Home / Browse projects / Pune, Maharashtra / Raviraj Splendour Greens

Registered No litigation declared Residential / Group Housing project

Raviraj Splendour Greens

By RAVIRAJ SHETH DEVELOPERS LLP

RG-MH-04877 · RERA P52100021159 · Last updated on MahaRERA portal: 26 Jun 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 42 months
  • 2 extensions taken
  • Rs 30.00 crore secured on the land, in favour of BAJAJ HOUSING FINANCE LIMITED

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedmoved 42 months from the original
3 of 33Construction stages doneacross 3 buildings; furthest along: Slabs of Super Structure, 93%
102 of 176Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 139 documents Report an error

Raviraj Splendour Greens is a Residential / Group Housing project by RAVIRAJ SHETH DEVELOPERS LLP in Pune, Maharashtra, registered with MahaRERA as P52100021159 on 14 Jun 2019. Possession is promised by 31 Dec 2027. The completion date has moved by 42 months from the original filing. 74 of the 176 units on this registration are recorded sold or booked, and 3 of 33 construction stages are filed complete.

At a glance

Project

  • NameRaviraj Splendour Greens
  • TypeResidential / Group Housing
  • Location
    • S. No. 7
    • Kondhwa Budruk
    • kondhwa BK
    • Haveli
    • Pune
    • 411048
  • Pincode411048
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100021159
  • ReraGenie IDRG-MH-04877

Builder

  • NameRAVIRAJ SHETH DEVELOPERS LLP
  • Entity typeLimited Liability Partnership
  • LLPINAAY-9230
  • PartnerShilpa Rupesh Sheth

Key dates

this monthRegisteredJun 2019First promiseJun 2024Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on14 Jun 2019
  • Promised completion31 Dec 2027
  • Revised completionRevised to 31 Dec 2027 (originally 30 Jun 2024)
  • Buildings3 building records
  • Documents filed139 files

Current status

42%74 of 176 units booked
38.5%Work done, per cost certificate

Figures as on 26 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
AA8636036
BNA161456056
CNA161484084

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 26 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Slabs of Super Structure, at 93%.

A · wing A29%
ActivityProgress
Excavation100%
Basement (if any)80%
Podiums (if any)0%
Plinth0%
Stilt Floor80%
Slabs of Super Structure40%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises14%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B34%
ActivityProgress
Excavation100%
Basement (if any)80%
Podiums (if any)0%
Plinth0%
Stilt Floor80%
Slabs of Super Structure93%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises18%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
C34%
ActivityProgress
Excavation100%
Basement (if any)80%
Podiums (if any)0%
Plinth0%
Stilt Floor80%
Slabs of Super Structure93%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises20%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 26 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed743

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots743
Closed/Covered743
BuildingClosed/CoveredTotal
A A167167
B185185
C391391

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area7,800 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofBAJAJ HOUSING FINANCE LIMITED
Secured amountRs 30.00 crore
CERSAI search filedYes
Declared on2 Feb 2026

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI14412.27
Proposed, not sanctioned14,412 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPB No 7, Near Di Chi Company, Kasarwadi, Pune 411 034
Estimated costRs 59.98 cr
Cost incurredRs 23.11 cr
Work done38.53%
BuildingWingEstimatedIncurred
AARs 17.99 crRs 5.04 cr
BNARs 17.99 crRs 5.22 cr
CNARs 17.99 crRs 12.54 cr
-NARs 6.00 crRs 31.49 lakh

Certifying professionals and partners9

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAnil S Saykar
EngineerHemant Khandelwal
EngineerSantosh Katare
EngineerMahadev Todkar
Chartered AccountantOswal NAHAR&CO
Chartered AccountantAgarwal Sarawgi and Associates
Chartered AccountantPatel & Sharma
Chartered AccountantMr dharod and Co
Chartered AccountantSajan Bogawat & Associates
PartnerRole in project
RAVIRAJ SHETH DEVELOPERS LLP-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100010744Jun 2024 → Dec 2026

Reason as filed by the promoterThe construction of the project is delayed due to the outbrake of COVID 19 pandemic in India. Maharashtra being the most affected state and Pune being one of the worst affected cities, labour were not available due migration. Hence the construction activity had to be stopped. The construction work has just recently commenced.

