Home / Browse projects / Thane, Maharashtra / RAUNAK CITY SECTOR VI - F1
RAUNAK CITY SECTOR VI - F1
RG-MH-86264 · RERA P51700033762 · Last updated on MahaRERA portal: 11 Jun 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- All 12 earlier projects delivered on promise
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 14 other registrations and every project registered within 2 km.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
RAUNAK CITY SECTOR VI - F1 is a Residential / Group Housing project by RAUNAK CORPORATION in Thane, Maharashtra, registered with MahaRERA as P51700033762 on 8 Mar 2022. Possession is promised by 31 Dec 2028. 126 of the 182 units on this registration are recorded sold or booked, and 8 of 11 construction stages are filed complete.
At a glance
Project
- NameRAUNAK CITY SECTOR VI - F1
- TypeResidential / Group Housing
- Location
- RAUNAK CITY ROAD
- KALYAN W
- adharwadi
- Kalyan
- Thane
- 421301
- Pincode421301
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700033762
- ReraGenie IDRG-MH-86264
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on8 Mar 2022
- Promised completion31 Dec 2028
- Revised completionNone
- Buildings1 building record
- Documents filed60 files
Current status
Figures as on 11 Jun 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| RAUNAK CITY SECTOR VI - F1 | NA | 32 | 31 | 175 | 7 | 182 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 11 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
8 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 50%.
RAUNAK CITY SECTOR VI - F1: 79% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 50% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 20% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 11 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 50% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| RAUNAK CITY SECTOR VI - F1 | NA | Rs 42.00 cr | Rs 18.96 cr |
| - | NA | Rs 3.00 cr | - |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | MANGESH RANE |
| Engineer | RAJAN TIPNIS |
| Engineer | HARSHAL MANOHARRAO POTODE |
| Chartered Accountant | ANKIT GOYANKA |
| Chartered Accountant | SANDEEP SHETH |
| Partner | Role in project |
|---|---|
| RAUNAK CORPORATION | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 3 Mar 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 3 Mar 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 21 Feb 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 21 Feb 2025Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2028
Documents filed60
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2A (FY 2025-2026)File: Form 2A F1 RC.pdf | 11 Jun 2026 |
| Withdrawal Update Form 1File: Withdrawal Application Form1 F1.pdf | 7 May 2026 |
| Withdrawal Update Form 1File: Withdrawal Application Form1 F1.pdf | 7 May 2026 |
| Withdrawal Update Form 2File: Withdrawal Application Form 2 F1.pdf | 7 May 2026 |
| Withdrawal Update Form 2File: Withdrawal Application Form 2 F1.pdf | 7 May 2026 |
| Withdrawal Update Form 3File: CA Certificate Raunak City Sector VI F1 31032026.pdf | 7 May 2026 |
| Withdrawal Update Form 3File: CA Certificate Raunak City Sector VI F1 31032026.pdf | 7 May 2026 |
| Withdrawal Update Form 1File: Withdrawal Application Form1 F1.pdf | 4 May 2026 |
| Withdrawal Update Form 2File: Withdrawal Application Form 2 F1.pdf | 4 May 2026 |
| Withdrawal Update Form 3File: CA Certificate Raunak City Sector VI F1 31032026.pdf | 4 May 2026 |
| Withdrawal Update Form 1File: Form 1 Raunak City Sec VI F1Dec 25.pdf | 12 Feb 2026 |
| Withdrawal Update Form 2File: Form2 F1.pdf | 12 Feb 2026 |
| Withdrawal Update Form 3File: CA Certificate Raunak City Sector VI F1 31122025.pdf | 12 Feb 2026 |
