER VITTHAL GOLANDE; Chartered Accountant: Bangad Parjane and Co; Chartered Accountant: CA PUNJARAM KALE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in RENUKAPURAM PHASE-2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About RENUKAPURAM PHASE-2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save RENUKAPURAM PHASE-2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.