EA24032620354Jun 2024 → Dec 2027

Reason as filed by the promoterWe would like to submit that the construction schedule of the project has been significantly impacted due to various genuine and unavoidable circumstances beyond the control of the promoter. These factors have cumulatively led to delays in the timely execution of the project as originally planned. The key reasons are detailed below: Disruption in Supply Chain and Delay in Procurement of Construction Materials: One of the primary causes of delay has been the disruption in the supply chain of essential construction materials such as cement, steel, sand, aggregates, plumbing components, electrica

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 7 May 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 25 Feb 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 25 Feb 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 1 Sep 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed139

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 139 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 1 Splendour Greens Mar 26.pdf26 Jun 2026
Withdrawal Update Form 2File: FORM 2 Mar 26.pdf26 Jun 2026
Withdrawal Update Form 3File: 00 Form 3 RaviSplGreen Compressed.pdf26 Jun 2026
Withdrawal Update Form 1File: FORM 1 Splendour Greens Mar 26.pdf25 Apr 2026
Withdrawal Update Form 2File: FORM 2 Mar 26.pdf25 Apr 2026
Withdrawal Update Form 3File: FORM 3 CA Mar 26.pdf25 Apr 2026
Building plan approvalFile: Wing A 2-6.pdf25 Feb 2026
Layout approvalFile: Layout_rotated Compressed Highlighted.pdf25 Feb 2026
Building plan approvalFile: Wing A 2-6.pdf25 Feb 2026
Building plan approvalFile: 3-6 Bwing.pdf25 Feb 2026
Building plan approvalFile: 4-6 B Wing Elevation.pdf25 Feb 2026
Building plan approvalFile: 5-6 C Wing.pdf25 Feb 2026
Building plan approvalFile: 6-6 Scan_20250123_141651.pdf25 Feb 2026
Building plan approvalFile: Layout_rotated Compressed Highlighted.pdf21 Feb 2026
Withdrawal Update Form 1File: FORM 1 SPLENDOUR GREENS.pdf3 Feb 2026
Withdrawal Update Form 2File: FORM 2 SPLENDOUR GREENS.pdf3 Feb 2026
Withdrawal Update Form 3File: FORM 3 SPLENDOUR GREENS.pdf3 Feb 2026
Layout approvalFile: Layout Plan.pdf13 Jan 2026
Form 2A (FY 2019-2020)File: FOrm 2 A Mar 22.pdf6 Nov 2025
Form 2A (FY 2020-2021)File: FOrm 2 A Mar 22.pdf6 Nov 2025
Form 2A (FY 2021-2022)File: FOrm 2 A Mar 22.pdf6 Nov 2025
Form 2A (FY 2022-2023)File: FORM 2A - MARCH 2023.pdf6 Nov 2025
Form 2A (FY 2023-2024)File: FORM 2A - MARCH 2024.PDF6 Nov 2025
Form 2A (FY 2024-2025)File: FORM 2A - MARCH 2025.PDF6 Nov 2025
Form 5 (FY 2019-2020)File: Form5 20-21.pdf6 Nov 2025
Form 5 (FY 2021-2022)File: Form5 21-22.pdf6 Nov 2025
Form 5 (FY 2022-2023)File: FOrm 3 22-23.pdf6 Nov 2025
Form 5 (FY 2024-2025)File: FORM 5 - FY- 24-25.PDF5 Nov 2025
Form 5 (FY 2023-2024)File: Form 5 23-24.pdf5 Nov 2025
Withdrawal Update Form 1File: FORM 1 - Ar CERTIFICATE - 30092025 - SG.PDF1 Nov 2025
Withdrawal Update Form 2File: FORM 2 - ENGINEERS CERTIFICATE - 30092025 - SG.PDF1 Nov 2025
Withdrawal Update Form 3File: FORM 3 - CA CERTIFICATE - 30092025 - SG.PDF1 Nov 2025
Withdrawal Update Form 1File: 17 June2025 - FORM 1.PDF10 Oct 2025
Withdrawal Update Form 2File: 17 June2025- ENGINEERS CERTIFICATE.PDF10 Oct 2025
Withdrawal Update Form 3File: 17 June2025- CA CERTIFICATE.PDF10 Oct 2025
Form 5 (FY 2020-2021)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21).pdf16 Aug 2025
Form 1File: 1 30062021 - FORM 1.PDF4 Aug 2025
Form 2File: 1 JUne 21- ENGINEERS CERTIFICATE.PDF4 Aug 2025
Form 3File: 1 June2021- CA CERTIFICATE.PDF4 Aug 2025
Disclosure of Sold and Booked InventoryFile: 1 SOLD UNSOLD - June21.PDF4 Aug 2025
Form 1File: 2 30092021 - FORM 1.PDF4 Aug 2025
Form 2File: 2 Sep 21 ENGINEERS CERTIFICATE.PDF4 Aug 2025
Form 3File: 2 Sep2021- CA CERTIFICATE.PDF4 Aug 2025
