Home / Browse projects / Raigarh, Maharashtra / Renaissance Royal Phase 1
Renaissance Royal Phase 1
By Shree Sharada Infrastructures
RG-MH-96178 · RERA P52000019557 · Last updated on MahaRERA portal: 10 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 24 months
- 2 extensions taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Renaissance Royal Phase 1 is a Residential / Group Housing project by Shree Sharada Infrastructures in Raigarh, Maharashtra, registered with MahaRERA as P52000019557 on 8 Feb 2019. Possession is promised by 31 Dec 2026. The completion date has moved by 24 months from the original filing. 64 of the 216 units on this registration are recorded sold or booked, and 18 of 33 construction stages are filed complete.
At a glance
Project
- NameRenaissance Royal Phase 1
- TypeResidential / Group Housing
- Location
- Shinde wadi
- Neral
- Karjat
- Raigarh
- 410101
- Pincode410101
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52000019557
- ReraGenie IDRG-MH-96178
Builder
- NameShree Sharada Infrastructures
- Entity typePartnership
- GSTIN27ABWFS9545H1Z8
- GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
- PartnersSachin Dattatrey Dharmadhikari, Rahul Dattatrey Dharmadhikari
- Other registrations1 more →
- Declared earlier projects1 →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on8 Feb 2019
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 30 Dec 2024)
- Buildings3 building records
- Documents filed170 files
Current status
Figures as on 10 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Wing A | NA | 8 | 6 | 84 | 0 | 84 |
| Wing B | NA | 8 | 6 | 84 | 0 | 84 |
| Wing D | NA | 7 | 4 | 48 | 0 | 48 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 10 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
18 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Sanitary Fittings within the flats / premises, at 80%.
Wing A77%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 80% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 70% |
Wing B82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Wing D38%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 50% |
| Slabs of Super Structure | 70% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 30% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 70% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 10 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 80% |
| Water Supply | Yes | 20% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 20% |
| Storm Water Drains | Yes | 80% |
| Landscaping & Tree Planting | Yes | 15% |
| Street Lighting | Yes | 40% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 30% |
| Electrical meter room, sub-station, receiving station | Yes | 30% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed49
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| Wing A | 19 | 19 |
| Wing B | 19 | 19 |
| Wing D | 11 | 11 |
Land and ownership9
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| Kishor Narayan Patil | Neral | Raigarh |
| Ganesh Narayan Patil | Neral | Raigarh |
| Balu Ganpat Chanche | Neral | Raigarh |
| Atmaram Ambo Chanche | Neral | Raigarh |
| Ramchandra Ambo Chanche | Neral | Raigarh |
| Narayan Ambo Chanche | Neral | Raigarh |
| Sunil Ambo Chanche | Neral | Raigarh |
| Ulhas Bhaga Shingate | Neral | Raigarh |
| Ramchandra Kamlu Hable | Neral | Raigarh |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Shree Sthapatya Associates |
| Engineer | SK Consultants & Engineers |
| Engineer | Sandeep Dashrath Deshmukh |
| Chartered Accountant | NB Sayed & Associates |
| Chartered Accountant | PRANAV BHASKARAN & ASSOCIATES |
| Chartered Accountant | CAP & CO. |
| Partner | Role in project |
|---|---|
| Shree Sharada Infrastructures | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterIn accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19.
Reason as filed by the promoterWe apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 30 Jan 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 1 Feb 2019 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 28 Nov 2025 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 1 Feb 2019Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2026
Documents filed170
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 170 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2A (FY 2025-2026)File: Form 2A.pdf | 10 Jul 2026 |
| Form 5 (FY 2023-2024)File: Form 5 - Renaissance Royal Phase - 1 FY 23-24.pdf | 5 Jun 2026 |
| Form 5 (FY 2024-2025)File: Form 5 - Renaissance Royal Phase - 1 FY 24-25.pdf | 5 Jun 2026 |
| Withdrawal Update Form 1File: Form 1 - Renaissance Royal Phase 1 as on March 2026.pdf | 29 May 2026 |
| Withdrawal Update Form 2File: Form 2 - Renaissance Royal Phase 1 as on March 2026.pdf | 29 May 2026 |
| Withdrawal Update Form 3File: Form 3 -Renaissance Royal Phase 1 as on March 2026.pdf | 29 May 2026 |
| Withdrawal Update Form 1File: Form 1 - Renaissance Royal Phase -1 as on Dec 2025.pdf | 13 Jan 2026 |
| Withdrawal Update Form 2File: Form 2 - Renaissance Royal Phase -1 as on Dec 2025.pdf | 13 Jan 2026 |
| Withdrawal Update Form 3File: Form 3 - Renaissance Royal Phase -1 as on Dec 2025.pdf | 13 Jan 2026 |
| Building plan approvalFile: 2.pdf | 28 Nov 2025 |
| Building plan approvalFile: 5.pdf | 28 Nov 2025 |
| Building plan approvalFile: 6.pdf | 28 Nov 2025 |
| Building plan approvalFile: 7.pdf | 28 Nov 2025 |
| Building plan approvalFile: 8.pdf | 28 Nov 2025 |
| Building plan approvalFile: 11.pdf | 28 Nov 2025 |
| Building plan approvalFile: 12.pdf | 28 Nov 2025 |
| Building plan approvalFile: 13.pdf | 28 Nov 2025 |
| Building plan approvalFile: 14.pdf | 28 Nov 2025 |
| Building plan approvalFile: 15.pdf | 28 Nov 2025 |
| Building plan approvalFile: 16.pdf | 28 Nov 2025 |
| Withdrawal Update Form 1File: Form 1 - Renaissance Royal Phase -1 as on Sep 2025.pdf | 18 Nov 2025 |
| Withdrawal Update Form 2File: Form 2 - Renaissance Royal Phase -1 as on Sep 2025.pdf | 18 Nov 2025 |
| Withdrawal Update Form 3File: Form 3 - Renaissance Royal Phase -1 as on Sep 2025.pdf | 18 Nov 2025 |
| Withdrawal Update Form 1File: Form 1 - Renaissance Royal Phase 1 as on June 2025.pdf | 10 Nov 2025 |
| Withdrawal Update Form 2File: Form 2 - Renaissance Royal Phase 1 as on June 2025.pdf | 10 Nov 2025 |
| Withdrawal Update Form 3File: Form 3 - Renaissance Royal Phase 1 as on June 2025.pdf | 10 Nov 2025 |
| Certificates of CA (Form 3)File: Form 3 of Renaissance Royal Phase -1 as on 31-03-2025-Signed.pdf | 20 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Renaissance Royal Phase 1 as on March 2025.pdf | 20 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Renaissance Royal Phase 1 as on Dec 2024.pdf | 7 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Renaissance Royal Phase 1 as on March 2025.pdf | 7 Apr 2025 |
| Certificates of CA (Form 3)File: Form 3 - Renaissance Royal Phase 1 as on Dec 2024.pdf | 7 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Renaissance Royal Phase 1 as on Dec 2024.pdf | 7 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - ARCHITECH CERTIFICATE - JUL24 TO SEP 24.pdf | 24 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - ARCHITECH CERTIFICATE - JUL24 TO SEP 24.pdf | 24 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - ARCHITECH CERTIFICATE - JUL24 TO SEP 24.pdf | 24 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Renaissance Royal Phase 1 as on Sep 2024.pdf | 20 Oct 2024 |
| Certificates of CA (Form 3)File: Form 3 of Renaissance Royal Phase -1 as on 30-09-2024.pdf | 20 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Renaissance Royal Phase 1 as on Sep 2024.pdf | 20 Oct 2024 |
| Certificates of CA (Form 3)File: Form 3 of Renaissance Royal Phase -1 as on 30-09-2024.pdf | 20 Oct 2024 |
| Certificates of CA (Form 3)File: Form 3 of Renaissance Royal Phase -1 as on 30-09-2024.pdf | 20 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Renaissance Royal Phase 1 as on Sep 2024.pdf | 20 Oct 2024 |
| Declaration in FORM BFile: Form B (Affidavit cum Declaration).pdf | 7 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Architect Certificate.pdf | 7 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineers Certificate June 2024.pdf | 7 Oct 2024 |