| Withdrawal Update Form 1File: Form 1 F1.pdf | 20 Nov 2025 |
| Withdrawal Update Form 2File: Form2 F1.pdf | 20 Nov 2025 |
| Withdrawal Update Form 3File: CA Certificate Raunak City Sector VI F1 30092025.pdf | 20 Nov 2025 |
| Form 5 (FY 2024-2025)File: Raunak City Sector VI - F1.pdf | 3 Nov 2025 |
| Withdrawal Update Form 1File: AC_Sector VI-F1.pdf | 13 Oct 2025 |
| Withdrawal Update Form 1File: Raunak city Certificate F1.pdf | 13 Oct 2025 |
| Withdrawal Update Form 2File: Raunak City F1 Form 2.pdf | 13 Oct 2025 |
| Withdrawal Update Form 2File: Raunak City F1 Form 2.pdf | 13 Oct 2025 |
| Withdrawal Update Form 3File: CA Certificate Raunak City Secc VI F1 30062025.pdf | 13 Oct 2025 |
| Withdrawal Update Form 3File: CA Certificate Raunak City Secc VI F1 30062025.pdf | 13 Oct 2025 |
| Form 2A (FY 2024-2025)File: Form 2A RC F1.pdf | 13 Oct 2025 |
| Form 1File: Form 1 F1 31032025.pdf | 1 Jul 2025 |
| Form 2File: Form 2 Engineer Certificate F1.pdf | 1 Jul 2025 |
| Form 3File: CA Certificate Raunak City Sector VI F1 31032025.pdf | 1 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: F1 31032025.pdf | 1 Jul 2025 |
| Commencement Certificates / NA Order for plotted developmentFile: Raunak City Sec IV and Sec VI CC 30-06-2022.pdf | 21 Feb 2025 |
| Declaration about Commencement CertificateFile: F1.pdf | 21 Feb 2025 |
| Details of encumbrancesFile: Financial Encumbarane RC ICICI.pdf | 10 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 F1 311224.pdf | 10 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Signed CA Certificate Raunak City Sector VI F1 31122024.pdf | 10 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer's Certificate Raunak City Sctor VI F1 311224.pdf | 10 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: Raunak City VI 31122024 F1.pdf | 10 Feb 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: F1.pdf | 29 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 7_Form-2A-RC-F1.pdf | 2 Jul 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form5_Rcity_F1.pdf | 23 Nov 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Raunak City Sec VI F1 Form 2A 2023.pdf | 4 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: EC_RC VI-F1.pdf | 20 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AC_Sector VI-F1.pdf | 7 Feb 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: EC_Raunak City Sector VI.pdf | 7 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form5_RC_F1_2021-22.pdf | 7 Feb 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: RC_VI_F1_22.pdf | 2 May 2022 |
| Layout approvalFile: LEY-OUT_F1.pdf | 3 Mar 2022 |
| Copy of the legal title reportFile: Title-Certificate - RC-VI-1.pdf | 3 Mar 2022 |
| Copy of the legal title reportFile: Title-Certificate - RC-VI-2.pdf | 3 Mar 2022 |
| Details of encumbrancesFile: Encumbrance Certificate-F1.pdf | 3 Mar 2022 |
| Copy of Layout Approval (in case of layout)File: LEY-OUT_F1.pdf | 3 Mar 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE F1_compressed.pdf | 3 Mar 2022 |
| Proforma of Allotment letterFile: FSA-Sect-VI-F1 220222 Rera.pdf | 2 Mar 2022 |
| PAN CardFile: Raunak Corporation PAN Copy_compressed.pdf | 23 Feb 2022 |
| CERSAI detailsFile: CERSAI_Assets-Based.pdf | 23 Feb 2022 |
| Building plan approvalFile: F1 Building Plan_compressed.pdf | 21 Feb 2022 |
| Copy of the legal title reportFile: 1 Copy of the legal title report (1).pdf | 21 Feb 2022 |
| Details of encumbrancesFile: Encumbrance details.pdf | 21 Feb 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: F1 Building Plan_compressed.pdf | 21 Feb 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: F1 F2 F3 CC.pdf | 21 Feb 2022 |