Disclosure of Sold and Booked InventoryFile: 2 SOLD UNSOLD - Sep2021.PDF4 Aug 2025
Form 1File: 3 Dec 21 Form 1.PDF4 Aug 2025
Form 2File: 3 Dec 21 ENGINEERS CERTIFICATE.PDF4 Aug 2025
Form 3File: 3 Dec2021- CA CERTIFICATE.PDF4 Aug 2025
Disclosure of Sold and Booked InventoryFile: 3 SOLD UNSOL - Dec2021.PDF4 Aug 2025
Form 1File: 4 Mar2022 - FORM 1.PDF4 Aug 2025
Form 3File: 4 Mar2022- CA CERTIFICATE.PDF4 Aug 2025
Form 2File: 4 Mar2022- ENGINEERS CERTIFICATE.PDF4 Aug 2025
Disclosure of Sold and Booked InventoryFile: 4 SOLD UNSOLD - Mar2022.PDF4 Aug 2025
Form 1File: 5 June2022- FORM 1.PDF4 Aug 2025
Form 2File: 5 June2022- ENGINEERS CERTIFICATE.PDF4 Aug 2025
Disclosure of Sold and Booked InventoryFile: 5 SOLD UNSOLD - June2022.PDF4 Aug 2025
Form 3File: 5 June2022- CA CERTIFICATE.PDF4 Aug 2025
Form 1File: 6 Sep2022 - FORM 1.PDF4 Aug 2025
Form 2File: 6 Sep2022- ENGINEERS CERTIFICATE.PDF4 Aug 2025
Form 3File: 6 Sep2022- CA CERTIFICATE.PDF4 Aug 2025
Disclosure of Sold and Booked InventoryFile: 6 SOLD UNSOLD - Sep2022.PDF4 Aug 2025
Form 1File: 7 Dec2022 - FORM 1.PDF4 Aug 2025
Form 2File: 7 Dec2022- ENGINEERS CERTIFICATE.PDF4 Aug 2025
Form 3File: 7 Dec2022- CA CERTIFICATE.PDF4 Aug 2025
Disclosure of Sold and Booked InventoryFile: 7 SOLD UNSOLD - Dec2022.PDF4 Aug 2025
Form 1File: 8 Mar2023- FORM 1.PDF4 Aug 2025
Form 2File: 8 Mar2023- ENGINEERS CERTIFICATE.PDF4 Aug 2025
Form 3File: 8 Mar2023- CA CERTIFICATE.PDF4 Aug 2025
Disclosure of Sold and Booked InventoryFile: 8 SOLD UNSOLD - Mar2023.PDF4 Aug 2025
Form 1File: 9 June2023 - FORM 1.PDF4 Aug 2025
Form 3File: 9 June2023- CA CERTIFICATE.PDF4 Aug 2025
Form 2File: 9 June2023- ENGINEERS CERTIFICATE.PDF4 Aug 2025
Disclosure of Sold and Booked InventoryFile: 9 SOLD UNSOLD - June2023.PDF4 Aug 2025
Form 1File: 10 Sep2023 - FORM 1.PDF4 Aug 2025
Form 2File: 10 Sep2023- ENGINEERS CERTIFICATE.PDF4 Aug 2025
Form 3File: 10 Sep2023- CA CERTIFICATE.PDF4 Aug 2025
Disclosure of Sold and Booked InventoryFile: 10 SOLD UNSOLD - Sep2023.PDF4 Aug 2025
Form 1File: 11 Dec2023 -FORM 1.PDF4 Aug 2025
Form 2File: 11 Dec2023- ENGINEERS CERTIFICATE.PDF4 Aug 2025
Form 3File: 11 Dec2023- CA CERTIFICATE.PDF4 Aug 2025
Disclosure of Sold and Booked InventoryFile: 11 SOLD UNSOLD - Dec2023.PDF4 Aug 2025

How this compares with Pune

42%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 42 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Raviraj Splendour Greens on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kondhwa Budruk13,700+ in Pune

2 kmRaviraj Splendour GreensCompleted 66Lapsed / revoked 42Other 55Dot size: filed unitsN

Filed coordinates, straight-line distance. 163 registered projects within 2 km.

Builder: RAVIRAJ SHETH DEVELOPERS LLP

RAVIRAJ SHETH DEVELOPERS LLP has 1 registration on MahaRERA, including Raviraj Splendour Greens. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Raviraj Splendour Greens is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Raviraj Splendour Greens?

The registered promoter entity is RAVIRAJ SHETH DEVELOPERS LLP, a limited liability partnership as per the filing. Its LLPIN AAY-9230 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Raviraj Splendour Greens?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Raviraj Splendour Greens?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Raviraj Splendour Greens?

The professionals named in the filing: Architect: Anil S Saykar; Engineer: Hemant Khandelwal; Engineer: Santosh Katare; Engineer: Mahadev Todkar; Chartered Accountant: Oswal NAHAR&CO; Chartered Accountant: Agarwal Sarawgi and Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Raviraj Splendour Greens?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Raviraj Splendour Greens. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Raviraj Splendour Greens to a free account