| Certificates of CA (Form 3)File: Form 3 CA Certificate June 2024.pdf | 7 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Circular 29 - Disclosure of Sold Booked Inventory.PDF | 7 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: (19-20) Form 2A - Quality Assurance Certificate.pdf | 7 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: (20-21) Form 2A - Quality Assurance Certificate.pdf | 7 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: (21-22) Form 2A - Quality Assurance Certificate.pdf | 7 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: (22-23) Form 2A - Quality Assurance Certificate.pdf | 7 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: (23-24) Form 2A - Quality Assurance Certificate.pdf | 7 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: (18-19) Form 5 RERA Audit.pdf | 7 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: (19-20) Form 5 RERA Audit.pdf | 7 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: (20-21) Form 5 RERA Audit.PDF | 7 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: (21-22) Form 5 RERA Audit.pdf | 7 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: (22-23) Form 5 RERA Audit.pdf | 7 Oct 2024 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: Format A.pdf | 7 Oct 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A (2).pdf | 7 Oct 2024 |
| Declaration in FORM BFile: Form B (Affidavit cum Declaration).pdf | 7 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Architect Certificate.pdf | 7 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineers Certificate June 2024.pdf | 7 Oct 2024 |
| Certificates of CA (Form 3)File: Form 3 CA Certificate June 2024.pdf | 7 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Circular 29 - Disclosure of Sold Booked Inventory.PDF | 7 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: (19-20) Form 2A - Quality Assurance Certificate.pdf | 7 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: (20-21) Form 2A - Quality Assurance Certificate.pdf | 7 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: (21-22) Form 2A - Quality Assurance Certificate.pdf | 7 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: (22-23) Form 2A - Quality Assurance Certificate.pdf | 7 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: (23-24) Form 2A - Quality Assurance Certificate.pdf | 7 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: (18-19) Form 5 RERA Audit.pdf | 7 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: (19-20) Form 5 RERA Audit.pdf | 7 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: (20-21) Form 5 RERA Audit.PDF | 7 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: (21-22) Form 5 RERA Audit.pdf | 7 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: (22-23) Form 5 RERA Audit.pdf | 7 Oct 2024 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: Format A.pdf | 7 Oct 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A (2).pdf | 7 Oct 2024 |
| Declaration in FORM BFile: Form B (Affidavit cum Declaration).pdf | 7 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Architect Certificate.pdf | 7 Oct 2024 |
| Certificates of CA (Form 3)File: Form 3 CA Certificate June 2024.pdf | 7 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineers Certificate June 2024.pdf | 7 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: (19-20) Form 2A - Quality Assurance Certificate.pdf | 7 Oct 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Raigarh
Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.
Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 170 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Renaissance Royal Phase 1 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Neral5,900+ in Raigarh
Filed coordinates, straight-line distance. 139 registered projects within 2 km.
ForeverLand
HOABL IMPACTUM LAND PRIVATE LIMITED
Chitrapatjanak Dadasaheb Phalke Township - Pha
Anukarati Homes Pvt Ltd
Olympeo Neo City
PRIZTINE INFRA LLP
DEEPJYOTI CITY
DeepJyoti Infra
VISION AARAMBH
M/s Vision Aarambh ( AOP )
Olympeo Riverside - Phase 3
Olympeo Riverside Projects LLP
See every Raigarh project, with the district possession charts
Builder: Shree Sharada Infrastructures
Shree Sharada Infrastructures has 2 registrations on MahaRERA, including Renaissance Royal Phase 1 and RENAISSANCE ROYAL PHASE II. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Raigarh district page.
Frequently asked questions
What are my rights if Renaissance Royal Phase 1 is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Renaissance Royal Phase 1?
The registered promoter entity is Shree Sharada Infrastructures, a partnership as per the filing. Its GSTIN 27ABWFS9545H1Z8 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Renaissance Royal Phase 1?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Renaissance Royal Phase 1?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Renaissance Royal Phase 1?
The professionals named in the filing: Architect: Shree Sthapatya Associates; Engineer: SK Consultants & Engineers; Engineer: Sandeep Dashrath Deshmukh; Chartered Accountant: NB Sayed & Associates; Chartered Accountant: PRANAV BHASKARAN & ASSOCIATES; Chartered Accountant: CAP & CO.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Renaissance Royal Phase 1?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.