| Declaration about Commencement CertificateFile: Declaration of CC F1.pdf | 21 Feb 2022 |
| Declaration in FORM BFile: Form B - F1_compressed.pdf | 21 Feb 2022 |
Promoter's earlier projects12
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| RAUNAK CITY SECTOR IV - D9P51700017488 | Near Adharwadi Jail, Don Bosco School, Thane | - | Aug 2018 | Completed | Dec 2027 | Jul 2021 |
| RAUNAK CITY SECTOR IV - D6P51700020261 | KALYAN WEST, Thane | - | Mar 2019 | Completed | Dec 2027 | Jul 2024 |
| RAUNAK CITY SECTOR IV - D7P51700020241 | KALYAN WEST, Thane | - | Mar 2019 | Completed | Jun 2026 | Jul 2024 |
| RAUNAK CITY SECTOR IV - D5P51700020240 | KALYAN WEST, Thane | - | Mar 2019 | Completed | Jun 2026 | Jul 2024 |
| RAUNAK CITY SECTOR IV - D8P51700020182 | KALYAN WEST, Thane | - | Mar 2019 | Completed | Dec 2025 | Jul 2024 |
| RAUNAK CITY SECTOR IV - D2P51700003210 | KALYAN, Thane | - | Aug 2017 | Completed | Dec 2025 | Mar 2018 |
| RAUNAK CITY SECTOR IV - D10P51700009331 | KALYAN WEST, Thane | - | Aug 2017 | Completed | Dec 2025 | Jul 2019 |
| RAUNAK CITY SECTOR IV - D1P51700003377 | KALYAN, Thane | - | Aug 2017 | Completed | Dec 2025 | Mar 2018 |
| RAUNAK CITY SECTOR IV - D4P51700019962 | KALYAN WEST, Thane | - | Mar 2019 | Completed | Jun 2025 | Jun 2023 |
| RAUNAK CITY SECTOR IV - D3P51700019790 | KALYAN WEST, Thane | - | Mar 2019 | Completed | Dec 2024 | Jun 2023 |
| RAUNAK CITY SECTOR III | RAUNAK CITY VILLEGE WADEGHR NEAR DON BOSCO SCHOOL ADHAR WADI JAIL ROAD KALYAN WEST 421301 | 669 | - | Completed | Dec 2017 | Jul 2017 |
| RAUNAK CITY SECTOR II | RAUNAK CITY VILLEGE WADEGHR NEAR DON BOSCO SCHOOL ADHAR WADI JAIL ROAD KALYAN WEST 421301 | 758 | - | Completed | Dec 2015 | Dec 2015 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 14 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 60 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep RAUNAK CITY SECTOR VI - F1 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near KALYAN W7,600+ in Thane
Filed coordinates, straight-line distance. 136 registered projects within 2 km.
PODDAR RIVIERA PHASE - I
Poddar Housing and Development Limited
Sinhagad by Bhagwati Haware - Wing - B
Bhagwati Haware Properties Supertech
Pratapgad by Bhagwati Haware - Wing - C
Bhagwati Haware Properties Supertech
Rajgad by Bhagwati Haware - Wing - D
Bhagwati Haware Properties Supertech
PODDAR RIVIERA PHASE - III
Poddar Housing and Development Limited
THARWANI PARKGLEN PHASE I
THARWANI REALTORS
See every Thane project, with the district possession charts
Builder: RAUNAK CORPORATION
RAUNAK CORPORATION has 15 registrations on MahaRERA, including RAUNAK CITY SECTOR IV - D10 and RAUNAK CITY SECTOR IV - D1. Its filings disclose 12 earlier MahaRERA projects: declares 12 of 12 past projects completed on time. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What are my rights if RAUNAK CITY SECTOR VI - F1 is delayed beyond 31 Dec 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of RAUNAK CITY SECTOR VI - F1?
The registered promoter entity is RAUNAK CORPORATION, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in RAUNAK CITY SECTOR VI - F1?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for RAUNAK CITY SECTOR VI - F1?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at RAUNAK CITY SECTOR VI - F1?
The professionals named in the filing: Architect: MANGESH RANE; Engineer: RAJAN TIPNIS; Engineer: HARSHAL MANOHARRAO POTODE; Chartered Accountant: ANKIT GOYANKA; Chartered Accountant: SANDEEP SHETH. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in RAUNAK CITY SECTOR VI - F1?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback